Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Pioneer Hydrothermal ... vs M/S. Techsharp Engineers Pvt.Ltd
2022 Latest Caselaw 5987 Mad

Citation : 2022 Latest Caselaw 5987 Mad
Judgement Date : 24 March, 2022

Madras High Court
M/S.Pioneer Hydrothermal ... vs M/S. Techsharp Engineers Pvt.Ltd on 24 March, 2022
                                                                          C.M.A.No.84 of 2022

                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                               DATED: 24.03.2022

                                                   CORAM:

                                     THE HONOURABLE Ms. JUSTICE P.T.ASHA

                                              C.M.A.No.84 of 2022

                  M/s.Pioneer Hydrothermal Services Pvt.Ltd.,
                  Pioneer House, 3-10-4/B/2,
                  Near St.Joseph's High School,
                  Ramanthapur, Hyderabad- 500 013,
                  Represented by its Director and Authorized Signatory,
                  Konghot Krishn Prasad,
                  Residing at Flat No.E-304, 3rd Floor,
                  Aparna Sarovar Granda, Kanchi Gachibowli,
                  Nallagandia, Lingampally,
                  K.V.Rangareddy, Hyderabad – 500 013                       ... Appellant

                                                      vs.

                  1. M/s. Techsharp Engineers Pvt.Ltd.,
                     Represented by its Authorized Officer,
                     C-39, 2nd Avenue, Anna Nagar,
                     Chennai 600 040,
                     presently having Office at
                     No.10/17, 8th Street, M-Block, Anna Nagar East,
                     Chennai 600 102.

                  2. M/s.Bharath Petroleum Corporation Limited (BPCL),
                     Kochi Refinery,
                     Karimughal Road, Thrippunithura,
                     Ambalamugal, Kochi, Kerala – 682 302                 ... Respondents




                  1/14
https://www.mhc.tn.gov.in/judis
                                                                                C.M.A.No.84 of 2022

                  PRAYER: Civil Miscellaneous Appeal filed under Section 37 of the
                  Arbitration and Conciliation Act, 1996 praying to set aside the order dated
                  07.01.2021 passed by the learned Arbitrator which had arisen out of the
                  dispute between the Appellant and the respondents and thereby passing an
                  Award directing the first respondent to pay the costs of the petition.
                                  For Appellant               : Mr.Vipin Warrier
                                                                for M/s.Indian Law LLP

                                  For Respondent-1            : Mr.Jayesh B.Dolia

                                  For Respondent-2            : Mr.M.Vijayan


                                                      JUDGMENT

Aggrieved by the Order dated 07.01.2021 passed by the Arbitral

Tribunal in allowing an application filed under Section 16 of the

Arbitration and Conciliation Act, 1996, the claimant is before this Court.

2. Since the issue, which has been placed for consideration of

this Court is with reference to the correctness of the order passed in a

Section 16 application, I do not intend to traverse through the entire

pleadings of the parties. Suffice it to state that the appellant herein, who is

a Sub Contractor of the first respondent herein, has a dispute with the first

respondent, for which, they have invoked the Arbitration Clause contained

https://www.mhc.tn.gov.in/judis C.M.A.No.84 of 2022

in the work order that was issued by the first respondent to the claimant /

appellant herein. The work order that has been issued is for the Supply and

application of Insulation of Piping system on back to back basis for offsite

(Part-A) of IREP Project of BPCL, Kochi Refiner. The second respondent

has engaged the services of the first respondent, who in turn, has engaged

the services of the appellant. The appellant would contend that though they

had completed their work, the first respondent had not cleared the bills and

therefore, they had raised a dispute and requested the first respondent to

appoint an Arbitrator. However, the request was not considered favourably

by the first respondent, which compelled the appellant to file a petition in

O.P.No.688 of 2019 under Section 11 of the Arbitration and Conciliation

Act, 1996 (hereinafter, for the sake of brevity, referred to as "the 1996

Act") before this Court. In O.P.No.688 of 2019, by order dated 18.11.2019,

this Court was pleased to appoint an Arbitrator.

3. The appellant had filed their claim statement before the learned

Arbitrator and after the first respondent had entered appearance before the

learned Arbitrator instead of filing their defense statement, they had taken

out an application under Section 16 of the Arbitration and Conciliation Act,

https://www.mhc.tn.gov.in/judis C.M.A.No.84 of 2022

which is impugned in this appeal. The application was filed stating that the

claim had to be terminated, since the cause of action for the claimant to file

the claim is pre-mature. The grounds, on which the application has been

filed by the first respondent, has been set out in paragraphs 10 and 11 of the

affidavit filed in support of the said impugned application.

4. The appellant has filed a counter before the Arbitral Tribunal ,

denying that the allegations and disputing that the contract is back to back

in nature. They had countered the allegations by stating that the first

respondent herein is a chronic defaulter and that the bills were never paid

on time. The appellant had also contended that for every RA Bill (Running

Account Bill), 10% had been retained by the first respondent. The

appellant would submit that they had completed their part of the work and

despite the second respondent clearing the Bank Guarantee issued by the

first respondent, payments have not been made to the appellant. The

appellant had also submitted that they had information that the first

respondent had received substantial payments, which they have diverted

elsewhere.

https://www.mhc.tn.gov.in/judis C.M.A.No.84 of 2022

5. Considering the fact that there was a valid dispute between

the parties, the contention that there is no cause of action, is absolutely

without any basis. However, the learned Arbitrator relying upon Clause

10.3 of the Work Order, concluded that the appellant's cause of action for

claiming payments would arise, only after release of the final payments by

the second respondent to the first respondent. The claim of the appellant

herein would fructify only then and till such time, there is no cause of

action for invoking the arbitration clause. The Arbitral Tribunal therefore

held that it could not continue, when there is no dispute. The learned

Arbitrator allowed the application and consequently, the arbitration

proceedings were terminated. Aggrieved by the same, the appellant is

before this Court.

6. Mr.Vipin Warrier, learned counsel appearing for the appellant

would draw the attention of the Court to Clause 10.3, which is the basis on

which, the application has been allowed. He would submit that the learned

Arbitrator has not considered Clause 10.4, which gives the payment break-

up and the various stage of payment. It is his contention that, as per Clause

10.3, it is only the final payment that is considered which is clear from

https://www.mhc.tn.gov.in/judis C.M.A.No.84 of 2022

reading Clause 10.4, which gives the payment break-up. Under Clause

10.4, the final payment that constituted 5% was to be kept back and 95% of

the payment had to be cleared. Therefore, the contention that the appellant

did not have the cause of action for filing the claim, is totally misconceived

and without any basis. He would further argue that the learned Arbitrator

had allowed Section 16 application only on the ground that the first

respondent had not received their final payment from the second respondent

and that the liability to pay had therefore, not fructified. However, in the

counter filed to the Section 9 application in Arb.Appl.180 of 2021, the first

respondent stated that they had submitted their final bill to the second

respondent as early as on 21.03.2019 and the amount that was due, was

only a sum of Rs.5,15,37,000/-. In fact, the second respondent herein had

submitted that they were willing to create a Fixed Deposit in respect of the

sum of Rs.4,00,37,000/-, which according to them, was due to the first

respondent. Therefore, he would contend that the statement that the final

payment has not been paid, would be totally incorrect, in the light of the

statement made in Section 9 application.

https://www.mhc.tn.gov.in/judis C.M.A.No.84 of 2022

7. Per contra, Mr.Jayesh B.Dolia, learned counsel appearing for

first respondent would contend that the final payment, as per Clause 10.3,

was payable only after the payments were fully received from the second

respondent and admittedly, till date, the payments have not been made

available to the first respondent. Therefore, the liability to pay the

appellant, has not arisen. He would submit that the provisions of Clause

10.4 would have no application to the instant case. He would therefore

pray that the order of the learned sole Arbitrator be confirmed.

8. Mr.M.Vijayan, learned counsel appearing on behalf of the

second respondent-Corporation would submit that they are unnecessary

parties to the proceedings. The Arbitration contract is only between the

appellant and the first respondent and the second respondent is not a party

to the same. Therefore, the presence of the second respondent in the

proceedings, is totally unnecessary.

9. The learned counsel for the appellant would submit that

second respondent-Corporation has been made a party only for the purpose

of confirming as to whether the second respondent had made payments to

https://www.mhc.tn.gov.in/judis C.M.A.No.84 of 2022

the first respondent.

10. Heard the learned counsels on either side and perused the

materials available on record.

11. The issue is in a narrow compass as to whether the appellant

could claim their payment from the first respondent. A perusal of the

documents would indicate that on 05.02.2018, the appellant herein had

issued a legal notice to the first respondent, demanding the final payment.

In the said notice, the appellant has stated as follows:

“We are told that the Company has paid an amount of Rs.7,72,90,718/- in various installments dated from 14.07.2016 to 22.09.2017 as part payments so far to our client. The last part payment from the side of your company was Rs.30 lacs on 22.09.2017. Now an amount of Rs.6,62,17,343/- (Rupees six crore sixty two lacs seventeen thousand three hundred and forty three only) is outstanding after deduction of statutory recoveries.

Despite repeated reminders, e-mail and direct communication made by the representatives of our client, the Company did not paid the outstanding amount due to our client.”

https://www.mhc.tn.gov.in/judis C.M.A.No.84 of 2022

The total value of the work order has been set out in the Annexure to the

work order under the caption " Schedule of Rates". In the legal notice, the

first respondent was also informed that, if payments were not received, the

appellant would be constrained to take the legal re-course. In response to

the above legal notice, a reply has been sent on 01.03.2018, wherein, the

first respondent had denied their liability on the ground that the invoices

that had been forwarded, had not been certified on the basis of

measurement sheet, documents and other parameters and that the debris at

the site had not been cleared to the satisfaction of the first respondent. The

reply also set out that the appellant had not addressed the issue of the delay.

The first respondent had not raised the plea that the claim was pre-mature.

Neither in their response to the Arbitration notice nor in the Section 11

petition, had this plea been raised by the first respondent.

12. Clause 10.3, on which, the first respondent has based its

claim would read as follows:-.

“10.3: All RA Bill payments shall be regarded as payment on account / advance against final payment and not as value of work done. On satisfactory completion of work and issue of taking over certificate and release of final

https://www.mhc.tn.gov.in/judis C.M.A.No.84 of 2022

payment of Client, Sub Contractor will be paid the total amount due after deduction of any liquidated damages due under Contract, less payment already made and any other recoveries due from the Sub-Contractor.”

In fact, Section 10.3 falls under the headings “Terms of payment”.

13. It is necessary to also consider Clause 10.4 as well as 10.5,

which reads as follows:

10.4 Payment break ups:-

40% progressive payment after receipt of materials at site.

55% after Installation in all respect. 5% after completion of work in all respects and acceptance thereof and submission of all final documents.

10.5 Retention amount:

10% retention amount would be withheld against all RA Bills 5% of which would be released on successful completion, handing over to Client, material reconciliation and upon receipt of final payment from Client by Company. Balance 5% shall be released upon completion of 'defect liability period" as

https://www.mhc.tn.gov.in/judis C.M.A.No.84 of 2022

per Clause No.2.2.

Contrary to the same, Sub-Contractor may exercise the option of submitting a Bank Guarantee to the tune of % amount of the Work order to be valid covering 'defect liability period' and in such case Company shall release 5% payment upon receipt of BG.

14. From a reading of Clause 10.4, it is seen that the schedule of

payment has been prescribed therein. The first two schedule of payments is

contemplated while the work is in progress it is only the final payment

which is contemporaneous to the final payment being received by the first

respondent from the second respondent. The final payment, which is only

5%, is the amount, which is payable, after completion of work in all

respects and acceptance thereof and on submission of all final documents.

Therefore, Clause 10.3 has to be read in conjunction with Clause 10.4 and

not in isolation, since a reading of 10.3 in isolation will give no meaning to

Clause 10.4.

15. The learned counsel for the first respondent had raised a plea

that the appellant / claimant had not completed the works satisfactorily.

https://www.mhc.tn.gov.in/judis C.M.A.No.84 of 2022

This is an issue, which has to be considered during the enquiry before the

Arbitral proceedings and not at this preliminary stage. What is now placed

for the consideration of this Court is whether the appellant has a cause of

action for institution of Arbitral proceedings, which this Court holds is

available for the appellant.

16. Considering the responses to the earlier notices and Section

11 petition and also taking into account Clause 10.3 and Clause 10.4, the

appellant definitely has a cause of action for instituting the Arbitral

proceedings. Therefore, the observation of the Arbitral Tribunal that the

payment to the appellant is dependent on payment of monies by the second

respondent to the first respondent, is not in keeping with the terms of the

Work Order as also the observations that the claim is pre-mature. It is only

the final tranche, which is linked to the payment received by the first

respondent from the second respondent.

17. Therefore, the order of the Arbitral Tribunal, dated

07.01.2021 is set aside and the matter is remitted back to the Arbitral

Tribunal for consideration. Considering the fact that the term of the

https://www.mhc.tn.gov.in/judis C.M.A.No.84 of 2022

Arbitral Tribunal has come to an end, the term of the Arbitral Tribunal is

extended by a further period of 6 months (i.e), till 27.10.2022.

Accordingly, the Civil Miscellaneous Appeal is allowed. No costs.

24.03.2022 Index : Yes/No Speaking / Non-speaking order srn

To

M/s.Bharath Petroleum Corporation Limited (BPCL), Kochi Refinery, Karimughal Road, Thrippunithura, Ambalamugal, Kochi, Keral – 682 302

https://www.mhc.tn.gov.in/judis C.M.A.No.84 of 2022

P.T.ASHA, J.,

srn

C.M.A.No.84 of 2022

24.03.2022

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter