Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Superintending Engineer vs R.Rajendran
2022 Latest Caselaw 4887 Mad

Citation : 2022 Latest Caselaw 4887 Mad
Judgement Date : 11 March, 2022

Madras High Court
The Superintending Engineer vs R.Rajendran on 11 March, 2022
                                                                                  S.A.(MD)No.535 of 2010


                          BEFORE THE MADURAI BENCH OF MADRAS HIGH COURT

                                                   DATED : 11.03.2022

                                                        CORAM

                            THE HONOURABLE MR.JUSTICE G.R.SWAMINATHAN

                                               S.A.(MD)No.535 of 2010

                1.The Superintending Engineer,
                  Tamil Nadu Electricity Board,
                  Thanjavur.

                2.The Junior Electrical Engineer (O & M),
                  Tamil Nadu Electricity Board,
                  Nadimuthu Nagar,
                  Pattukkottai.                                              ... Appellants

                                                          Vs.
                R.Rajendran                                                  ... Respondent


                Prayer : Second Appeal filed under Section 100 of Civil Procedure Code,

                against the judgment and decree made in A.S.No.4 of 2008 dated 29.09.2009 on

                the file of the Principal District Judge, Thanjavur, reversing the judgment and

                decree made in O.S.No.16 of 2006 dated 12.12.2007 on the file of the Sub

                Court, Pattukkottai.


                                  For Appellants    : Mr.B.Ramanathan,
                                                         Standing Counsel.

                                  For Respondent : Mr.K.K.Ramakrishnan

https://www.mhc.tn.gov.in/judis
                1/8
                                                                                 S.A.(MD)No.535 of 2010




                                                    JUDGMENT

The Tamilnadu Electricity Board is the appellant in this second appeal.

The respondent herein filed O.S.No.16 of 2006 before the Sub Court,

Pattukottai for forbearing the appellants herein from effecting disconnection of

the electricity supply till the resolution of the dispute raised by him.

2.The plaintiff examined himself as P.W.1 and one other witness as P.W.2

and Exs.A1 to A16 were marked. On the side of TNEB, three officials were

examined as defence witnesses and Exs.B1 to B6 were marked.

3.After consideration of the evidence on record, by judgment and decree

dated 12.12.2007, the trial Court dismissed the suit. Challenging the same, the

plaintiff filed A.S.No.4 of 2008 before the Principal District Court, Thanjavur.

By the impugned judgment and decree, the decision of the trial Court was

reversed and the first appeal was allowed and the suit was decreed as prayed.

Aggrieved by the same, this second appeal came to be filed.

https://www.mhc.tn.gov.in/judis

S.A.(MD)No.535 of 2010

4.The second appeal was admitted on 19.08.2010 on the following

substantial questions of law:-

“ 1.Whether in law, the judgment and decree of the lower appellate Court is sustainable in granting the relief of injunction and mandatory injunction without the prayer of declaration?

2.Whether in law, the judgment and decree of the lower of appellate Court reversing the well considered judgment and decree of the trial Court without assigning any reasons which he ought to have given is sustainable?

3.Whether in law, without approaching the alternative remedy available under the terms and conditions, the suit filed by the plaintiff is maintainable in terms of judgment of the Hon'ble Apex Court reported in 1997 (5) SCC 120? and

4.Whether the judgment and decree of the lower appellate Court is sustainable without reversing the finding of the trial Court regarding the maintainability of the suit is sustainable?”

5.The learned standing counsel for TNEB reiterated all the contentions

set out in the memorandum of grounds and called upon this Court to answer the

https://www.mhc.tn.gov.in/judis

S.A.(MD)No.535 of 2010

substantial questions of law in favour appellants and set aside the impugned

judgment and decree and restore the decision of the trial Court.

6.Per contra, the learned counsel for the respondent submitted that the

impugned judgment and decree do not call for any interference.

7.I carefully considered the rival contentions and went through the

evidence on record. The respondent/plaintiff was a consumer of electricity. He

had purchased a building and was carrying out certain repair works/additional

construction. The specific allegation of the appellant Board is that for carrying

out such works, the plaintiff must have obtained temporary connection and paid

the charges under tariff VI. He had not done so. When this was pointed out,

the plaintiff had made some payment. Audit objections were later raised

stating that the calculation was not correctly done. Therefore, demand notice

was issued by TNEB officials under Ex.A7 dated 09.01.2006. Thereupon, the

plaintiff through his counsel issued legal notice dated 16.02.2006 (Ex.A8)

raising a dispute. Under Section 42 r/w. 56 of the Electricity Act, 2003,

whenever dispute regarding liability to make payment arises, the same will

have to be resolved by the jurisdictional Superintending Engineer. If payment

as contemplated under Section 56 of the Act is made, then till the resolution of

https://www.mhc.tn.gov.in/judis

S.A.(MD)No.535 of 2010

the dispute, electricity connection cannot be disconnected. In the case on hand,

the plaintiff was threatened with disconnection. That is why, he filed the

aforesaid suit. I carefully went through the suit prayer. The plaintiff had only

sought limited relief. He only wanted the appellants to resolve the dispute

through the competent authority and till such resolution, the electricity

connection should not be cut off. Such a suit is clearly maintainable. There

was no need to seek any relief of declaration for getting such a injunction

decree. The first appellate Court correctly approached the legal issue.

However, it went wrong on facts. Even during the pendency of the first appeal,

the plaintiff appears to have given a letter dated 15.07.2009 seeking permission

to clear the liability in easy installments. Vide communication on the same day,

the Executive Engineer (O & M), Pattukkottai had sent a letter to the plaintiff

accepting his request and permitted him to clear the arrears in three

installments. The plaintiff paid the first installment on the same day. Since the

outcome of the first appeal was in his favour, he did not pay the other two

installments. I felt that since the plaintiff himself had accepted his liability and

also paid one installment, this second appeal could be disposed of by

permitting the respondent to pay the balance amount in easy installments. The

learned counsel for the respondent sought pass over. The learned counsel for

the respondent contacted the plaintiff on whatsapp and after getting

https://www.mhc.tn.gov.in/judis

S.A.(MD)No.535 of 2010

instructions submitted that this second appeal could be disposed of based on

the plaintiff's letter dated 15.07.2009.

8.Therefore, this second appeal is disposed of in the following terms:-

The plaintiff's liability was quantified on 15.07.2009 as

Rs.2,08,467/-. The plaintiff had paid a sum of Rs.69,489/- on the

same date. He was liable to make a further payment of

Rs.1,38,978/- to the appellant Board/TNEB/TANGEDCO. Almost

13 years have elapsed since then. The plaintiff is therefore obliged

to pay interest. The plaintiff cannot really be blamed. The

appellants have needlessly misconstrued the nature of injunction

order passed by the trial Court. Therefore, in the interest of justice,

it is enough if the plaintiff pays simple interest at the rate of 6% per

annum. The interest burden would come to Rs.1,08,402/-. Adding

the two components, the total liability of the plaintiff comes to

Rs.2,47, 380/-. I permit the plaintiff to clear the same in four

installments. The plaintiff shall pay a sum of Rs.61,870/- on the

first working day of every month. The plaintiff's liability will

commence from April 2, 2022 onwards. In other words, by

https://www.mhc.tn.gov.in/judis

S.A.(MD)No.535 of 2010

02.07.2022, the plaintiff should have cleared his liability in toto. If

the plaintiff commits default and fails to clear the liability in full by

02.07.2022, TANGEDCO can not only resort to disconnection of

plaintiff's electricity supply but also file execution petition for

enforcing this decree. No costs.”

11.03.2022 Index : Yes / No Internet : Yes/ No ias

To:

1.The Principal District Court, Thanjavur.

2.The Sub Court, Pattukkottai.

Copy to:

The Record Keeper, V.R. Section, Madurai Bench of Madras High Court, Madurai.

https://www.mhc.tn.gov.in/judis

S.A.(MD)No.535 of 2010

G.R.SWAMINATHAN, J.

ias

S.A.(MD)No.535 of 2010

11.03.2022

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter