Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Ultra Tech Cement Ltd vs The Tamil Nadu Electricity Board
2022 Latest Caselaw 717 Mad

Citation : 2022 Latest Caselaw 717 Mad
Judgement Date : 12 January, 2022

Madras High Court
M/S.Ultra Tech Cement Ltd vs The Tamil Nadu Electricity Board on 12 January, 2022
                                                                     W.P.No.30483 of 2015




                              IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                          DATED : 12.01.2022

                                                CORAM :

                       THE HONOURABLE MR. JUSTICE S.M. SUBRAMANIAM

                                          W.P.No.30483 of 2015
                                                   &
                                          M.P.Nos.1 to 3 of 2015


                    M/s.Ultra Tech Cement Ltd.,
                    Reddipalayam Cement Works
                    (Previously Known as Samruddhi Cement Ltd.,
                    & Prior to that as Grasim Industries Ltd.,)
                    Represented by its Senior Vice President (F&C)
                    Ariyalur Taluk 621 704
                    Perambalur                                        ... Petitioner

                                                   Vs.


                    1.The Tamil Nadu Electricity Board,
                      Rep. by its Chairman,
                      No.800, Anna Salai,
                      Chennai 600 002.

                    2.The Chief Engineer,
                      Civil Designs,
                      Tamil Nadu Electricity Board,
                      3rd Floor, NPKRR Maaligai,
                      No.144 Anna Salai, Chennai 600 002.
https://www.mhc.tn.gov.in/judis


                    Page 1 of 22
                                                                                W.P.No.30483 of 2015



                    3.The Chief Engineer,
                      Tamil Nadu Electricity Board,
                      Mettur Thermal Power Station,
                      Mettur Dam – 636 406.                           ... Respondents


                    Prayer : Writ Petition filed under Article 226 of the Constitution of
                    India for issuance of a Writ of Certiorarified Mandamus, calling for
                    the           entire   records       of   the   3rd      respondent          in
                    Lr.No.CE/SE/M.II/EE/O&AHS/MTPS-I/F                    shortcollection         /
                    D.No.681/15 dated 11.09.2015 and quash the same as illegal and
                    arbitrary and consequently direct the 1st Respondent to issue
                    appropriate instructions to the 3rd Respondent to strictly comply
                    with the terms of the agreement between parties and not to levy any
                    penalty for short collection.


                                   For Petitioner    :        Mr.Rahul Balaji

                                   For Respondents :          Mr.L.Jai Venkatesh
                                   1&2

                                   For Respondent 3 :         Mr.Abdul Kalam


                                                         ORDER

The demand notice issued by the respondent TANGEDCO

invoking the terms and conditions of Memorandum of Understanding

https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

executed at Headquarters/TNEB with the petitioner company and the

TANGEDCO is under challenge in the present writ petition.

2. The petitioner is a company and the manufacturer of

cement. The petitioner states that they produce cement of high

quality and manufacture of cement involves several raw materials

including gypsum and fly ash. In this regard, admittedly, the

contract was signed between the petitioner company and the

respondent TANGEDCO. Based on the Memorandum of

Understanding between the parties, the petitioner was collecting the

fly ash and using the same for manufacturing of cements.

3. The respondents also conducted inspection regarding the

performance of the terms and conditions of the contract periodically

and invoked Clause-5 of the Memorandum of Understanding and

issued the impugned demand notice.

4. The learned counsel for the petitioner strenuously

https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

contended that no opportunity was provided to the petitioner

enabling them to submit their defects in respect of the lapses noticed

by the TANGEDCO authorities. Even the nature of lapses, loss, if

any, occurred and its details are absent in the impugned order. Under

those circumstances, the petitioner is constrained to move the

present writ petition.

5. The learned counsel for the petitioner is of an opinion

that the petitioner is entitled for an opportunity of presenting their

case and no such opportunity was offered and the demand notice

impugned was issued based on the unilateral decision taken by the

TANGEDCO authorities.

6. In support of the said contention, the learned counsel for

the petitioner relied on the judgment of the Hon'ble Supreme Court

of India in the case of State of Karnataka vs. Shree Rameshwara

Rice Mills, Thiruthahalli reported in (1987) 2 SCC 160,

particularly paragraphs 7 and 8, which reads as under:

https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

''7.On a consideration of the matter we find

ourselves unable to accept the contentions of

Mr.Iyenger. The terms of Clause 12 do not afford scope

for a liberal construction being made regarding the

powers of the Deputy Commissioner to adjudicate upon

a disputed question of breach as well as to assess the

damages arising from the breach. The crucial words in

Clause 12 are ?and for any breach of conditions set

forth hereinbefore, the first party shall be liable to pay

damages to the second party as may be assessed by the

second party?. On a plain reading of the words it is

clear that the right of the second party to assess

damages would arise only if the breach of conditions is

admitted or if no issue is made of it. If is was the

intention of the parties that the officer acting on behalf

of the State was also entitled to adjudicate upon a

dispute regarding the breach of conditions the wording

of Clause 12 would have been entirely different. It https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

cannot also be argued that a right to adjudicate upon an

issue relating to a breach of conditions of the contract

would flow from or is inhered in the right conferred to

assess the damages arising from a breach of conditions.

The power to assess damages, as pointed out by the Full

Bench, is a subsidiary and consequential power and not

the primary power. Even assuming for arguments sake

that the terms of Clause 12 afford scope for being

construed as empowering the officer of the State to

decide upon the question of breach as well as assess the

quantum of damages, we do not think that adjudication

by the officer regarding the breach of the contract can

be sustained under law because a party to the agreement

cannot be an arbiter in his own cause. Interests of

justice and equity require that where a party to a

contract disputes the committing of any breach of

conditions the adjudication should be by an independent

person or body and not by the other party to the https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

contract. The position will, however, be different where

there is no dispute or there is consensus between the

contracting parties regarding the breach of conditions.

In such a case the officer of the State, even though a

party to the contract will be well within his rights in

assessing the damages occasioned by the breach in view

of the specific terms of Clause 12.

8.We are, therefore, in agreement with the view

of the Full Bench that the powers of the State under an

agreement entered into by it with a private person

providing for assessment of damages for breach of

conditions and recovery of the damages will stand

confined only to those cases where the breach of

conditions is admitted or it is not disputed.?

7. In the case of J.G. Engineers Private Limited vs. Union

of India and another reported in (2011) 5 SCC 758 at paragraphs

19 and 20, which reads as under:

https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

''?........

19.In fact the question whether the other party

committed breach cannot be decided by the party

alleging breach. A contract cannot provide that one

party will be the arbiter to decide whether he committed

breach or the other party committed breach. That

question can only be decided by only an adjudicatory

forum, that is, a court or an Arbitral Tribunal.

20.In State of Karnataka v. Shree Rameshwara

Rice Mills this Court held that adjudication upon the

issue relating to a breach of condition of contract and

adjudication of assessing damages arising out of the

breach are two different and distinct concepts and the

right to assess damages arising out of a breach would

not include a right to adjudicate upon as to whether

there was any breach at all. This Court held that one of

the parties to an agreement cannot reserve to himself the

power to adjudicate whether the other party has https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

committed breach. This Court held: (SCC p. 164, paras

7-8)

?7. ... Even assuming for argument's sake that

the terms of Clause 12 afford scope for being construed

as empowering the officer of the State to decide upon the

question of breach as well as assess the quantum of

damages, we do not think that adjudication by the

officer regarding the breach of the contract can be

sustained under law because a party to the agreement

cannot be an arbiter in his own cause. Interests of

justice and equity require that where a party to a

contract disputes the committing of any breach of

conditions the adjudication should be by an independent

person or body and not by the other party to the

contract. The position will, however, be different where

there is no dispute or there is consensus between the

contracting parties regarding the breach of conditions.

In such a case the officer of the State, even though a https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

party to the contract will be well within his rights in

assessing the damages occasioned by the breach in view

of the specific terms of Clause 12.

8.We are, therefore, in agreement with the view

of the Full Bench that the powers of the State under an

agreement entered into by it with a private person

providing for assessment of damages for breach of

conditions and recovery of the damages will stand

confined only to those cases where the breach of

conditions is admitted or it is not disputed.?

8. Relying on the above judgments, the learned counsel for

the petitioner reiterated that the petitioner may be driven to the Civil

Court only in the event of permitting him to present their case. The

basis on which a decision is taken for issuing an order of demand

itself is not explained to the petitioner and under those

circumstances, the petitioner has chosen to file the present writ

petition. Thus, the order impugned is directly in violation of the https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

principles of natural justice and the present writ petition is to be

considered.

9. The learned counsel appearing on behalf of the

respondents relying on the counter affidavit made a submission that

admittedly, the dispute arises based on the contractual obligation

between the parties. The impugned order is in tune with the contract

conditions, specifically condition No.5. Thus, the writ petition is not

maintainable, as such disputes are to be adjudicated before the

competent civil Court of law and not in a writ proceedings. The

respondents filed counter narrating facts and circumstances to

establish that the petitioner has violated certain terms and conditions

and the manner in which the calculations are made and the

impugned demand notices are issued.

10. However, this Court is of the considered opinion that

all such disputed facts cannot be adjudicated in a writ proceedings,

as it requires examination of documents in original and evidences

https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

and even oral evidences. Prima facie, it is raised that no opportunity

was provided to the petitioner, even to present their case and it is to

be considered. In a contractual obligation between the parties,

whether such a show cause notice or opportunity is required to be

given or not is to be considered. No doubt, it depends on the facts

and circumstances and also the terms and conditions agreed between

the parties. However, it cannot be concluded by holding that in each

and every case, a show cause notice and an opportunity of presenting

the case must be provided in contractual obligations. Thus, a writ

cannot be entertained merely on the ground that no opportunity to

present the case is given in the event of the dispute with reference to

the terms and conditions of the contract between the parties.

11. It is needless to state that the terms and conditions

agreed are known to the parties. Once agreed to the terms and

conditions are violated, the question of further opportunity by any

one of the parties would not arise. A dispute arises in the present

case, as the petitioner states that an opportunity is to be given to

https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

present their case. This Court is of an opinion that such a procedure,

which is not agreed between the parties need not be considered, as

providing of an opportunity is also a dispute, which is to be

considered with reference to the agreed terms and conditions of the

contract.

12. The concept of principles of natural justice can be

applied in a contract only in certain circumstances and the

performance of contractual obligation between the parties cannot be

compared with the statutory functions of the authorities. Though in

the present case, the Tamil Nadu Electricity Board is a State under

Article 12 of the Constitution of India. Thus, a distinction is to be

drawn between the contractual obligation between the parties and

the statutory functions and the powers to be exercised under the

statute by such officials of the State. These distinct factors are to be

demarcated when the facts are clear and more so relatable to the

terms and conditions of contract.

https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

13. Presuming that a writ Court examines the terms and

conditions of the contract, a doubt arises whether it is possible to

form an opinion with reference to the factual disputes which is to be

adjudicated in an elaborate manner with reference to the original

documents and evidences. Undoubtedly, there is a possibility of

error, omission, commission or otherwise, if any such opinion is

formed. That is the reason why the Constitutional Courts have taken

a consistent view that in the matter of contractual obligations

between the parties, they must approach the Civil Court of law as it

involves trial nature adjudication, which would provide an

opportunity to examine and cross examine the witnesses to cull out

the truth and resolve the issues in the manner known to law.

14. Per contra, based on the mere affidavit in a writ petition

and relying on certain xerox copies of the documents, which is

enclosed in the typed set of papers, such factually disputed issues

can never be adjudicated in a concrete manner so as to give complete

justice to the parties, who are all approaching the writ Court.

https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

15. With reference to the judgment relied upon by the

petitioner, the Hon'ble Apex Court of India in Shree Rameshwara

Rice Mills case cited supra at paragraphs-7 and 8 itself held that

''?the position will, however, be different where there is no dispute

or there is consensus between the contracting parties regarding the

breach of conditions. In such a case the officer of the State, even

though a party to the contract will be well within his rights in

assessing the damages occasioned by the breach in view of the

specific terms of Clause 12''?. Therefore, only in the event of no

dispute and there is a consensus between the contracting parties, the

writ Court may be in a position to take a decision in such nature of

issues and not otherwise. Therefore, the Hon'ble Supreme Court

entertained the argument in a particular case by distinguishing the

facts and ruled that the contractual obligations may be entertained by

the writ Court only if there is no dispute between the contracting

parties and there is a consensus. Even in paragraph-9, the Hon'ble

Supreme Court observed that recovery of the damages will stand https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

confined only to those cases where, the breach of conditions is

admitted or it is not disputed.

16. In the present case, the demand notice is disputed by

the petitioner, the manner in which the TANGEDCO assessed the

damages or otherwise is also questioned by the petitioner, and not

providing an opportunity to present the case is also raised. In this

regard, examination in detail with reference to the terms and

conditions of the contract are imminent and require adjudication.

Even in the other case relied on by the petitioner, the proposition

laid down by the Hon'ble Supreme Court in J.G.Engineers Private

Limited case cited supra is referred and in paragraph-19 the Hon'ble

Apex Court observed that ?''a contract cannot provide that one

party with the arbiter to decide whether he committed breach or the

other party committed breach. That question can only be decided by

only an adjudicatory forum, that is, a Court or an Arbitral

Tribunal''?. Admittedly, in the present case, the parties have not

agreed for arbitration, thus, necessarily they have to approach the https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

competent Court of law for the purpose of adjudicating issues.

17. Let us look into the reliance placed by the petitioner i.e.

Clause:5 of the Memorandum of Understanding. Clause-5 reads as

under:

'5.Performance of the cement company in

collecting 100% of Fly Ash will be reviewed for a period

of one year and penalty deemed fit will be imposed for

the short collection of Fly Ash due to the fault of

company after one year of the reviewed period.'

18. The above clause reveals that the collection of fly ash

will be reviewed for a period of one year and penalty deemed fit will

be imposed for the short collection of fly ash due to the fault of the

company. For understanding purposes, this Court is of an opinion

that the parties agreed that the performance of the petitioner

company will be reviewed and penalty deemed fit will be imposed.

Thus, the petitioner was very much aware and agreed regarding https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

imposition of penalty by the TANGEDCO. Question arises whether

an opportunity is to be provided prior to issuance of any such

demand notice. In this regard, it is stated in the Clause that penalty

deemed fit will be imposed for short collection of fly ash due to the

fault of the company. This exactly is the dispute to be adjudicated as

the short collection of fly ash and the quantum of short collection and

the fault of the company or there is no fault of the company and the

quantum of penalty to be imposed are disputed facts, which cannot

be adjudicated in a writ proceedings.

19. These issues require an elaborate examination of the

records and evidences. As far as the opportunity is concerned, no

doubt if there is a consensus between the parties or if any doubt

arises with reference to the performance or otherwise, it is open to

the parties to the contract to negotiate and form an opinion and

resolve the issues in an amicable manner. Therefore, it is for the

petitioner to approach the competent authorities, if they agree for

such consensus or for a negotiation and settlement of issues.

https://www.mhc.tn.gov.in/judis

W.P.No.30483 of 2015

However, the impugned order is concerned, it is for the petitioner to

initiate appropriate steps for effective adjudication of the disputes

for the purpose of redressing their grievances in the manner known

to law.

20. The petitioner if chosen to approach the competent

Court of law for resolving the issues, the Court shall consider the

period in which the writ petition was pending before the High Court

for the purpose of condoning the delay, if any petition to condone the

delay is filed by the petitioner.

21. With these observations, the writ petition stands

dismissed. No costs. Consequently, connected miscellaneous

petitions are closed.

                                                                              12.01.2022
                    kan
                    Internet : Yes
                    Index    : Yes / No
                    Speaking order / Non Speaking order



https://www.mhc.tn.gov.in/judis



                                                            W.P.No.30483 of 2015




                    To

                    1.The Tamil Nadu Electricity Board,
                      Rep. by its Chairman,
                      No.800, Anna Salai,
                      Chennai 600 002.

                    2.The Chief Engineer,
                      Civil Designs,
                      Tamil Nadu Electricity Board,
                      3rd Floor, NPKRR Maaligai,
                      No.144 Anna Salai, Chennai 600 002.

                    3.The Chief Engineer,
                      Tamil Nadu Electricity Board,
                      Mettur Thermal Power Station,
                      Mettur Dam – 636 406.




https://www.mhc.tn.gov.in/judis



                                              W.P.No.30483 of 2015




                                    S.M. SUBRAMANIAM, J.

                                                             kan




                                       W.P.No.30483 of 2015




https://www.mhc.tn.gov.in/judis



                                    W.P.No.30483 of 2015




                                        12.01.2022




https://www.mhc.tn.gov.in/judis



 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter