Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Shanmugavelu vs The Authorised Officer
2021 Latest Caselaw 21513 Mad

Citation : 2021 Latest Caselaw 21513 Mad
Judgement Date : 27 October, 2021

Madras High Court
Shanmugavelu vs The Authorised Officer on 27 October, 2021
                                                                             CRP Nos.1892 & 2282 of 2021



                                     IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                    DATED: 27.10.2021

                                                         CORAM :

                                THE HON'BLE MR.SANJIB BANERJEE, CHIEF JUSTICE
                                                              AND
                                      THE HON'BLE MR.JUSTICE P.D.AUDIKESAVALU


                                            C.R.P. Nos.1892 & 2282 of 2021

                      Shanmugavelu
                      Managing Director
                      M/s. Sunbright Designers Private Limited
                      Module No.4                                                    Petitioner in
                      Readymade Garment Complex                                      CRP No.1892/21
                      SIDCO Industrial Estate                                        Respondent in

Guindy, Chennai - 600 032. .. CRP No.2282/21

Vs.

                      The Authorised Officer
                      Central Bank of India
                      Corporate Finance Branch                                       Respondent in
                      Addison Buildings                                              CRP No.1892/21
                      No.803, Anna Salai                                             & Petitioner in
                      Chennai-600 002.                                        ..     CRP No.2282 /21



Prayer in CRP No.1892 of 2021: Petition under Article 227 of the Constitution of India against the order dated 30.07.2021 in R.S.(SA)119 of 2019 in SA No.143 of 2018 i.e “The impugned order stands modified to the extent that bank is entitled for forfeiture of a

__________

http://www.judis.nic.in CRP Nos.1892 & 2282 of 2021

sum of Rs.50 lakhs” passed by the Debt Recovery Appellate Tribunal Chennai on the file of the Debt Recovery Appellate Tribunal, Chennai.

Prayer in CRP.No.2282 of 2021: Petition under Article 227 of the Constitution of India against the order dated 30.07.2021 made in RA (SA) No.119 of 2019 on the file of the Debt Recovery Appellate Tribunal, Chennai.


                                     For Petitioner in
                                     CRP No.1892/21 &
                                     Respondent in
                                     CRP No.2282/21        :   Mr.G.Sethuraman

                                     For Respondent in
                                     CRP No.1892/21 &
                                     Petitioner in
                                     CRP No.2282/21        :   Mr.M.Devaraj


                                                     COMMON ORDER
                                           (Made by the Hon'ble Chief Justice)


Both the secured creditor bank and the original auction-

purchaser question the propriety of an order dated July 30, 2021

passed by the Debt Recovery Appellate Tribunal in Chennai. The order

impugned has been passed on an appeal by the bank assailing an

order dated May 06, 2019 passed by the Debts Recovery Tribunal II,

Chennai in proceedings under Section 17 of the Securitisation and

__________

http://www.judis.nic.in CRP Nos.1892 & 2282 of 2021

Reconstruction of Financial Assets and Enforcement of Security

Interest Act, 2002.

2. The appeal raises a fundamental issue and needs to be dealt

with on first principles. At the center of the controversy is a provision

of the Security Interest (Enforcement) Rules, 2002. Rule 9 of the said

Rules pertains to the time of sale, issue of sale certificate and delivery

of possession and the like of secured assets. Sub-rule (5) of Rule 9,

which is relevant for the present purpose, provides as follows:

"9. Time of sale, issue of sale certificate and delivery of possession, etc. -

(1) ....

(5) In default of payment within the period mentioned in sub-rule (4), the deposit shall be forfeited and the property shall be resold and the defaulting purchaser shall forfeit all claim to the property or to any part of the sum for which it may be subsequently sold.

... "

3. In the present case, the property was put up for sale in

December, 2016. The petitioner in CRP No.1892 of 2021 bid Rs.12.27

__________

http://www.judis.nic.in CRP Nos.1892 & 2282 of 2021

crore for the relevant immovable property at the auction conducted by

secured creditor Central Bank of India on December 07, 2016. An

initial deposit was made by the auction-purchaser and, subsequent to

the bid, a total amount of Rs.3,06,75,000/- was tendered in total

against the bid price of Rs.12.27 crore. Repeated requests from the

secured creditor failed to elicit any further payment and, upon due

notice to the said highest bidder, the same property was put up for

sale again.

4. At the subsequent auction held on March 30, 2019, the

highest bid received was of Rs.14.76 crore. There is no doubt that the

sale has now been completed, the subsequent highest bidder has put

in the entire consideration and the sale certificate has been issued in

favour of such purchaser.

5. The issue that remained unresolved between the secured

creditor and the initial auction-purchaser was how the amount that had

been tendered by the initial auction-purchaser could be dealt with by

the secured creditor. After all, a substantial part of the consideration,

to the extent of Rs.3,06,75,000/- as indicated above, had been paid

__________

http://www.judis.nic.in CRP Nos.1892 & 2282 of 2021

against the bid amount of Rs.12.27 crore. The secured creditor read

Rule 9(5) of the said Rules to imply that it was entitled to forfeit the

entire amount tendered. The initial auction-purchaser questioned such

forfeiture before the DRT II.

6. By a judgment and order of May 06, 2019, the DRT II made a

rough and ready estimate of the expenses that the secured creditor

may have incurred in conducting the sale for a second time and

allowed the secured creditor to retain a sum of Rs.5 lakh out of the

entire money tendered by the initial auction-purchaser. As a

consequence, the secured creditor was liable to refund a sum of

Rs.3,01,75,000/- to the initial auction-purchaser in terms of the order

of the Tribunal of May 06, 2019.

7. The secured creditor carried such order of the Tribunal to the

appellate authority. By the judgment and order impugned dated July

30, 2021, the DRAT agreed in principle that the secured creditor was

not entitled to forfeit the entire amount tendered by the defaulting

initial auction-purchaser; but the Appellate Tribunal enhanced the

amount permitted to be retained by the secured creditor from Rs.5

__________

http://www.judis.nic.in CRP Nos.1892 & 2282 of 2021

lakh to Rs.55 lakh. Both sets of parties have questioned the order

dated July 30, 2021: the initial auction-purchaser on the ground that

there is no basis for the enhancement of the quantum to be forfeited;

and, the secured-creditor on the ground that the law permits the entire

amount to be forfeited and neither the DRT nor the DRAT had any

authority to question the forfeiture.

8. In support of the secured creditor's case, Section 35 of the Act

of 2002 is placed to indicate that the Act of 2002 has overriding effect,

notwithstanding anything inconsistent therewith contained in any other

law for the time being in force or even any instrument having the

effect by virtue of any other law. According to the secured creditor,

since the said Rules permit the forfeiture and since it is evident that

the initial auction-purchaser may have bitten off more than it could

chew and did not have the means to sustain its bid, it is only

appropriate that the money has been forfeited so that other upstarts

do not come in future and make fanciful bids that their resources

cannot match up to.

9. Before even referring to the primary assertion made on behalf

__________

http://www.judis.nic.in CRP Nos.1892 & 2282 of 2021

of the initial auction-purchaser, what begs the question is whether any

distinction may be made between an auction-purchaser who is in

default to the extent of 99% of the bid amount and an auction-

purchaser who may be in default to the extent of 1% of the bid

amount. The key to understanding the answer to the issue may lie in

appreciating the different positions of such defaulting bidders.

10. Section 74 of the Contract Act, 1872 provides for

compensation for breach of contract where the penalty is stipulated.

Section 73 of the Contract Act is the general rule that provides for

compensation for loss or damage caused by breach of contract and

Section 74 is where the quantum is specified. What Section 73 of the

Contract Act mandates is that a party who suffers as a result of a

breach committed by the other party to the contract "is entitled to

receive from the party who has broken the contract, compensation for

any loss or damage caused to him thereby, which naturally arose in

the usual course of things from such breach, or which the parties

knew, when they made the contract, to be likely to result from the

breach of it". Any detailed discussion on such provision would be

beyond the scope of the present lis and may require many more

__________

http://www.judis.nic.in CRP Nos.1892 & 2282 of 2021

sheets that may be conveniently expended in the present exercise.

Indeed, Section 73 of the Contract Act is in the nature of a

jurisprudential philosophy that is accepted as a part of the law in this

country. In short, it implies that only such of the loss or damage

suffered by the party not in breach, may be recovered from the party

in breach, as a consequence of the breach. It is possible that as a

result of the breach, the party not in breach does not suffer any

adverse impact. It is also possible, as in the present case, that as a

consequence of the breach, the party not in breach obtains a benefit.

In such cases, where no loss or damage has been occasioned to the

party not in breach, such party cannot extract any money merely on

account of such breach, as the entitlement in law to compensation is

not upon the commission of breach, but only upon any loss or damage

being suffered as a consequence thereof. That is elementary.

11. Even in cases of liquidated damages, where the quantum

specified is regarded as a genuine pre-estimate by parties to the

contract, there needs to be some loss or damage suffered for the party

not in breach to even be entitled to claim the amount quantified in the

contract itself. The factum of having suffered damages in such a

__________

http://www.judis.nic.in CRP Nos.1892 & 2282 of 2021

situation has to be established, though the quantum of the loss need

not be, since the contract contains a genuine pre-estimate thereof.

12. Rule 9(5) of the said Rules of 2002 has to be seen as an

enabling provision that permits forfeiture in principle. However, such

Rule cannot be conferred an exalted status to override the underlying

ethos of Section 73 of the Contract Act. In other words, Rule 9(5) has

to yield to the principle recognised in Section 73 of the Contract Act or

it must be read down accordingly. Thus, notwithstanding the wide

words used in Rule 9(5) of the said Rules, a secured creditor may not

forfeit any more than the loss or damage suffered by such creditor as

a consequence of the failure on the part of a bidder to make payment

of the consideration or the balance consideration in terms of the bid. It

is only if such principle, as embodied in Section 73 of the Contract Act,

is read into Rule 9(5) of the said Rules, would there be an appropriate

answer to the conundrum as to whether a colossal default of the

entirety of the consideration or the mere default of one rupee out of

the consideration would result in the identical consequence of

forfeiture as indicated in the provision.

__________

http://www.judis.nic.in CRP Nos.1892 & 2282 of 2021

13. In any event, notwithstanding the reference to Section 35 of

the Act of 2002, the apparent overriding effect of the provisions of the

Act of 2002 has to be tempered in the light of Section 37 of the Act.

Though Section 37 of the Act refers to several statutes by name, the

residual limb of such provision recognises "or any other law for the

time being in force", which would embrace the Contract Act within its

fold. It is completely unacceptable that by virtue of the delegated

legislation as in the Rules of 2002, the fundamental principle envisaged

in the Contract Act would get diluted or altogether disregarded.

14. As far as the secured creditor's contention is concerned, the

above adequately answers the same. Accordingly, the secured

creditor's challenge to the order impugned is found to be without

basis, though it remains to be seen whether the enhancement of the

amount forfeited was permissible.

15. For any quantum to be awarded on account of the damages,

there is a twin exercise which has to be undertaken: the first limb of

the exercise is to ascertain the factum; it is only upon the factum

being established that the quantum may be assessed. In other words,

__________

http://www.judis.nic.in CRP Nos.1892 & 2282 of 2021

if the factum of loss and damage is not established, there is no need to

proceed to the second part to try and assess the quantum.

16. It must also be noticed that assessment of damages is a

complex exercise and sometimes courts are given to making an

approximation on the basis of a degree of guesswork and estimation,

as there can be no exact science in ascertaining the quantum of

damages suffered with any arithmetical precision. In several fields,

particularly in engineering contracts, there are complex formulae which

are relied upon in different situations. Even the Supreme Court, as

regards the law in this country, has reckoned that when there is loss of

profit, an amount of about 15% of the total contract value may be

taken as the profit component. There are several other fields where

judicial precedents indicate the bandwidth, on the basis of percentage

or otherwise, of the quantum in assessing damages.

17. In the present case, the DRT did not embark on any rational

methodology for trying to assess the quantum of loss and damage

apparently suffered by the secured creditor as a consequence of the

initial auction-purchaser not honouring its commitment. The DRT

__________

http://www.judis.nic.in CRP Nos.1892 & 2282 of 2021

assessed in a rough and ready manner that a sum of Rs.5 lakh on

account of additional expenses incurred would be an appropriate

amount, since the subsequent sale fetched a substantially higher price

than the initial sale. It must also be noticed that the initial auction-

purchaser had accepted its fate and not questioned the quantum of

forfeiture as directed by the DRT. It was only the secured creditor

which carried the order dated May 06, 2019 passed by the DRT to the

appellate authority seeking the entire pound of flesh in terms of Rule

9(5) of the said Rules of 2002 that the secured creditor considered to

be sacrosanct.

18. It was completely open to the appellate authority to enhance

the quantum as awarded by the DRT. However, such exercise could

have been undertaken by inviting evidence in such regard. The

appellate authority purported to enhance the quantum from Rs.5 lakh

to Rs.55 lakh without indicating any or cogent grounds for such

enhancement. Though an element of guesstimation is permitted while

assessing damages, when an initial authority has indicated a ballpark

figure, any tinkering with such figure at the appellate stage would

require material in support thereof, which is completely lacking in the

__________

http://www.judis.nic.in CRP Nos.1892 & 2282 of 2021

judgment and order impugned dated July 30, 2021 passed by the

appellate authority in the present case.

19. For the reasons aforesaid, the enhancement of the quantum

of forfeiture as permitted by the Appellate Tribunal in the impugned

order of July 30, 2021 cannot be sustained and the same is set aside.

The quantum as awarded by the DRT II, Chennai in its order of May

06, 2019 is restored and, to such extent, the order of the appellate

authority is set aside.

20. Before parting, there is another aspect that has to be

referred to for the completeness of the discussion. The purpose of the

Act of 2002 is to ensure speedy recovery of the debt due to secured

creditors covered by such statute. Towards such end, the provisions of

the said Act and the Rules made thereunder give primacy to the

secured creditor in initially assessing the quantum of debt due and in

proceeding against the securities furnished for realising such debt due.

However, no secured creditor, not even by embracing the provisions of

the said Act of 2002, can unjustly enrich itself or obtain any more by

way of resorting to any of the measures contemplated under Section

__________

http://www.judis.nic.in CRP Nos.1892 & 2282 of 2021

13(4) of the Act or otherwise than the debt that is due to it and the

costs that may have been incurred in course of trying to recover the

debt due. In a sense, if the forfeiture provision in Rule 9(5) of the said

Rules is ready to imply what the secured creditor in this case seeks to,

it may result in a secured creditor unjustly enriching itself, which is not

permissible.

21. CRP Nos. 2282 and 1892 of 2021 are disposed of as above.

There will, however, be no order as to costs. CMP Nos.17278 and

14695 of 2021 are closed.

                                                                  (S.B., CJ.)      (P.D.A., J.)
                                                                            27.10.2021
                      Index : Yes

                      kpl




                      __________



http://www.judis.nic.in
                                          CRP Nos.1892 & 2282 of 2021




                                      THE HON'BLE CHIEF JUSTICE
                                                   AND
                                           P.D.AUDIKESAVALU, J.

                                                                (kpl)




                                      CRP Nos.1892 & 2282 of 2021




                                                        27.10.2021




                      __________



http://www.judis.nic.in

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter