Citation : 2021 Latest Caselaw 20649 Mad
Judgement Date : 7 October, 2021
O.P.Nos.461, 503 and 669 of 2017
IN THE HIGH COURT OF JUDICATURE AT MADRAS
DATED : 07.10.2021
CORAM
THE HONOURABLE MR.JUSTICE N. SATHISH KUMAR
O.P.Nos.461,503 and 669 of 2017
O.P.No.461 of 2017
M/s.G.G.Hospitals
Rep. By its Sole Proprietor,
Mrs.Kamala Selvaraj,
6E, Nungambakkam High Road,
Nungambakkam, Chennai – 600 034. .. Petitioner
vs
1.M/s.Ascent Engineers & Infrastructures Pvt Ltd.,
(Formerly M/s.Ascent Engineers, a Partnership Firm)
Rep. By its Managing Director,
Mr.Srinivasan S.Iyer,
No.12, 46th Street, 9th Avenue,
Ashok Nagar, Chennai – 600 083.
2.M/s.Larsen & Toubro Limited,
Mount Poonamalee Road,
Manapakkam, Chennai – 600 089. ..Respondents
O.P.No.503 of 2017
M/s.Ascent Engineers & Infrastructures Pvt Ltd., (Formerly M/s.Ascent Engineers, a Partnership Firm) Rep. By its Managing Director, Mr.Srinivasan S.Iyer, No.12, 46th Street, 9th Avenue, Ashok Nagar, Chennai – 600 083. .. Petitioner
Vs
1.M/s.G.G.Hospitals Rep. By its Sole Proprietor,
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
Mrs.Kamala Selvaraj, 6E, Nungambakkam High Road, Nungambakkam, Chennai – 600 034.
2.Larsen & Toubro Limited, Mount Poonamalee Road, Manapakkam, Chennai – 600 089. ..Respondents
O.P.No.669 of 2017
M/s.Larsen & Toubro Limited, Mount Poonamalee Road, Manapakkam, Chennai – 600 089. .. Petitioner
vs
1.M/s.Ascent Engineers & Infrastructures Pvt Ltd., (Formerly M/s.Ascent Engineers, a Partnership Firm) Rep. By its Managing Director, Mr.Srinivasan S.Iyer, No.12, 46th Street, 9th Avenue, Ashok Nagar, Chennai – 600 083.
2.M/s.G.G.Hospitals Rep. By its Sole Proprietor, Mrs.Kamala Selvaraj, 6E, Nungambakkam High Road, Nungambakkam, Chennai – 600 034. .. Respondents
Prayer in O.P.No.461 of 2017: Petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 praying this Court to set aside arbitral award dated 14.04.2017 and an order order of correction of the error dated 20.04.2017 and pass such further or other orders as this Court may deem fit and proper in the circumstances of the case.
Prayer in O.P.No.503 of 2017: Petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 praying this Court to (a) setting aside the arbitral award dated 14.04.2017 as corrected/amended by an order dated 20.04.2017, passed by the Arbitrator herein, limited only in so far as the rate of interest awarded; grant of rebate of 2% and the cost factor, (b) awarding costs of the present petition; and (c) granting such further or other
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
reliefs as may be deemed fit and necessary in the circumstances of the case.
Prayer in O.P.No.669 of 2017: Petition filed under Section 34 of the Arbitration and Conciliation Act, 1996 praying this Court (a) to set aside arbitral award dated 14.04.2017, corrected on 20.04.2017 passed by the learned arbitrator to the extent set out in this petition and (b) and pass such other or further orders as this Court may deem fit and proper in the circumstances of the case.
For Petitioner : Mr.V.Kuberan for M/s.Rank Associates (in O.P.No.503 of 2017)
Mr.S.R.Rajagopal for M/s.Ojas Law Firm (in O.P.No.461 of 2017)
Mr.R.Murari, Senior Counsel for Ms.Preeti Mohan (in O.P.No.669 of 2017)
For Respondents : Mr.S.R.Rajagopal for M/s.Ojas Law Firm Mr.R.Murari, Senior Counsel for Ms.Preeti Mohan for R2 (in O.P.No.503 of 2017)
Mr.V.Kuberan for M/s.Rank Associates for R1 Mr.R.Murari, Senior Counsel for Ms.Preeti Mohan for R2 (in O.P.No.461 of 2017)
Mr.V.Kuberan for M/s.Rank Associates for R1 Mr.S.R.Rajagopal for M/s.Ojas Law Firm for R2 (in O.P.No.669 of 2017)
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
COMMON ORDER
O.P.No.461 of 2017 has been filed challenging the arbitral
award directing the petitioner/applicant to pay a sum of
Rs.1,10,24,982/- towards refund of retention money with interest
together as ordered in the award.
2. O.P.No.503 of 2017 is filed by the first respondent only
against the rate of interest awarded, rebate granted at 2% and the
cost factor.
3. O.P.No.669 of 2017 is filed against the arbitral award
challenging certain observations recorded against the
petitioner/applicant in the award. The above OP has been filed by
the second respondent in the main proceedings.
4. Since all three OPs are arising out of the same award, this
Court is inclined to dispose of all the three OPs by way of a common
order.
5. For the sake of convenience, petitioner in O.P.No.503 of
2017 viz, M/s.Ascent Engineers & Infrastructures Pvt Ltd., is
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
referred as claimant, petitioner in O.P.No.461 of 2017 viz.,
M/s.G.G.Hospitals is referred as first respondent and the petitioner
in O.P.No.669 of 2017 viz., M/s.Larsen & Toubro Limited is referred
as second respondent.
6. The claimant is the Contractor for execution and
construction of the Hospital, for the first respondent. The first
respondent wanted to construct a new multi speciality hospital and
engaged the services of the second respondent by agreement dated
23.04.2008 i.e., Consultancy Service Agreement wherein the
second respondent was appointed for providing Architecture &
Engineering Services for the project besides overseeing and
supervising the day-to-day execution of the work and the payment
to be made by the first respondent.
7. The second respondent has identified the claimant as the
contractor and, accordingly, a Tripartite agreement dated
21.10.2009 between the parties came to be executed. The
construction was carried as per the drawings and specifications of
the second respondent and on instructions issued from time to time
and to carry out day-to-day activities under the supervision of
respondents 1 and 2. The second respondent after measurements
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
and after satisfying with the completion certificate, raised the Bill of
Quantities.
8. The first respondent has not paid the outstanding amount
of Rs.4,08,33,039/- as on 15.11.2012. Hence it is the contention
that the claimant has raised for non-payment of the building
constructed by him and it is further stated that the entire
construction has been done as per the drawing and plan by the
second respondent, which has also been approved by the first
respondent. The first respondent has also started constructing the
fourth floor. As the fourth floor plan was not sanctioned, Chennai
Metropolitan Development Authority (CMDA) has issued a letter for
removal of unauthorized construction.
9. Hence, the contention of the first respondent is that the
planning permission was issued by the CMDA for construction of
double basement, ground floor plus three floors in the hospital
project. In the mean time, on the suggestion of the first respondent,
the claimant was entrusted with the construction of the hospital
project under the Tripartite agreement dated 21.10.2009 and on
01.02.2010 itself the first respondent handed over the site to the
claimant.
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
10. Though the plan was sanctioned for three floors, the
claimant started construction in the fourth floor without the
knowledge of the first respondent during the month of May,2011. It
is his contention that the first respondent has not issued any written
instructions to the claimant and the second respondent for putting
up additional/extra works in the fourth floor of the project. It is the
main contention that they never gave any permission to put up
construction in the fourth floor. Thereafter, when the CMDA officials
came for site inspection, it was found that the construction of the
fourth floor was in deviation of the sanctioned plan and the same
had to be demolished. The first respondent came to know about the
unauthorized construction by then only and was requesting the
claimant and the second respondent to demolish the fourth floor in
accordance with the norms. As the second respondent is not willing
to demolish the same, the first respondent was constrained to
engage the third party contractor to rectify the situation.
11. Insofar as the second respondent is concerned, it is the
contention that no claim can be raised against the second
respondent. Based on the pleadings, the Tribunal has framed the
issues. On appreciation of the evidence on both sides, the Tribunal
has passed the following award:-
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
“(I) Rs.2,69,74,070/- towards the certified Bills Account.
(II) Rs.1,10,24,982/- towards the refund of Retention Money, subject to the adjustment as directed below.
(III)Rs.21,15,363.44/- being the Interest @ 9% payable for the bleated payment of the certified RA Bills as on 28.02.2013.
(IV) Interest @ 9% P.A. From 01.03.2013 on Rs.2,69,74,070/- till date of realization of the said amount by the claimant from the 1st respondent.
(V) The claimant shall pay Rs.39,10,000/- being the 2% rebate assured to be given to the first respondent. This amount shall be set off and adjusted against the sum of Rs.1,10,24,982/- to be paid by the respondent and as against the sum, the claimant shall be entitled to and the respondent shall pay only Rs.71,14,982/- in full quit satisfaction of the amount awarded in (II) above.
(VI) Interest 9% P.A on Rs.21,15,363.40/- from the date of the award till the date of realization.
(VII) The counter claims raised by the 1st respondent shall stand rejected and dismissed. (VIII) The parties on either side shall bear their own respective costs of this Arbitration proceeding.”
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
12. As against the award as well as the dismissal of the
counter claim raised by the first respondent, O.P.No.461 of 2017
has been filed by the first respondent. Similarly, O.P.No.503 of 2017
is filed by the claimant as against the interest portion and
O.P.No.669 of 2017 is filed by the second respondent as against
certain observation that was made by the arbitrator in the award.
13. The learned counsel appearing for the petitioner in
O.P.No.461 of 2017, vehemently contended that the learned
arbitrator has passed award beyond the terms of the contract and
hence he has re-written the contract. It is his further contention
that the consultancy service agreement entered into between the
first respondent and the second respondent makes it obligatory on
the part of the second respondent for preparation of master plan for
the proposed new hospital block. It is the contention that the
second respondent has to prepare all necessary drawings and
documentation necessary for getting necessary approval of
Government statutory bodies and to ensure compliance with the
codes, standard and legislation, as applicable. Similarly, Clause 7 of
the contract makes it very clear that the second respondent
submitted the completion report and drawings for project as
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
required and assessed plan in terms of the Certificate. Tripartite
agreement entered into between the parties also makes it clear that
the second respondent has to supervise the entire construction and
the second respondent shall construct as per the approved plan.
14. It is his further contention that drawing plan of
construction of the fourth floor did not contain the signature of the
first respondent. Hence it is the contention that as per the contract
entered into between the parties, only as per the instructions and
drawings, the fourth floor has been constructed deviating the plan
sanctioned for third floor. Therefore, the first respondent has to
suffer severe damages in removing the deviation and hence it is the
contention that the learned arbitrator has not considered all these
facts and had re-written the contract.
15. Similarly, it is the contention that the construction of the
fourth floor was not in the knowledge of the first respondent and
only at the time of inspection by the CMDA officials, the owner of
the hospital came to know about the construction. Hence it is the
contention that the entire award has not been passed based on the
contractual terms and obligations entered upon between the parties
and, therefore, prays for setting aside the award. In support of his
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
contention, the learned counsel relied upon the following decisions
that (i) Associate Builders v. Delhi Development Authority reported
in (2015) 3 SCC 49, (ii) MMTC Limited v. Vedanta Limited reported
in (2019) 4 SCC 163, (iii) Patel Engineering Limited v. North
Eastern Electric Power Corporation Limited reported in (2020) 7
SCC 167, Peddi Virayya v Doppalapudi Subba Rao and another
reported in 1957 SCC Online AP 341, (iv)Sheladia Associates Inc. v.
Tamil Nadu Road Sector Project II, Rep. By its Project Director
reported in 2019 SCC Online Mad 1783 and (v) State of Orissa and
another v. Kalinga Construction Co. Pvt Ltd.,reported in (1970) 2
SCC 861.
16. Learned counsel appearing for the claimant submitted that
the sanction was available only upto third floors and he was
engaged and acted as per the instruction of L&T Management. As
per the direction of the drawing of the L&T and with approval of the
first respondent, he has put up the construction in the fourth floor.
It is his further contention that the owner of the hospital does not
have any knowledge about the construction is beyond the factual
aspects and there were six instances available on record to show
that the hospital authorities are aware of the construction put up on
the fourth floor. There is a tacit approval of the owner for
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
construction in the fourth floor. Hence it is his submission that when
the arbitral Tribunal has considered the entire aspect by
appreciating the evidence, the Court cannot re-appreciate the entire
evidence once again as an appellate court. No grounds have been
made out to interfere with the award. It is his further contention
that it is only grievance that the arbitrator has not awarded the
interest fully and a portion of the award alone has to be set aside.
17. Whereas the Learned Senior Counsel appearing for the
second respondent submitted that the second respondent was a
formal party in the case and this petition has been filed only to
challenge certain observations of the arbitral tribunal that the
second respondent has not participated in the proceedings, which is
contrary to the facts. Thus, the contention is that the OP has been
filed only to a limited extent.
18. It is not disputed by both sides that the Consultancy
Agreement was entered into between the owner and the applicant
herein and the L&T Management for providing services like drawing,
planing etc., It is relevant to note that the GG Hospital engaged the
services of L&T Limited for professional services for giving
architectural design and engineering design with various other
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
detailed engineering services. Clause 2 to 6 sub-clause (6) makes it
clear that the L&T Management will provide necessary drawings and
documentation also to get approval from the Government statutory
bodies. However, the costs to be paid by the owner. It is also
agreed by L&T that even during construction such L&T has to check
and approve the drawings submitted by the contractor and visit the
site of work and wherever necessary to clarify the decision. The
entire document makes it clear that the main part of agreement
entered between the hospital and L&T is to provide design and
necessary documents of drawings etc., The claimant was engaged
to construct the hospital and accordingly, the Tripartite agreement
came to be executed between the parties. These facts are not in
dispute.
19. The construction put up by the claimant is not disputed up
to third floor of the hospital. The only dispute seems to be with
regard to the fourth floor violating the sanctioned plan. The
sanctioned plan was only up to third floor by the CMDA, whereas, in
the fourth floor construction have been raised in the month of
May,2011 as per the plan by L&T. It is the case of the owner that
they have no knowledge that such construction has been put up in
the fourth floor.
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
20. The learned arbitral tribunal on appreciation of entire
evidence negatived the contention of the Hospital and recorded a
factual finding that in fact such construction was in violation of the
plan and the same has been put up with the knowledge of the
owner. Therefore, they cannot retain the running bills account for
the claim. The learned Arbitrator has not only considered the
documentary evidence but also the oral evidence of the parties and
concluded that the construction has been put up in the fourth floor
only as per the drawing and instructions furnished by the second
respondent which had necessary power along with Tripartite
agreement and the second respondent has obligatory under the
Tripartite agreement has also factually recorded that the hospital is
also aware of the construction of the fourth floor. Therefore, the
contention that they are not aware of the construction put up in the
fourth floor is dis-believed by the learned Arbitrator on appreciation
of evidence.
21. After appreciating the entire evidence, the learned
Arbitrator recorded the finding. It is also relevant to note the very
contention that the first respondent has no knowledge about the
construction of the fourth floor cannot be countenanced for the
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
simple reason that Ex.C17 filed before the Arbitral tribunal would
show that the letter was written on behalf of the hospital authorities
enclosing the cost analysis for the fourth floor and it is agreed that
the cost of the fourth floor is Rs.360 lakhs. Similarly, letter
addressed to the owner of the hospital for bringing the officials for
inspection to be taken up in the fourth floor construction. Same
indicates that the owner of the hospital remained silent to go ahead
with the construction and the letter dated 3.07.2012 by the hospital
to the CMDA indicated that in fact they wanted to retain the fourth
floor building construction. The mail sent by the hospital authorities
available on record also indicate that they agreed to pay the amount
after getting the loan. All these facts clearly indicate that deviation
has been made with the knowledge of the owner of the hospital.
Therefore, it cannot be said that the owner had no knowledge in
bringing up the construction in her own building. This has been
appreciated factually by the learned Arbitrator. Therefore, the
contention that the Arbitrator has not taken note of the terms of the
contract has no legs to stand. In fact, the learned Arbitrator has in
detail discussed every issues and considered various documents
including the oral evidence.
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
22. In such view of the matter, this Court is of the view that
once the learned Arbitrator has passed the award appreciating the
evidence, merely because, some view is possible, this Court cannot
substitute the counsel's own views, in the place of arbitrators view.
It is in the domain of the Arbitrator to interpret the contract and to
appreciate the evidence and that he has done it rightly in this
matter. The very contention that the owner had no knowledge about
the unauthorized construction put up in a massive building itself is
highly improbable and cannot be believed.
23. In such view of the matter, the contention of the learned
counsel to challenge the award in entirety has no legs to stand
though various judgments have been cited by the learned counsel
appearing for the petitioner in O.P.No.461 of 2017. On a perusal of
the award, this Court is of the view that the arbitrator has
appreciated every document and facts including the oral evidence
and gave the finding. Therefore, this Court cannot re-write the
award by substituting the view of the Applicant, who suffered an
award. On a perusal of the award, none of the grounds has been
made out to interfere with the very reasoned award passed by the
learned Arbitrator.
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
24. As far as the interest portion challenged by the learned
counsel, the learned arbitrator in fact awarded interest from
28.02.2013 at the rate of nine per cent, the same cannot be said to
be perverse. Further, none of the circumstances pointed out by the
learned counsel to contend that the interest restricted by the
learned Arbitrator at 2% is perverse. Therefore, the O.P.
challenging the interest portion, namely, O.P.No.503 of 2017 also
fails.
25. The other O.P. filed by the second respondent challenging
the award on the ground that certain observations have been made
against L&T is also liable to be dismissed. It is to be noted that the
second respondent was only made as a formal party and no claim
whatsoever is made against them. In fact, no claim whatsoever is
also passed against them. Admittedly, no relief has been granted.
Therefore, the mere dismissal of the application filed under Section
16 by the arbitral tribunal cannot be a ground to interfere with the
well reasoned award passed as against the first respondent. What
is recorded is only that the second respondent has not participated
fully in the proceedings. Except filing the defence, they have not
participated in the proceedings, which has been recorded by the
arbitral tribunal and, therefore, by no stretch of imagination it can
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
be said that such a finding is adverse and have any impact on the
second respondent. Accordingly, as there is no award passed
against them, the award passed by the learned arbitrator, cannot be
interfered with, for the sake of the second respondent merely based
on some observations recorded by the arbitrator.
26. For the foregoing reasons, the award passed by the
learned Arbitrator stands confirmed and all these Original Petitions
are dismissed. No costs.
07.10.2021
Index: Yes/No ssm
https://www.mhc.tn.gov.in/judis/
O.P.Nos.461, 503 and 669 of 2017
N. SATHISH KUMAR, J.
(ssm)
O.P.Nos.503,461 and 669 of 2017
07.10.2021
https://www.mhc.tn.gov.in/judis/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!