Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Chief Engineer Highway vs M/S.Roman Tarmat Ltd
2021 Latest Caselaw 13801 Mad

Citation : 2021 Latest Caselaw 13801 Mad
Judgement Date : 12 July, 2021

Madras High Court
The Chief Engineer Highway vs M/S.Roman Tarmat Ltd on 12 July, 2021
                                                                      O.S.A.Nos.147 and 153 of 2021



                                         IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                    DATED:    12.07.2021

                                                          CORAM :

                                        THE HON'BLE MR.SANJIB BANERJEE, CHIEF JUSTICE
                                                             AND
                               THE HON'BLE MR.JUSTICE SENTHILKUMAR RAMAMOORTHY
                                                O.S.A.Nos.147 and 153 of 2021

                     1.The Chief Engineer Highway
                     Metro/Employer,
                     No.1, New Street,
                     Super Bazar Building,
                     Alandur, Chennai 600 016

                     2.The Division Engineer,
                     Highways TNUDP III,
                      C.M.D.P. Division IV
                     Chennai 600 016                                       ...   Appellants

                                   Vs

                     1.M/s.Roman Tarmat Ltd.
                     rep. By its General manager,
                     Mr.N.V.Natarajan

                     2.The Executive Director
                     T.N.Road Infrastructure Development Corporation
                     4th Floor, LLA Building,
                     735, Anna Salai,
                     Chennai 600 002                              ...            Respondents

Appeals filed against the Order of this Court dated 24.11.2020 in O.P.Nos.431 and 413 of 2020.




                     __________

https://www.mhc.tn.gov.in/judis/
                                                                    O.S.A.Nos.147 and 153 of 2021



                               For Appellants        : Mr.R.Shunmugasundaram,
                                                       Advocate-General,
                                                       Assisted by Mr.V.T.Aravind Gosh,
                                                       A.G.P. (CS)

                               For Respondents       : Mr.M.S.Krishnan,
                                                       Senior Counsel,
                                                       for Mr.B.Harikrishnan



                                                 COMMON JUDGMENT

                                          (made by the Hon'ble Chief Justice)

The appeals arise out of a common judgment and order of

November 24, 2020 passed on petitions challenging an arbitral award

of December 28, 2019. The appellants' challenge to the arbitral award

on the ground of the claim being barred by limitation has been

repelled. On the first respondent contractor's challenge to the

counter-claim filed in the arbitral reference by the appellants herein,

the counter-claim has been rejected.

2. The short question raised in seeking to dislodge the

contractor's claim is that the termination of the two contracts was not

questioned within the time referred to in a clause in the contract; and,

as a consequence whereof, the contractor is deemed to have accepted

the termination of the two contracts. The appellants submit that

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

though such ground was squarely taken in course of the proceedings

under Section 34 of the Arbitration and Conciliation Act, 1996 and

even urged in course of the hearing before the arbitration court, it is

apparent from the order impugned that the arbitration court

misconstrued the submission and did not deal with such aspect of the

matter in the judgment and order impugned dated November 24,

2020.

3. The issues involved in the two appeals are identical. The

appellants awarded similar contracts in favour of the respondent

contractor for constructing two stretches of a road for the first ten

kilometer and from the tenth kilometer to the 17th kilometer. Both

contracts required the work to be completed within a certain period of

time and the work to be taken up on a continuous basis.

4. For reasons that are not necessary to be looked into at

present, the contracts were terminated by the employer on April 21,

2011. It is necessary, at this juncture, to notice clause 24 of the

contract in either case that provides as follows:

“If the Contractor believes that a decision given by the Engineer was either outside the authority given to the

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

Engineer by the contract or that the decision was wrongly taken, the decision shall be referred to Adjudicator within 14 days of the notification of the Engineer’s decision”.

5. The relevant provision implies that the engineer had due

authority to take decisions as to the nature of the work and any other

conditions attendant thereto. However, the engineer’s decision was

subject to scrutiny by an adjudicator, who was named in the relevant

contracts, and the adjudicator could receive any grievance that the

contractor would deem necessary to carry from any decision of the

engineer. It cannot be missed that the clause expressly provides that

the objection to the engineer’s decision should be taken to the

adjudicator, “within 14 days of the notification of the engineer’s

decision”.

6. There is also no dispute that the decision to terminate the

contract made on April 21, 2011 by the engineer concerned was not

challenged before the adjudicator within 14 days of the notification

thereof or of notice in such regard being received by the contractor.

Instead, the contractor instituted W.P.No.12392 of 2011 and

W.P.No.12393 of 2011 which were disposed of without any cheer for

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

the contractor except that the contractor was permitted to approach

the adjudicator, if the law so provided.

7. The contractor approached the adjudicator on November 28,

2011, more than seven months after the termination in either case

was notified. The appellants claim that since the relevant clause in

either contract required a decision of the engineer to be carried to the

adjudicator within 14 days of the notification thereof, it implied that

upon the expiry of 14 days and no objection being carried to the

adjudicator, the contractor had accepted the decision. Despite the

clause not providing negative words like ‘not later than’ or ‘not

thereafter’, the appellants insist that the parties by contract fixed a

particular time for an objection to the engineer’s decision to be taken

to the adjudicator and, in the contractor’s failure to adhere to the time

as was consensually fixed, the contractor lost the right to pursue any

objection pertaining to the relevant decision of the engineer that was

not carried to the adjudicator within the time stipulated in the contract.

8. The contention has to be raised to be rejected. However, the

impugned judgment does not refer to it, though the appellants submit

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

that the point was clearly taken as would be evident from ground ‘D’ of

the petition lodged under Section 34 of the said Act:

“D. The learned arbitrator ought to have dismissed the claims of the respondent (the contractor) herein as barred by the law of limitation as the claims were made beyond the time-limit prescribed by the statute i.e. Limitation Act, 1963 and the agreement between the parties (14 days) under Clause 24 of the conditions of contract."

9. However absurd the ground urged by the appellants herein

may have been, when an objection as to limitation – not only on the

basis of a contractual term but also under the governing statute – was

taken, the arbitration court was obliged to deal with such aspect of the

matter. On a reading of the judgment and order impugned dated

November 24, 2020, it is evident that another aspect of limitation

engaged the attention of the arbitration court but the appellants’

contention as to impermissibility of the contractor's claims on the

ground of limitation may have been misconstrued and the fact that the

ground was clearly taken in the petition may have been altogether

overlooked.

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

10. The objection on the ground of clause 24 was taken in

course of the arbitral proceedings and all murmurs of the contractor to

the contrary have to be ignored. The award dated December 28, 2019

clearly records the objection on the ground of limitation “due to the

contractual provisions” in paragraph 11 thereof. The discussion on

such aspect covers several pages of the award before the ground is

rejected, though in somewhat unsatisfactory terms. At least, there is

some substance in the appellants’ grievance that both before the

arbitrator and in the challenge proceedings before the arbitration

court, the substance of the objection raised was not appropriately

received or dealt with. As far as the arbitrator was concerned, the

point was dealt with and the ground dispelled without the appropriate

reasons being indicated. The aspect does not appear to have been

considered at all by the arbitration court, though it appears that the

ground was squarely urged.

11. While dealing with the objection, the arbitrator has referred

to Section 14 of the Limitation Act, 1963 and the period of time that is

excluded when a party bona fide approaches an erroneous forum and

diligently pursues the matter before such wrong forum. In such a case,

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

where the invocation of the jurisdiction of the initial forum must be

bona fide and the prosecution of the matter must be diligent, the time

spent before the wrong forum is excluded while counting the period of

limitation before the subsequent forum. Ordinarily, the contractor

approaching the writ court in this case may not have been regarded as

having approached an erroneous forum since the writ court was an

alternative forum, but not a wrong forum. Accordingly, the reference

to Section 14 of the Act of 1963 by the arbitral Tribunal was

completely unnecessary and utterly inapposite.

12. The arbitrator has next referred to the contractor having

invoked Section 11 of the Act of 1996 to obtain the appointment of the

arbitrator. It is true that an objection on the ground of limitation ought

to be taken in Section 11 proceedings, whether on account of the

substance of the claim being barred by limitation or the right to go to

arbitration being barred by limitation. As is well known, there are two

elements to limitation in arbitration matters: the limitation as to the

subject-matter of the claim and the limitation to proceed in arbitration

in such regard. In either case, if the remedy is barred, there is no

question of an arbitral reference being directed.

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

13. Even though while reversing the previous Constitution Bench

view in such regard, in S.B.P. and Co. vs. Patel Engineering Ltd.

[(2005) 8 SCC 618], the Supreme Court held that objections as to

limitation qua the subject-matter of the claim may be adjudicated by

the Chief Justice or his designate in proceedings under Section 11 of

the Act, it is not entirely impermissible for an objection on the ground

of limitation to be urged before the arbitral tribunal notwithstanding

such ground not having been taken in the previous proceedings under

Section 11 of the Act. To such extent, the arbitrator in this case

erroneously held that merely because the arbitral reference

commenced upon an order passed in proceedings under Section 11 of

the Act, the point of limitation was not open to the respondent in the

reference before it. The arbitrator completely glossed over the

appellants’ reliance on clause 24 and the permissibility of such clause

to be regarded as a clause of limitation despite no words of restriction

or impediment being evident therefrom.

14. As noted above, the issue, though directly and substantially

raised in the challenge to the award, was lost on the arbitration court.

Usually, when a ground of importance is canvassed but is not

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

addressed by an adjudicatory authority, the superior adjudicatory

authority in seisin of a revision or an appeal may not go into the

aspect by itself and may set aside the order impugned before it and

remand the matter for a fresh consideration by the lower adjudicatory

authority. However, a practical view of the matter also needs to be

taken. If the point is of such substance that it cannot be said with a

degree of certainty as to whether the point would be accepted or

rejected, it would be better to allow the adjudicating authority of first

instance to give an opinion thereon since an original adjudication at

the revisional or appellate level on such aspect would deprive the party

which loses the point a court of appeal or a forum of revision.

However, when the revising or appellate authority finds that there is

hardly any merit in the point and it may be summarily dealt with on

the basis of established principles, the time-consuming exercise of

remanding the matter for a fresh adjudication may be avoided.

15. In the present case, it is the fervent appeal of the

respondent that there is no merit in the ground of limitation urged by

the appellants and when the objection taken inherently lacks merit, the

appellate or revisional forum should not send the matter for a fresh

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

consideration and prolong the time spent in court or the suffering of

the parties. It is on such basis that the objection as to limitation as

raised by the appellants herein is taken up for consideration even

though such aspect of the matter did not receive the consideration of

the arbitration court in seisin of the challenge to the award and the

issue was inadequately and inappropriately dealt with by the

arbitrator.

16. For a start, a clause of the kind that is sought to be pressed

into service here by the appellants cannot be read to be a clause in the

nature of limitation since it does not preclude the contractor

approaching the adjudicator beyond a period of 14 days from the

engineer's decision. Logically, it may be said that the clause implies a

sense of limitation; but law is not always dependent on logic and the

experience of law instructs that when a particular act – that would be

permissible in the usual course – is sought to be prohibited, there

must be an express embargo spelt out and not one gleaned out by

implication. Secondly, it does not follow from the clause that merely

because the contractor does not object to the engineer's decision by

carrying a grievance to the adjudicator within 14 days of the

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

engineer's decision, the contractor has no other remedy available.

Thirdly, even if the adjudicator, whose role is that of a mediator or the

like, is not approached, it cannot be said that the clause would prohibit

a civil suit to enforce the contractor's claim or the institution of an

arbitral reference if the contract was governed by an arbitration

clause. Finally, though it is not necessary to comprehensively answer

the issue on such score, what was done by the employer in this case

was to terminate the contract and bring the relationship between the

parties to an end. It is possible that the impact of the clause was

limited to matters pertaining to engineering decisions and directions as

to how the work would proceed or continue and it did not extend to a

seminal decision as the termination of the contract by the employer.

17. At any rate and without prejudice to the above, any

impediment to the natural or legal right of a party to approach a court

or an appropriate tribunal with the relief that it perceives it is entitled

to, would fall foul of Section 28 of the Contract Act, 1872 just as

prescribing a shorter period of limitation to institute the relevant action

will also render the clause void under the same provision.

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

18. For the reasons aforesaid, the ground of limitation urged by

the appellants herein is found to be utterly unmeritorious. It is true

that the aspect should have been adequately dealt with by the

arbitrator and engaged the attention of the arbitration court; but

merely because the ground was raised and may not have been

appropriately or adequately addressed would not imply that the

substance of the ground cannot be assessed even at this stage and

appropriate reasons be indicated to the appellants.

19. The other side of the limitation issue raised by the appellants

pertains to the permissibility of the counter-claim being carried by the

appellants herein before the arbitral tribunal. Such part of the matter

has been appropriately and more than adequately dealt with in the

judgment and order impugned. Merely because an arbitral reference

may have been lodged before the arbitrator on a particular day would

not imply that the period of limitation to file the counter-claim would

begin to be counted from such date. The period of limitation in a

counter-claim starts to run from when the cause of action arises. The

distinction between a counter-claim and a set-off is that a set-off is in

the nature of confession and avoidance and a set-off can be pleaded

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

and asserted notwithstanding any period of limitation; though a

counter-claim on similar grounds cannot be carried beyond the period

of limitation, for the substance of such counter-claim has to stand

independent of the rival principal claim.

20. On facts, the arbitration court in this case found that the

appellants herein had done nothing before lodging the counter-claim

before the arbitrator to stop the clock of limitation running, so to say.

In matters pertaining to arbitration, a claim may be filed before the

arbitrator ten years after the contract is terminated as long as there is

an earlier request for the constitution of an arbitral tribunal since the

commencement of the arbitral reference, within the meaning of

Section 21 of the Act of 1996, is reckoned from the date on which a

request for a reference is made by one party and such request is

received by the other. The clock of limitation stops immediately upon

the receipt of the request by the other party. The subject-matter of the

claim cannot be said to be barred by limitation if the commencement

of the arbitral reference within the meaning of Section 21 of the Act

has happened ten years prior to the statement of claim being lodged

before the arbitrator.

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

21. At the same time, just because the clock of limitation has

stopped for one party to the contract, it does not imply it has stopped

for the other party, too. It would not do for a party to a contract to

receive a request for an arbitral reference, not take any action in

respect thereof and not even pursue its own claim; and then, to wait

for the statement of claim of the other party to be lodged before

starting to count the period of limitation. The period of limitation would

still be running from the time the cause of action accrued to make the

counter-claim irrespective of whatever steps may have been taken by

the other party to the contract. The reasoning in the judgment and

order impugned in such regard, as to the counter-claim of the

appellants herein being hopelessly barred by limitation at the time it

was lodged, cannot be flawed and calls for no interference whatsoever.

22. For the reasons indicated above, the appeals are dismissed

and the arbitral award of December 28, 2019 as upheld and modified

by the judgment and order impugned dated November 24, 2020 is left

untouched, though on some additional grounds not found either in the

award or the impugned judgment.

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

23. O.S.A.Nos.147 of 2021 and 153 of 2021 stand dismissed.

There will, however, be no order as to costs. Consequently,

C.M.P.Nos.6623 and 6711 of 2021 are closed.

                                                                         (S.B., CJ.)      (S.K.R., J.)
                                                                                   12.07.2021

                     Index : yes
                     tar




                     __________

https://www.mhc.tn.gov.in/judis/
                                                                    O.S.A.Nos.147 and 153 of 2021




                     To

The Sub Assistant Registrar (Original Side), Madras High Court.

__________

https://www.mhc.tn.gov.in/judis/ O.S.A.Nos.147 and 153 of 2021

THE HON'BLE CHIEF JUSTICE AND SENTHILKUMAR RAMAMOORTHY, J.

(tar)

O.S.A.Nos.147 and 153 of 2021

12.07.2021

__________

https://www.mhc.tn.gov.in/judis/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter