                                                                    W.P.NOS.26479 & 31327 OF 2017


                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                               DATED : 22.02.2021

                                                      CORAM

                                  THE HONOURABLE MR. JUSTICE M.GOVINDARAJ

                                         WP NOS.26479 AND 31327 OF 2017
                                          AND WMP NO.15152 OF 2020

                     WP NO.26479 / 2017

                     D.Kathirvel
                     State President
                     Tamil Nadu Electricity Board Anna
                        Podu Thozhilalar Sangam
                     (Reg.No.MDS/1916]
                     No.3/2, V.V.Koil Street,
                     Vellala Teynampet, Chennai - 600 086.
                     Cause list amended vide order dated
                     22.02.2021 made in WMP No.15152/2020
                     in WP No.26479/2017)                                        .. Petitioner

                                                          Versus

                     1.The Management of
                         Chairman,
                       Tamil Nadu Electricity Board
                       800, Anna Salai,
                       Chennai - 600 002.

                     2.The Presiding Officer
                       Industrial Tribunal, Tamil Nadu,
                       High Court Buildings,

                     1/25



https://www.mhc.tn.gov.in/judis
                                                                           W.P.NOS.26479 & 31327 OF 2017


                        Chennai - 600 104.

                     3.The President
                       Anna Thozhir Sanga Peravai
                       275, Avvai Shanmugam Salai,
                       Royapettai, Chennai - 600 014.

                     4.Tr.Sankaralingam                                         .. Respondents

PRAYER: Writ Petition filed under Article 226 of the Constitution of India praying to issue a Writ of Certiorari, to call for the records and papers from the file of the 2nd respondent Tribunal in I.D.No.36 of 2007 and quash the Award made therein dated 18.08.2017 insofar as the 2nd respondent Tribunal has rejected the claim made by the petitioner Union in I.D.No.36 of 2007.

                                  For Petitioner   :        Mr.K.M.Ramesh
                                  For Respondent-1 :        Mr.Anand Gopalan
                                                            for M/s.T.S.Gopalan & Co.
                                  For Respondent-4 :        Mr.Praveen Sethia


                     WP NO.31327 / 2017

                     K.S.Sankaralingam                                          .. Petitioner

                                                        Versus

1.The Management of Tamil Nadu Electricity Board Rep. by its Chairman No.800, Anna Salai, Chennai - 600 002.

2.The Presiding Officer Industrial Tribunal Tamil Nadu

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

High Court Buildings, Chennai - 600 104.

3.The President Anna Thozhir Sanga Peravai 275, Avvai Shanmugam Salai, Royapettai, Chennai - 600 014.

4.D.Kathirvel .. Respondents PRAYER: Writ Petition filed under Article 226 of the Constitution of India praying to issue a Writ of Certiorari, to call for the records pertaining to the I.D.No.36 of 2007 from the second respondent Tribunal and quash the award made therein dated 18.08.2017.

                                  For Petitioner   :         Mr.Praveen Sethia
                                  For Respondent-1 :         Mr.Anand Gopalan
                                                             for M/s.T.S.Gopalan & Co.
                                  For Respondent-4 :         Mr.K.M.Ramesh

                                                 COMMON ORDER

The above writ petitions are directed against the Award dated

18.08.2017 passed by the Industrial Tribunal, Tamil Nadu, Chennai, in

I.D.No.36 of 2007.

2.The writ petitions are filed by two individuals claiming

themselves as the President of Tamil Nadu Electricity Board Anna Podhu

Tholizhalar Sangam.

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

3.Instead of delving into the issue as to who is the elected

President of the Union and who is entitled to maintain the writ petition, this

Court is inclined to discuss the main issue as to whether the Award passed

by the Tribunal is sustainable or not.

4.The admitted facts are that the Tamil Nadu Electricity Board

at its initial period engaged Contract Labourers for the purpose of executing

the projects. At one point of time, the volume of the Casual Labourers,

Temporary Workers, Contract Labourers exceeded limit and therefore, the

Electricity Board decided to stop the recruitment. Thereafter,

G.O.Ms.No.1177 dated 28.11.1980 was issued for the purpose of fixing the

pre-requisite qualification for appointment to the lowest post. Accordingly,

the first respondent issued proceedings in B.P.MS (FB) No.38 dated

23.05.1986 amending the service regulations by prescribing qualification

for the post of Helper. It was decided to fill up 7000 vacancies of Helper by

direct recruitment with prescribed qualification. This was challenged by the

Contract Labourers and the Unions and also writ petitions were filed for

regularisation of the Contract Labourers. On 10.04.1990, the Hon'ble

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

Supreme Court in SLP No.1820 of 1990 appointed Hon'ble Mr.Justice

V.Khalid to go into that issue. Justice V.Khalid's commission finding it as

human problem rather than deciding on the validity of the prescription of

the qualification and non-regularisation, submitted a report on 11.02.1991.

In that report, it was observed that 18006 Contract Labourers, as per the list

submitted by the Unions participated shall be regularised along with fresh

candidates possessing qualification in the ratio of 1:1.

5.Accepting the report, 18006 Labourers as well as 7000 fresh

candidates were recruited in a phased manner in the ratio of 1:1. This

process was completed during March 1998. The report also observed that

once the regularisation / appointment of the members in the list submitted

by 3 Unions was completed, liberty was granted to the Board to recruit

candidates with prescribed qualification.

6.In the interregnum period, during 1997-1998, there was a

demand for Bonus, which was resisted by the Management and the Unions

requested at least for ex-gratia payment. Thereafter, the Board decided to

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

pay ex-gratia to those Contract Labourers who were in continuous

engagement for five years or more as on 31.03.1997. A Committee was

constituted to identify those people who have completed five years or more

as on 31.03.1997. Accordingly, 8400 Labourers were identified as eligible

for receiving ex-gratia payment.

7.It is also noted that there were certain anomalies in

regularising the Contract Labourers, for, there was a post of Mazdoor

Trainee, which was abolished. Thus, Mazdoors, who does not require any

qualification were also not regularised. Thereafter, in the year 2005, the post

of Mazdoor Grade - II was revived to accommodate those Mazdoor Grade-II

(Trainee) appointed for two years and thereafter, absorbed as Mazdoor. Out

of 8500 Contract Labourers, 2500 were appointed as Mazdoor Grade-II

during October 2005.

8.In the meanwhile, on 28.06.2005, there was a demand made

by the Unions for further absorption of Contract Labourers. Thereafter,

negotiations were held between the Management and the Unions and during

the conciliation in front of the Commissioner of Labour, a settlement was

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

arrived at. Accordingly, a Settlement under Section 12(3) of the Industrial

Disputes Act, 1947, was entered into on 10.08.2007 and the respondent

Electricity Board agreed to absorb 21,600 Contract Labourers, which

includes those 6,000 Labourers, who were identified by the Committee to

receive ex-gratia payment in a phased manner. Accordingly, on 06.09.2007,

B.P.(CH) No.44, Admin Branch was issued absorbing the 21,600 Contract

Labourers including the 6,000 identified Labourers, who have completed

five years of service as on 31.03.1997. It is pertinent to note that the

petitioners' Union had also participated in the negotiations, but refused to

sign the agreement. However, other Unions have signed the agreement and

the Settlement was finalised. Thereafter, on 09.01.2008, a Committee was

constituted to examine the claims of Contract Labourers not covered by the

Settlement under Section 12(3) of the Act.

9.It is also pertinent to note that the respondent Electricity

Board engaged some Contract Labourers on need basis even prior to

05.01.1998 and continuously engaged them. Thereafter, orders were issued

by the Board on 20.02.2008 and 04.03.2008 to absorb them. Accordingly, in

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

the year 2012, 4037 Contract Labourers were absorbed as Mazdoor

(Trainee).

10.While the matter stood thus, the Contract Labourers

working in the Distribution Circle have approached the Commissioner for

Workmen Compensation for conferment of permanent status and claimed

permanency. The Commissioner for Workmen Compensation has also

granted the relief in favour of them. When the prescribed qualification

under the Settlement dated 10.08.2007 was insisted by the respondents, writ

petitions were filed challenging the 12(3) settlement as well as for further

regularisation of the Contract Labourers. Ultimately, the issue was decided

by a Division Bench of this Court on 24.10.2008 in W.A.Nos.1302 of 2003

etc., batch, wherein the Division Bench has upheld the 12(3) settlement

entered between the parties and the Contract Labourers, who obtained

orders from the Commissioner of Workmen Compensation for permanency,

were directed to work out their remedies in the light of the 12(3) Settlement

dated 10.08.2007.

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

11.The members of the writ petitioners' Union have raised the

dispute and the conciliation ended in failure. On the basis of the failure

report, a reference was made by the Government of Tamil Nadu in G.O.(D)

No.389, Labour and Employment Department, dated 23.05.2007 to the

Tribunal.

12.The main contention of the writ petitioners is that the

Settlement reached between the other Unions will not bind the petitioners'

Union. The learned counsel for the petitioners would contend that the

Hon'ble Supreme Court in G.M. ONGC, SHILCHAR VS. ONGC

CONTRACTUAL WORKERS UNION [2008 (12) SCC 275] has held that

applying Uma Devi's case in all cases mechanically is not correct. The

precedential value of a decision depends of facts and circumstances of each

and every case. It cannot take away the rights of workers indiscriminately

based on sham and nominal contracts. Further, in the judgment of the

Hon'ble Supreme Court in STEEL AUTHORITY OF INDIA LTD. AND

OTHERS VS. NATIONAL UNION WATER FRONT WORKERS AND

OTHERS [2001 (7) SCC 1] it has been held that after introduction of

Contract Labour Regulation and Abolition Act (CLRA) no automatic

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

absorption of the Contract Labourers working in the establishment was

ordered, but after finding the contract to be sham and nominal error as

camouflage, the absorption was ordered.

13.The Hon'ble Supreme Court in MAHARASHTRA STATE

ROAD TRANSPORT CORPORATION AND ANOTHER VS.

CASTERIBE RAJYA P. KARMACHARI SANGHATANA AND OTHERS

[2009 (8) SCC 556] has categorically held that the judgment in Uma Devi's

case will not denude the Industrial and Labour Courts of their statutory

power under Section 30 read with Section 32 of MRTU & PULP Act to

order permanency of the workers, who have been the victim of unfair labour

practice on the part of the employer under item 6 of Schedule IV where the

posts on which they have been working exists.

14.Relying on the rationale laid down by the Hon'ble Supreme

Court in the above judgments, learned counsel for the petitioners would

contend that the engagement of Contract Labourers is sham and nominal

and all the members of the petitioners' union were working directly under

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

the principal employer. Therefore, they are entitled to absorption. The

so-called Settlement dated 10.08.2007 will not bind them as they were

refused to sign the agreement. According to the learned counsel, the

Tribunal has not applied its mind to the oral and documentary evidence in

proper perspective.

15.On the other hand, it is noted that from the contention of the

learned counsel for the respondents, 19 witnesses were examined on the

side of the workers and Exs.W1 to W99 were marked, particularly Exs.W12,

W22, W23, W24 and W31 and exhibits marked on the side of the

Management Ex.M9 and M10 inter alia admits the criteria fixed for

absorption. The Settlement reached by the Unions and the Management

under Section 12(3) of the Act, dated 10.08.2007 is binding on all aspects

viz., number of Contract Labourers to be absorbed, their qualification

among other things. Once the prescription of the qualification is admitted

and that the Settlement dated 10.08.2007 was upheld by the Division Bench,

the petitioners are not entitled to seek any relief contrary to the judgment of

this Court and the Settlement dated 10.08.2007.

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

16.This Court has perused the Award passed by the Tribunal. It

has to be seen as to whether the Tribunal has exercised its power in proper

perspective, applied its mind, adhered to the principles of natural justice and

given its finding based on the evidence placed before it, while passing the

impugned Award.

17.It is noted that the Tribunal has considered the oral evidence

of 19 witnesses presented before it. It is also observed that most of the

witnesses have stated that they have not at any point of time received any

ex-gratia payment. It is pertinent to note that at the first instance, by virtue

of the report submitted by Justice V.Khalid's Commission, 18006 Contract

Labourers were absorbed in a phased manner till 1998. During the

interregnum period, 8500 Labourers were identified as having put in five

years of service as on 31.03.1997 and were paid ex-gratia payment. Later,

on 10.08.2007, a Settlement was reached pursuant to the conciliation in

front of the Commissioner of Labour under Section 12(3) of the Act. Even

though the petitioners' Union states that they have refused to sign the

agreement and it was signed by all other Unions and further contend that it

is not binding on them, the legal position is that the said agreement reached

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

between the parties and signed by majority Unions under Section 12 (3) of

the Act, it is a binding Settlement on all the workmen of the establishment

and also the future employees.

18.Clause-I of the terms of settlement prescribes certain

qualifications for appointment to the posts of Assessor Grade - II, Helper,

Meter Reader and Mazdoor. This settlement was signed by the Board and

majority of the Unions.

19.The Hon'ble Supreme Court in P.VIRUDHACHALAM

AND OTHERS VS. MANAGEMENT OF LOTUS MILLS AND

ANOTHER [1998 (1) SCC 650] has categorically distinguished the

agreements under Section 18(1), 18(3) and 12(3) of the Industrial Disputes

Act, 1947. Para 8 of the said judgment reads as under:

"8. The aforesaid relevant provisions of the Act, therefore, leave no room for doubt that once a written

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

settlement is arrived at during the conciliation proceedings such settlement under Section 12(3) has a binding effect not only on the signatories to the settlement but also on all parties to the industrial dispute which would cover the entire body of workmen, not only existing workmen but also future workmen. Such a settlement during conciliation proceedings has the same legal effect as an award of Labour Court, or Tribunal or National Tribunal or an arbitration award. They all stand on a par. It is easy to visualise that settlement contemplated by Section 12(3) necessarily means a written settlement which would be based on a written agreement where signatories to such settlement sign the agreement. Therefore, settlement under Section 12(3) during conciliation proceedings and all other settlements contemplated by Section 2(p) outside conciliation proceedings must be based on written agreements. Written agreements would become settlements contemplated by Section 2(p) read with Section 12(3) of the Act when arrived at during conciliation proceedings or even outside conciliation proceedings. Thus, written agreements would become settlements after relevant

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

procedural provisions for arriving at such settlements are followed. Thus, all settlements necessarily are based on written agreements between the parties. It is impossible to accept the submission of learned counsel for the appellants that settlements between the parties are different from agreements between the parties. It is trite to observe that all settlements must be based on written agreements and such written agreements get embedded in settlements. But all agreements may not necessarily be settlements till the aforesaid procedure giving them status of such settlements gets followed. In other words, under the scheme of the Act, all settlements are necessarily to be treated as binding agreements between the parties but all agreements may not be settlements so as to have binding effect as provided under Section 18(1) or (3) if the necessary procedure for giving them such status is not followed in given cases. On the aforesaid scheme of the Act, therefore, it must be held that the settlement arrived at during conciliation proceedings on 5-5-1980 between Respondent 1- management on the one hand and the four out of five unions of workmen on the other, had a binding effect

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

under Section 18(3) of the Act not only on the members of the signatory unions but also on the remaining workmen who were represented by the fifth union which, though having taken part in conciliation proceedings, refused to sign the settlement. It is axiomatic that if such settlement arrived at during the conciliation proceedings is binding on even future workmen as laid down by Section 18(3)(d), it would ipso facto bind all the existing workmen who are all parties to the industrial dispute and who may not be members of unions that are signatories to such settlement under Section 12(3) of the Act."

20.Even the Labourers who were represented by the petitioners'

Union though having taken part in the conciliation proceedings, refused to

sign the Settlement, still it will be binding on them. It cannot be denied that

it will not be binding on minority Union.

21.The Hon'ble Supreme Court has also laid down the ratio in

the above judgments that all agreements may not actually be the settlement

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

till the procedure laid down for the purpose is followed. But all the

settlements are necessarily to be treated as binding agreements between the

parties, particularly, the agreements reached between the parties under

Section 12(3) of the Act and also the agreements reached between the

parties, written agreements would become settlement contemplated by

Section 2(p) read with Section 12(3) of the Act when arrived at during

conciliation proceedings or even outside conciliation proceedings. Thus,

written agreements would become settlement after relevant procedural

requirements for arriving at such settlements are followed.

22.In the instant case, it is admitted that a 12(3) settlement was

arrived at between the parties before the Commissioner of Labour on

10.08.2007. Therefore, it is binding on all the parties including those

appointed in the future also. It is also relevant to note that the above said

Settlement dated 10.08.2007 has been upheld by a Division Bench and a

direction was issued to the Contract Labourers to work out their remedies in

terms of 12(3) Settlement. As found by the Tribunal, except WW17, all

other candidates did not receive ex-gratia payment and they would affirm

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

the same in their oral evidence. Admittedly, all these Contract Labourers

were not qualified as prescribed under the 12(3) Settlement dated

10.08.2007. Therefore, it goes without saying that the petitioners are not

entitled to claim absorption outside the scope of 12(3) Settlement.

23.As observed above, at the risk of repetition, I reiterate that

the 12(3) Settlement is binding upon all the workmen including the writ

petitioners. Therefore, the claim for absorption shall be within the terms of

Settlement dated 10.08.2007.

24.In the instant case, the petitioners failed to prove that they

are qualified and eligible to get absorption. The petitioners' Union has not

come out with a clear case that as to how many members of their Union had

completed five years of service as identified by the Committee constituted

by the respondent Board. It is also not specified as to how many number of

Contract Labourers engaged on need basis prior to 06.01.1998 and

continued in service. Even WW1 would state that he was engaged till 1998

after that he did not work. The Union could give exact details as to the

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

number of workmen who were engaged on need basis prior to 06.01.1998.

Further, the Tribunal has gone into the representation made by the Union,

wherein at the first instance, vide Ex.W3 dated 29.01.2001, it was

mentioned as 10,442 Contract Labourers / Mazdoors. In Ex.W4 dated

16.02.2001, it was mentioned as 10,489 Contract Labourers / Mazdoors. In

Ex.W5 dated 09.03.2001 it was mentioned as 10,551 Contract Labourers /

Mazdoors, in Ex.W6 dated 05.04.2001, it was mentioned as 10,586 Contract

Labourers / Mazdoors, in Ex.W7 dated 12.04.2001 it was mentioned as

10,592 Contract Labourers / Mazdoors. But the petitioners' Union could not

specifically state out of this 10,592 Contract Labourers / Mazdoors, how

many of them were absorbed as per the Settlement dated 10.08.2007

possessing the prescribed qualification and how many of them were

absorbed as Mazdoors and how many of them were not engaged for want of

prescribed qualification. Without there being any clear picture, the Union

claims absorption of all the workmen.

25.The Tribunal has categorically applied its mind to the above

factum and held that the judgments relied on by the petitioners in ONGC's

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

case (cited supra), Steel Authority's case (cited supra) and Maharashtra

State Road Transport Corporation's case (cited supra) will not apply to the

instant case.

26.It is important to note that the absorption is not made in

violation of labour laws. In fact, the agreement was reached between the

parties under Section 12(3) of the Act and as per the agreement, the

absorption / regularisation / appointments are made. It is also important to

note that the said 12(3) Settlement has been upheld by a Division Bench of

this Court. In that event, it cannot be said that there is unfair labour practice

and the Management is acting upon sham and nominal contracts. Since the

petitioners' Union has failed to prove that they are eligible to get absorption

as per the Settlement and / or otherwise, it is not entitled to the relief sought

for. The Award of the Tribunal does not suffer any illegality or discrepancy

and thereby, it is confirmed.

27.However, the learned counsel for the petitioners would

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

contend that many of the members of the Union fulfilled the criteria laid

down by the respondent Board. Many of them are qualified to hold the posts

and they have put in more than five years of service and received ex-gratia

payment. They have material documents to prove their eligibility to get

absorption even otherwise.

28.Considering the submissions made, liberty is granted to the

Members of the petitioners' Union to submit the relevant materials to the

first respondent within a period of four weeks from the date of receipt of a

copy of this order and a further direction is given to the first respondent to

consider and dispose of the same, on merits and in accordance with law,

within a period of six weeks from the date of receipt of such

representations.

29.With these observations and directions, the writ petitions are

disposed of. No costs. Consequently, connected miscellaneous petition is

closed.

22.02.2021 Index : Yes / No Internet : Yes / No TK

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

To

1.The Chairman Management of Tamil Nadu Electricity Board 800, Anna Salai, Chennai - 600 002.

2.The Presiding Officer Industrial Tribunal, Tamil Nadu, High Court Buildings, Chennai - 600 104.

M.GOVINDARAJ, J.

TK

WP NOS.26479 AND 31327 OF 2017

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

22.02.2021

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

W.P.NOS.26479 OF 2017 AND 31327 OF 2017

M.GOVINDARAJ, J.

This matter is listed today under the caption "for being mentioned" at the instance of the learned counsel for the petitioner.

2.It is brought to the notice of this Court that WMP No.15152 of 2020 in W.P.No.26479 of 2017 which was filed for amending the short cause title of the petitioner from his individual capacity to one of the official capacity as State President of the Union was not ordered and it was closed without granting the prayer sought for. Now that, considering the order passed in the main writ petition, the miscellaneous petition filed for amendment in WMP No.15152 of 2020 in W.P.No.26479 of 2017 is ordered as prayed for.

3.Registry is directed to carry out necessary amendment in the cause title and issue fresh order copy to the parties.

21.12.2021 VUM/TK

https://www.mhc.tn.gov.in/judis W.P.NOS.26479 & 31327 OF 2017

M.GOVINDARAJ, J.

VUM/TK

W.P.NOS.26479 OF 2017 AND 31327 OF 2017

21.12.2021

https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter