Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The Union Of India vs Famectech
2021 Latest Caselaw 2717 Mad

Citation : 2021 Latest Caselaw 2717 Mad
Judgement Date : 5 February, 2021

Madras High Court
The Union Of India vs Famectech on 5 February, 2021
                                                                             S.A..No.1013 of 2008



                                   IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                              DATED :      05.02.2021

                                                      CORAM

                                   THE HONOURABLE MR. JUSTICE T. RAVINDRAN

                                                   S.A.No. 1013 of 2008
                                                        and
                                                  M.P.No.1 of 2008

                     The Union of India
                     Rep. by Garrison Engineers
                     Fort. St. George
                     Chennai 600 009                                           ... Appellant
                                                        Vs.

                     1. Famectech
                        No.17, N.P. Developed Plot
                        Industrial Estate, Guindy
                        Chennai 600 097

                     2. R.S. Kanwar
                        Superintending Engineers
                        SOI (Services)
                        Chief Engineer Chennai Zone
                        Island Grounds, Chennai 600 009                      ... Respondents

                     Prayer: Second Appeal filed under Section 100 of the Civil Procedure
                     Code against the       Judgment of the learned Appellate authority, the
                     Principle Judge, City Civil Court at Chennai dated 24.07.2006 made in
                     Appeal Suit No. 583/05 confirming the judgment and order dated

                     Page 1 of 14

https://www.mhc.tn.gov.in/judis/
                                                                                S.A..No.1013 of 2008



                     30.03.1999 passed by the learned III Asst. Judge, City Civil Court,
                     Chennai in O.S.No.3054/95.


                                            For Appellant     : Mr. S. Janarthanam, SPC


                                            For Respondents
                                            For R1            : Mr. P.B. Ramanujam
                                            For R2            : No appearance

                                                 JUDGMENT

Challenge in this second appeal is made to the judgment and

decree dated 24.07.2006 passed in Appeal Suit No. 583/05 on the file of

the Principle Judge, City Civil Court, Chennai confirming the judgment

and decree dated 30.03.1999 passed in O.S.No.3054/95 on the file of the

III Assistant Judge, City Civil Court, Chennai .

2. The unsuccessful plaintiff in the courts below is the

appellant in the Second Appeal.

https://www.mhc.tn.gov.in/judis/ S.A..No.1013 of 2008

3. The plaintiff has laid the suit against the defendants under

Section 14 of the Indian Arbitration Act, 1940 for directing the sole

Arbitrator, namely, the second defendant to file the award published by

him on 19.10.1994 into the Court and on such production to pass a

decree in favour of the plaintiff and against the first defendant in terms of

the award passed by the second defendant with costs.

4. Shorn of unnecessary particulars, it is seen that the case of

the plaintiff is that the plaintiff had called for tenders from various

contractors for relaying the water supply line at the family quarters in

Nandanam and the lowest tender was submitted by the first defendant

and thereafter, on 10.02.1992, a revised amount of Rs.2,18,945/- for

carrying out the special requirements for the said quarters was submitted

by the first defendant, which was accepted by the plaintiff on 18.03.1992

by way of a letter and when the plaintiff insisted the first defendant for

signing the contract and to receive the work order, the first defendant did

not put its signature nor commenced the work at the site as per the terms

of the contract and despite the forwarding of the work order through

https://www.mhc.tn.gov.in/judis/ S.A..No.1013 of 2008

registered post on 21.04.1992, there had been no response from the first

defendant and consequently, the plaintiff was unable to complete the

work and left with no other alternative, gave a final warning to the first

defendant on 28.07.1992 and had accepted the tender of another agency

on 21.11.1992 for Rs.2,64,505/- and the entire work was completed on

23.03.1993 and on account of the abovesaid facts, according to the

plaintiff, it had sustained loss and thus, the first defendant had to

compensate the plaintiff for the breach of the contract by the first

defendant for a sum of Rs.32,689.38 and the first defendant failed to pay

the said amount to the plaintiff. Therefore, according to the plaintiff, it

had appointed a sole arbitrator as per the terms of the contract, namely,

the second defendant and the sole arbitrator had issued a notice to both

the parties and passed the award on 19.10.1994 and even thereafter, the

plaintiff's request to the first defendant to settle the claim did not yield

any positive response from the first defendant and the arbitrator had

signed and published the award for a sum of Rs.32,689.38 without costs

or interest and the plaintiff had received the award published and signed

by the arbitrator on 24.10.1994 at Madras and therefore, the plaintiff's

https://www.mhc.tn.gov.in/judis/ S.A..No.1013 of 2008

claim is within the time prescribed under law and hence, the suit against

the first defendant is filed.

5. It is seen that the arbitrator, who had been arrayed as the

second defendant in the suit had remained exparte both in the suit and in

the first appeal.

6. The first defendant resisted the plaintiff's suit contending

that the plaintiff's suit is hopelessly barred by limitation and the arbitrator

is none other than the officer of the plaintiff who is stated to have made

the award and though the award was claimed to be published after giving

notice to the parties on 19.10.1994 and from the said date of the notice,

the plaintiff, as per law, is required to file the award of the arbitrator

within 30 days as per Article 119 of the Arbitration Act. The suit having

been filed on 23.11.1994 beyond 30 days is clearly barred by limitation.

Further it is also put forth by the first defendant that the claim of the

plaintiff that he had received the award on 24.10.1994 is incorrect as in

the plaint the date of receipt of the award has been originally mentioned

https://www.mhc.tn.gov.in/judis/ S.A..No.1013 of 2008

as 21.10.1994 in several places and also the date had been corrected

from 21.10.1994 to 24.10.1994 solely for the purpose of showing the

limitation period as if the suit is filed within the time allowed by law

from the date of receipt of the award and therefore, the first defendant

contended that the plaintiff's suit is barred by limitation and liable to be

dismissed.

7. It is found that neither the plaintiff nor the first defendant

had adduced oral and documentary evidence in support of their case and

hence the courts below had proceeded to dispose of the case laid by the

plaintiff based on the documents produced along with the plaint as well

as the pleas put forth by the parties and resultantly, it is noted that both

the trial court as well as the first appellate court has held that the

plaintiff's suit is clearly barred by limitation. Impugning the judgment

and decree of the courts below, the plaintiff has preferred the second

appeal.

https://www.mhc.tn.gov.in/judis/ S.A..No.1013 of 2008

8. The plaintiff has laid the suit in the form of Original Petition

directing the second defendant, the arbitrator, to file the award published

on 19.10.1994,which, according to the plaintiff, was passed in respect of

the dispute arising between the plaintiff and the first defendant. As per

the pleas put forth by the plaintiff in the plaint though the tender of the

first defendant had been originally accepted, it is noted that the revised

tender had been submitted by the first defendant which was also accepted

by the plaintiff. However, the plaint clearly avers that the first defendant

did not sign the contract nor received the work order to undertake the

work specified by the plaintiff in the tender. That apart, the first

defendant had also failed to proceed with the work despite the final

warning given by the plaintiff and hence, the plaintiff had been

necessitated to hand over the work under question to the third party.

Therefore, the plaintiff has to establish clearly that there has been a clear

concluded contract between the plaintiff and the first defendant for the

specified work mentioned by the plaintiff in the tender. If there is no

contract, as such, between the parties nothing would flow from the

alleged passing of the award by the arbitrator, namely, the second

https://www.mhc.tn.gov.in/judis/ S.A..No.1013 of 2008

defendant.

9. When the parties had not endeavoured to adduce evidence in

respect of their respective claims, as noted by the courts below, there is

nil material on the part of the plaintiff to establish that a concluded

contract had been entered into between the plaintiff and first defendant

and that there is a clause contained in the contract for appointing an

arbitrator in the case of any dispute arising out the said contract. When it

is admitted that the first defendant had not even signed the contract sent

to him, therefore, it is seen that as concluded by the courts below, the

appointment of an arbitrator on the part of the plaintiff to resolve the

dispute between the parties is found to be not legally sustainable.

10. Even the award copy has not been, as such, exhibited in the

court. Be that as it may, when according to the plaintiff the arbitrator has

signed the award on 19.10.1994 and the same had been received by the

plaintiff on 21.10.1994, it is not made clear by the plaintiff as to why the

date of receipt of the award mentioned as 21.10.1994 in the plaint in all

the places had been corrected as 24.10.1994 wherever it is mentioned and

https://www.mhc.tn.gov.in/judis/ S.A..No.1013 of 2008

accordingly, according to the first defendant, the plaintiff had not

actually received the award on 24.10.1994 as claimed by it and by way of

correcting the date, as above pointed out, had endeavoured to bring its

suit within the limitation period by committing fraud upon the court and

with reference to the abovesaid factors, no proper explanation is forth

coming on the part of the plaintiff.

11. When the first defendant had denied the receipt of the

award by the plaintiff from the arbitrator, it is the duty of the plaintiff to

produce the copy of the award delivered to him and the date of receipt of

the award was only on 24.10.1994 as mentioned in the plaint and thereby

establish that the plaintiff's suit is in time. As held by the courts below,

the plaintiff has not chosen to examine any person to safely hold that the

award had been received by the plaintiff's office on 24.10.1994 only.

The plaintiff being the public office ought to have maintained the

despatch and receipt of tapal received in the office. The said register

should have been produced to show that the award was received by the

plaintiff only on 24.10.1994 as per the correction made in the plaint.

https://www.mhc.tn.gov.in/judis/ S.A..No.1013 of 2008

Therefore, the courts below are found to be justified in drawing adverse

inference against the plaintiff for failing to place the best evidence to

show that the award of the arbitrator had been really received by the

plaintiff only on 24.10.1994.

12. In the light of the abovesaid discussions, as rightly

contended by the first defendant and as rightly concluded by the courts

below, when there is no material on the part of the plaintiff to determine

that it had received the award only on 24.10.1994, the courts below are

justified in assuming that the notice of the award was given to the parties

on 19.10.1994 i.e., the date of the award and thereafter only it has been

published by the arbitrator and so calculated, it is found that particularly

considering the plea of limitation as provided under Article 119 of the

Limitation Act, the time limit being given is only 30 days and by the

abovesaid calculation, the period of limitation would expire by

20.11.1994 and even assuming that the award, as originally stated in the

plaint i.e. 21.10.1994 is taken into consideration and the limitation period

is calculated, the limitation for the suit would expire by 22.11.1994 on

https://www.mhc.tn.gov.in/judis/ S.A..No.1013 of 2008

factual matrix and when the plaintiff is found to have presented the suit

before the Court only on 23.11.1994 and when there is no acceptable

cause put forth by the plaintiff as to how it would be entitled to seek the

exemption as provided under Order 7 Rule 6 CPC, in all, the courts

below have rightly concluded that the plaintiff's suit is hopelessly barred

by limitation. As above pointed out, the plaintiff having failed to

establish that there is a concluded contract between the plaintiff and the

first defendant and the said contract had been reduced into writing and

the contract contains the clause for appointment of an arbitrator for

deciding the dispute between the parties, above all, in the light of the

abovesaid discussions, when the plaintiff's suit is not established to have

been laid within the time laid by the law, the courts below are justified in

declining the reliefs sought for in the suit. The reasonings and the

conclusions of the courts below for dismissing the plaintiff's suit for the

reasons including the point of limitation when found to be based on

proper appreciation of the materials available on record and on the point

of law and when no valid reason has been projected by the plaintiff for

warranting any interference to the same, it is seen that no substantial

https://www.mhc.tn.gov.in/judis/ S.A..No.1013 of 2008

question of law is involved in the second appeal.

13. For the reasons aforestated, the judgment and decree

Judgment and decree dated 24.07.2006 passed in Appeal Suit No. 583/05

on the file of the Principle Judge, City Civil Court, Chennai, confirming

the judgment and decree dated 30.03.1999 passed in O.S.No.3054/95 on

the file of the III Assistant Judge, City Civil Court, Chennai, are

confirmed. Resultantly, the second appeal is dismissed with costs.

Consequently, connected miscellaneous petition is closed.

05.02.2021 Index: Yes/No Internet: Yes/No Speaking/Non-Speaking order bga

To

1. The Principle Judge, City Civil Court, Chennai

2. The the III Assistant Judge, City Civil Court, Chennai,

3. The Section Officer, VR Section, High Court, Madras

4. Famectech No.17, N.P. Developed Plot Industrial Estate, Guindy

https://www.mhc.tn.gov.in/judis/ S.A..No.1013 of 2008

Chennai 600 097

https://www.mhc.tn.gov.in/judis/ S.A..No.1013 of 2008

T. RAVINDRAN, J.

bga

S.A.No.1013 of 2008

05.02.2021

https://www.mhc.tn.gov.in/judis/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter