Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S.Northern Freight Carriers vs India
2021 Latest Caselaw 24316 Mad

Citation : 2021 Latest Caselaw 24316 Mad
Judgement Date : 10 December, 2021

Madras High Court
M/S.Northern Freight Carriers vs India on 10 December, 2021
                                                                     WP Nos.7506 to 7511 of 2008


                                  IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                 DATED : 10-12-2021

                                                       CORAM

                              THE HONOURABLE MR. JUSTICE S.M.SUBRAMANIAM

                                            WP Nos.7506 to 7511 of 2008


                     M/s.Northern Freight Carriers,
                     Partnership Firm, represented by its
                     Partner, B.K.Garg,
                     No.274, Linghi Chetty Street,
                     Chennai – 600 001.                     ..   Petitioner in WP 7506/2008

                     G.S.Anand,
                     Proprietor of M/s.Karishma Express
                       Transport Co.,
                     No.280, Walltax Road,
                     Park Town,
                     Chennai – 600 003.                     ..   Petitioner in WP 7507/2008

                     M/s.Bic Logistics Ltd.,
                     Represented by its General Manager,
                     New No.109 (Old No.53),
                     Linghi Chetty Street,
                     2nd Floor,
                     Chennai-600 001.                    ..      Petitioner in WP 7508/2008

                     M/s.Green Express,
                     Represented by its Manager/Authorised
                       Signatory,
                     No.31, Stringer Street, Broad,
                     Chennai – 600 108.                  ..      Petitioner in WP 7509./2008
                     1/14


https://www.mhc.tn.gov.in/judis
                                                                   WP Nos.7506 to 7511 of 2008


                     M/s.Indo Arya Central Transport Ltd.,
                     Represented by its Dy. General Manager,
                     No.49, Broadway,
                     Chennai – 600 108.                ..      Petitioner in WP 7510/2008

                     M/s.Om Air Freight Ltd.,
                     Represented by its Manager/Authorised
                       Signatory,
                     No.97, Samy Pillai Street,
                     Choolai,
                     Chennai – 600 112.                ..      Petitioner in WP 7511/2008



                                                        vs.


                     Union of India,
                     Owning Southern Railway,
                     Represented by its General Manager,
                     Park Town,
                     Chennai – 600 003.                ..      R-1 in all WPs

                     The Chief Commercial Manager,
                     Southern Railway,
                     Chennai-3.                        ..      R-2 in all WPs

                     The Chief Traffic Manager,
                     Southern Railway,
                     Chennai-3.                        ..      R-3 in all WPs


                     The Chief Commercial Manager (FM),
                     Baroda House,
                     Northern Railway,
                     New Delhi.                      ..        R-4 in all WPs
                     2/14


https://www.mhc.tn.gov.in/judis
                                                                       WP Nos.7506 to 7511 of 2008




                                  WP 7506 of 2008 is filed under Article 226 of the Constitution of
                     India, praying for the issuance of a Writ of Certiorari, calling for the records
                     relating to the impugned order of the third respondent herein dated

26.02.2008 in No.C.441/II/10/Misc./overloading and quash the same.

WP 7507 of 2008 is filed under Article 226 of the Constitution of India, praying for the issuance of a Writ of Certiorari, calling for the records relating to the impugned order of the third respondent herein dated 26.02.2008 in No.C.441/II/10/Misc./overloading and quash the same.

WP 7508 of 2008 is filed under Article 226 of the Constitution of India, praying for the issuance of a Writ of Certiorari, calling for the records relating to the impugned order of the third respondent herein dated 10.03.2008 in No.C.206/86/40/38/VPU/Leasing/Ten.27/BIC and quash the same.

WP 7509 of 2008 is filed under Article 226 of the Constitution of India, praying for the issuance of a Writ of Certiorari, calling for the records relating to the impugned order of the third respondent herein dated 26.02.2008 in No.C.441/II/10/Misc./overloading and quash the same.

https://www.mhc.tn.gov.in/judis WP Nos.7506 to 7511 of 2008

WP 7510 of 2008 is filed under Article 226 of the Constitution of India, praying for the issuance of a Writ of Certiorari, calling for the records relating to the impugned order of the third respondent herein dated 26.02.2008 in No.C.441/II/10/Misc./overloading and quash the same.

WP 7511 of 2008 is filed under Article 226 of the Constitution of India, praying for the issuance of a Writ of Certiorari, calling for the records relating to the impugned order of the third respondent herein dated 10.03.2008 in No.C.206/86/40/38/VPU/Leasing/Ten.34/2615/16 and quash the same.

For Petitioner in WP 7506/2014 : Mr.R.Selvakumar

For Petitioner in WPs 7507to7511/2014: Mr.Guru Prasad for Ms.Shanmugavalli Sekar

For Respondents in all WPs : Mr.P.T.Ramkumar

COMMON ORDER

The order of termination of contract by the Railways, is under

challenge in all these writ petitions.

2. The petitioners are Transport Carriers undertaking transport

https://www.mhc.tn.gov.in/judis WP Nos.7506 to 7511 of 2008

of commercial materials. The petitioners were awarded lease rights of

carrying various goods in Parcel Van of Trains. The periods mentioned in the

Agreement For Lease are on Round Trip basis.

3. It is not in dispute that the Memorandum of Agreement signed

between the parties provides terms and conditions of including for termination

of contract.

4. The learned counsel for the petitioners states that before

issuing the order impugned, no show cause notice or opportunity was

provided to the petitioners and therefore, the order impugned is in violation of

principles of natural justice.

5. The learned counsel for the petitioners is of an opinion that

the petitioners are not committed any such allegation of overloading and the

Railway is having the head of not weighing the materials properly. On several

occasions, refunds were made in favour of the petitioners and therefore, the

order of termination is untenable.

https://www.mhc.tn.gov.in/judis WP Nos.7506 to 7511 of 2008

6. The learned counsel for the petitioners reiterated that in

respect of the contractual obligations these writ petitions are maintainable.

The petitioners relied on the judgment of the Hon'ble Supreme Court of India

and states that the opportunity to defend the case has not been provided and

therefore, these writ petitions are maintainable.

7. The learned counsel for the petitioners drew the attention of

this Court with reference to the terms and conditions of the contract and also

contended that the order of termination is cryptic and not containing any

reasons and thus, it is liable to be set aside.

8. The learned counsel for the respondent-Railways disputed the

abovesaid contentions of the petitioners by stating that the transactions

between the petitioner and the Southern Railways are on contract basis and

admittedly, the agreement had been signed between the parties.

https://www.mhc.tn.gov.in/judis WP Nos.7506 to 7511 of 2008

9. As per Clause 10 of the terms and conditions of the

agreement, the contract is liable to be terminated unilaterally by the Railways

without giving any prior notice if overloading on re-weighment is detected on

three occasions. Relying on the said conditions in the contract, the learned

counsel for the respondents reiterated that no prior notice is contemplated

under the contract and the contract was admittedly signed by the petitioners.

10. Whenever overloading of re-weighment is detected and if it

exceeds the three times, then the Railways has got powers to terminate the

contract by invoking Clause 10 of the agreement. However, in the present

case, show cause notice was issued to the petitioners on 03.07.2007,

categorically stating that as per surprise checks conducted overloading has

been detected. The details of the overloading are also provided in the show

cause notice and the petitioner was provided with an opportunity to submit

their reply within ten days.

11. Pertinently, the petitioners have submitted their objections

https://www.mhc.tn.gov.in/judis WP Nos.7506 to 7511 of 2008

on 24.11.2007, which is enclosed by the petitioners themselves in the typed

set of papers filed along with these writ petitions. They have raised certain

objections and the Railways have taken a decision to terminate the contract as

the overloading exceeds more than three occasions and accordingly issued the

impugned order of termination.

12. Earlier the learned counsel for the respondents brought to the

notice of this Court that on similar circumstances, rejected the relief in WP

No.5214 of 2010 dated 20.09.2010. Further, in the agreement between the

petitioners and the respondents, arbitration clause has been provided and the

petitioners also in the event of any such contractual disputes, have to invoke

the arbitration clause for the purpose of adjudication of the issues. Thus these

writ petitions are not maintainable and the arbitration clause provided in

clause 5 of he agreement and admittedly, these writ petitions are not invoking

the arbitration clause. In respect of arbitration clause, the Hon'ble Supreme

Curt of India in W.A.Nos.2470 and 2471 of 2010 passed an order on

06.12.2010, wherein the relevant paragraphs 10 to 13, the Hon'ble Supreme

Court held as under:-

https://www.mhc.tn.gov.in/judis WP Nos.7506 to 7511 of 2008

"10. It is also useful to refer to Clause 24.3 of the Agreement, which reads as under: -

In the event of any difference of opinion or dispute between the Railway Administration and the Leaseholder as to the respective rights and obligations of the parties hereunder of as to the true intent and meaning of these presents or any articles of conditions thereof. Such difference of opinion shall be referred to the sole arbitrator, who shall be a Gazetted Railway Officer appointed by the General Manager, Southern Railway, Chennai for the time being whose decision shall be final, conclusive and binding on the parties, the intention of the parties being that every matter in respect of this agreement must be decided by him a sole arbitrator and not taken to a Civil Court. All disputes are subject to the territorial jurisdiction of courts located in Chennai only.

11. From the aforesaid two clauses, it is evidently clear that the agreements were for a period of three years, which can be extended for a further period of two years, subject to satisfactory performance by the appellant. The

https://www.mhc.tn.gov.in/judis WP Nos.7506 to 7511 of 2008

learned single Judge found that the appellant violated the terms and conditions of the contract, for which penalty was imposed and the same was deposited by the appellant.

12. In the facts and circumstances of the case, we are of the definite view that a writ of mandamus cannot be issued directing the respondents to extend the lease for a further period of two years. Admittedly, the contract in question is not a statutory contract, rather a commercial contract having an arbitration clause also. Hence, the relief sought for by the appellant is not only hit by the provisions of the Specific Relief Act, 1963, but also the writ jurisdiction cannot be invoked having regard to the arbitration clause contained in the agreement.

13. For the reasons aforesaid, we do not find any merit in these appeals, and accordingly, they are dismissed. No costs. Consequently, miscellaneous petitions are closed."

It is brought to the notice of this Court that WP No.7506 of 2008 is filed by

the very same petitioner, namely, M/s.Northern Freight Carriers.

https://www.mhc.tn.gov.in/judis WP Nos.7506 to 7511 of 2008

13. This Court is of the considered opinion that contractual

obligations and violations of terms and conditions of contract cannot be

adjudicated in the writ proceedings. Only on exceptional circumstances, the

Court entertains the writ petitions filed against certain contractual obligations.

The factual disputes and the issues involved are to be decided by way of an

elaborate adjudication based on documents in original and evidences.

14. Contrarily, the High Court cannot enter into an adjudication

of this nature which involves scrutinisation of documents in original. Further

the arbitration clause has been agreed between the parties. Thus, the

petitioners have to invoke the arbitration clause for the purpose of resolving

the issues and contrarily, the petitioners have filed all these writ petitions by

merely stating that no show cause notice was issued to the petitioners before

passing the order of termination.

15. However, the respondents could able to establish that notice

was issued and the petitioners also filed their objections and thereafter

termination order was issued. Even in the absence of show cause notice,

https://www.mhc.tn.gov.in/judis WP Nos.7506 to 7511 of 2008

clause 10 of the agreement stipulates that without prior notice termination can

be issued if the overloading exceeds for more than three occasions.

16. This Court is of the considered opinion that regarding the

weighment or re-weighment of overloading and the facts involved as well as

the measurements or otherwise, the Authorities are bound to invoke the

arbitration clause. Even in the absence of arbitration clause, they are bound to

approach the Competent Civil Court of Law for effective adjudication of the

issues. Contrarily, the High Court cannot adjudicate such issues in the writ

proceedings under Article 226 of the Constitution of India and as far as these

writ petitions are concerned, the period of contract expired long back and

further the learned counsel for the respondents brought to the notice of this

Court that the petitioners were re-engaged by the revoking the cancellation.

17. This being the facts and circumstances, if at all any

grievance exists with reference to the factual issues or otherwise, the

petitioners are at liberty to invoke the arbitration clause or to approach the

Competent Civil Court of Law, as the case may be, for the purpose of

https://www.mhc.tn.gov.in/judis WP Nos.7506 to 7511 of 2008

redressal of such grievances. However, it is made clear that in the event of the

petitioners approaching the Arbitrator or the Civil Court, the issues are to be

decided independently uninfluenced by any of the observations made in these

writ petitions.

18. With the abovesaid observations, the writ petitions stand

dismissed. However, there shall be no order as to costs.

10-12-2021 Index : Yes/No.

Internet : Yes/No.

Speaking Order/Non-Speaking Order.

Svn

S.M.SUBRAMANIAM, J.

Svn

To

1.The General Manager, Union of India, Owning Southern Railway, Park Town,

https://www.mhc.tn.gov.in/judis WP Nos.7506 to 7511 of 2008

Chennai – 600 003.

2.The Chief Commercial Manager, Southern Railway, Chennai-3.

3.The Chief Traffic Manager, Southern Railway, Chennai-3.

                     4.The Chief Commercial Manager (FM),
                       Baroda House,
                       Northern Railway,
                       New Delhi.                            WPs 7506 to 7511 of 2008




                                                                            10-12-2021







https://www.mhc.tn.gov.in/judis

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter