Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Roman Tarmat Limited vs M/S. It Expressway Limited
2021 Latest Caselaw 16111 Mad

Citation : 2021 Latest Caselaw 16111 Mad
Judgement Date : 9 August, 2021

Madras High Court
Roman Tarmat Limited vs M/S. It Expressway Limited on 9 August, 2021
                                                                              O.P.No.306 of 2015

                                   IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                   Dated: 9/8/2021

                                                     CORAM

                                   THE HONOURABLE Mr.JUSTICE N. SATHISH KUMAR

                                                 O.P.No.306 of 2015
                                                       and
                                                  A.No.850 of 2020
                     Roman Tarmat Limited
                     rep. By its General Manager
                     Door No.6, Plot No.60
                     15th Cross Street, Tansi Nagar
                     Velacherry
                     Chennai 600 042.               ...          Petitioner
                                                          Vs
                     1. M/s. IT Expressway Limited
                        171 II Floor, TNMB Building
                        South Kesavaperumalpuram
                        Pasumpon Muthuramalingam Road
                        (Greenways Road) Raja Annamalaipuram
                        Chennai 600 028.

                     2. S.P.Krishnamoorthy
                        Presiding Arbitrator
                        C/o.Dr.K.Vasantha
                        New No.1, Old No.9 Police Commissioner Office Road
                        Opp. To Police Hospital
                        Egmore,
                       Chennai 600 008.

                     3. Mr.B.K.Thanupillai
                        Arbitrator
                        Flat No.4-10-1 Arihant Majestic Towers

                     1/18


https://www.mhc.tn.gov.in/judis/
                                                                                      O.P.No.306 of 2015

                          J.N.Salai, Koyambedu
                          Chennai 600 107.              ...          Respondents

                     PRAYER : Petition filed under Section 34                of the Arbitration and

                     Conciliation Act, 1996, to set aside the arbitral award dated 2/8/2014 passed

                     by the respondents 2 to 4.

                               For Petitioner          ...   Ms.Nalini Chidambaram
                                                  Senior Counsel
                                                  for Ms.C.Uma

                               For Respondents           ...   Mr.D.Balaraman
                                                  for R.1.
                                                            ------

                                                         ORDER

This Original Petition has been filed, to set aside the arbitral award,

dated 2/8/2014, passed by the respondents 2 to 4, directing the petitioner to

pay a sum of Rs.9,09,40,880/- to the first respondent.

2. The brief facts which lead to the filing and disposal of this

Original Petition are as follows:-

3. A contract was entered into between the petitioner and first

respondent, for construction of service road and foot path on LHS and RHS

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

in Rajiv Gandhi Salai (IT corridor), Chennai, Tamil Nadu. The salient

features of the contract agreement are as under:-

                                        1   Date of submission of bid      23/2/2020
                                        2   Isuse of letter of Intent      31/3/2010
                                        3   Date   of       signing      of 12/4/2010
                                            Agreement
                                        4   Date of commencement of 12/4/2010
                                            work
                                        5   Time period for completion 12 months
                                            of work
                                        6   Contractual       date       of 11/4/2011
                                            completion
                                        7   Contract price       as     per Rs.31,75,30,5
                                            Agreement                       60/-



4. The first respondent terminated the contract for slow progress and

for fundamental breaches committed by the petitioner. Hence, the matter

has been referred to the Three Member Arbitral Tribunal. The petitioner has

raised the dispute, to declare the termination notice, dated 30/11/2010,

issued by the first respondent, as arbitrary, illegal and premature and

directed the first respondent to pay a sum of Rs.7.68 crores, along with

interest, at the rate of 12%, from the date of filing of the claim statement, till

the date of payment.

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

5. The petitioner has completed only 17% of the work and from the

very inception, the work was slow and he has not provided with proper

designs. Therefore, as per the terms governing the parties, under the

contract, the contract has been terminated and there was no proper planning

in executing the work.

6. The first respondent has narrated and given the detailed reasons

for the delay attributable by the petitioner in the defence statement, which

may not be repeated once again.

7. Proceedings recorded by the Tribunal would indicate that the

claim statement filed originally did not contain any details and supporting

documents. Only after filing the statement of defence, an application has

been filed to seek amendment and thereafter, additional grounds have been

raised. Before the Tribunal, no oral evidence has been let in. They relied on

documentary evidence and contractual terms.

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

8. Challenging the order passed by the arbitral Tribunal, the present

Original Petition has been filed, praying for the relief stated supra.

9. Heard Ms.Nalini Chidambaram, learned Senior Counsel for the

petitioner and Mr.D.Balaraman, learned counsel for the first respondent.

10. Learned Senior Counsel appearing for the petitioner submitted

that award passed by the learned Tribunal has to be set aside, mainly on the

ground of inadequacy of reasons. The Arbitral Award was passed, based

on the submissions made by both sides and no proper discussion was made

by the learned Arbitrator.

11. It is contended by the learned Senior Counsel appearing for the

petitioner that the Contractor does not contain risk and cost Clause,

whereas the contract only indicate that the first respondent is entitled to levy

liquidated damages alone. Admittedly, 17% of the work has been

completed, whereas the new tender has been invited for the remaining work,

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

for an estimated value of Rs.45.33 crores. Tthere was no transparency in the

tender. Such differential cost sought to be recovered from the petitioner

without any evidence. Particularly, there is no Clauses in the contract to

recover such differential amount. Hence, it is the contention of the learned

Senior Counsel appearing for the petitioner that award is not sustainable in

the eye of law.

12. It is further contended by the learned Senior counsel appearing

for the petitioner that an application has been filed by the first respondent,

in A.No.850 of 2020, under Section 34 (4) of the Act, to adjourn the

proceedings in O.P.No.306 of 2015 and remit the award, dated 2/8/2014, to

the Arbitral Tribunal, comprising of respondents 2 to 4 and resume the

arbitral proceedings for assigning reasons for its findings in the award. The

first respondent himself has admitted that award lacks reasoning. This

ground itself is sufficient to interfere with the award. Hence prayed to set

aside the award.

13. Learned counsel appearing for the first respondent submitted that

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

A.No.850 of 2020 has been filed with abundant caution, wherein it is

clearly mentioned that the award is the result of proper reasoning given by

the Tribunal.

14. With regard to the termination of the contract, no submission was

made by either side. Therefore, it is contended that the first respondent

cannot take advantage of such application which has been objected. Hence,

it is submitted that application was filed on the basis of the judgment of the

Hon'ble Apex Court to the effect that such application can be filed only

during the pendency of the petition, under Section 34 of the Act. Therefore,

with abundant caution, such application has been filed and that itself cannot

be a ground to hold that the petitioner is automatically entited to succeed.

15. As far as the merits of the contention is concerned, the learned

Arbitrators have considered the entire documentary evidence and

particularly, the terms governing the parties, passed an award. Therefore,

the same cannot be interfered with, under Section 34 of the Act and no

grounds were made out to interfere with the award, under Section 34 of the

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

Act.

16. On a perusal of the entire award, learned Arbitral Tribunal has

given an anxious consideration, from paragraph 13 of the award.

Arbitrators have framed necessary issues in this regard and after considering

the submissions made by both sides, found that though the period of

completion of the work was 210 days, the completion period was extended

from 210 days 7 months to 12 months and the schedule of handing over site

possession under Section IV by the petitioner in S.O.C stands superseded.

The learned Arbitrator, after taking note of the drawings enclosed in the bid

documents, answered the second issue against the petitioner. Though the

reasons were not elaborate running to several pages, the reasons were based

mainly on the documents relied upon by the parties.

17. It is relevant to note that both sides have relied upon only on

documentary evidence. Merely because elaborate reasons have not been

given, it cannot be said that such order is bereft of any details. For every

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

issues, the learned Arbitrator has given proper reasons.

18. Clause 16.1 and 2 reads as follows:-

"16.1 – The Contractor shall commence

execution of the construction/improvement works

on the start date and shall carry out the

construction/improvement works in accordance

with the program submitted by the Contractor, as

updated with the approval of the Engineer and

complete them in all respects by the intended

Completion Date.

16.2. All the time during the construction

period, Contractor shall notify the Engineer details

of drawings and instructions required and of why

and by when it is required. This notice shall be

given by the contractor at least one month advance

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

correlating approved construction program."

19. Clause 45.1 deals with Penalty and Liquidated Damages and the

same reads as follows:-

"For Construction/Impovement Works

(a). In case of non-completion of the entire

construction/improvement works within the Intended

Completion Date as indicated in the Contract Data,

the Contractor shall pay liquidated damages to the

Employer at the rate per day stated in the Contract

Data for each day that the actual Completion Date is

later than the Intended Completion Date. The

liquidated damages amount shall be deducted from

payments due to the Contractor and shall not be

refundable. The total amount of liquidated damages

shall not exceed the amount defined in the Contract

Data.

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

b. Time is the essence of the Contract and

payment or deduction of penalty or liquidated

damages shall not relieve the Contractor from his

obligation to complete the works as per agreed

Construction Program and Milestones or from any

other of the Contractor's obligations and liabilities

under the Contract or the Employer's right to invoke

the Performance Security.

c. If the Intended Completion Date is extended

after liquidated damages have been paid, the Engineer

shall correct any overpayment of liquidated damages

have been paid, the Engineer shall corret any

overpayment of liquidated damages by the Contractor

by adjusting the next payment certificate. The

Contractor shall be paid interest on the over payment

calcualted from the date of payment to the date of

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

repayment at the ate of 8% p.a."

20. Clause 45.2 of the Conditions of Contract, reads as follows:-

"(a). In case the Contractor has not rectified

or addressed deficiencies as directed by the

Engineer at the time of Site Inspections during

defects liability period, the Employer retains the

right to get works done through a third party and

debit the cost and expenses incurred to the

Contractor. Alternatively, the Engineer may

recommend invoking of Performance Security in

part of full, as the case may be. In case, the

Contractor still fails to rectify or address

deficiencies even after Invoking Performance

Security, as described earlier, then the Employer

shall treat the event as fundamental breach of

Contract in terms of Clause 54 of Conditions of

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

Contract."

21. A bare reading of the above makes it clear that in the event of

work has not been completed and if any defect is pointed out has not been

rectified during the defect liability period, cost and expenses incurred to get

the work done through the third parties should be recovered by the

employer.

22. Clause 54 of the Conditions of Contract deals with the

Termination of the contract. When the employer of the Contractor commits

fundamental breach of contract which may lead to termination of the

contract. It is the case of the first respondent that despite agreed to

complete the work, as agreed in the contract, the petitioner has completed

only 17% of the work. Despite two show cause notices issued, no progress

has been shown.

23. 54.2 (g) and (i) of the Conditions of Contract reads as follows:-

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

(g). The Contractor has defaulted in fulfilling

his obligations under his Contract.

(i). If the Contractor, in the judgment of the

Employer has engaged in corrupt or fraudulent

practices in completing for or in the executing the

Contract.

24. Last paragraph of 54.2 reads as follows:-

"In case of default on the part of the Contractor

in carrying out the work as per programme, the

employer is entitled to employ and pay others to carry

out the work. The additional cost if any will be

recovered from the defaulting contractor."

25. It is to be noted that in case of default on the part of the

Contractor, in carrying out the work, as per programme, the employer is

entitled to employ and pay others to carry out the work. Admittedly, in this

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

case, the petitioner had completed only 17% of the work and the remaining

works ought to be completed by issuing another tender for a sum of

Rs.45.33 crores.

26. It is the further contention of the learned Senior Counsel

appearing for the petitioner that such amount has been escalated which is

unreasonable. The contract provides only for the work by engaging third

parties and not by separate tender. Therefore, that cost cannot be recovered

from the petitioner herein.

27. It is to be noted that when the contract provides and empowering

the employee to complete the remaining work and recover the additional

cost incurred for such completion, such contractual term is binding on the

parties to the contract. The petitioner cannot complain the manner in which

the remaining work to be completed. It is not for the petitioner to dictate

the manner in which the remaining work to be completed by the employer.

The very terms referred under Clause 54.2 makes it very clear that the

employer is entitled to get the remaining works done through other persons

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

and recover the additional cost. Merely because for remaining 83% work,

the contract was awarded for 45.33 crores that cannot be a reson that such

bid is not according to law.

28. Learned Arbitrator, in fact, has considered the submissions of

the petitioner that tender has not invited and bidding was not in a

transparent manner. In fact, the learned Arbitrator has perused the files

relating to the subsequent tenders and on a perusal of the records found that

the said contention of the petitioner is not maintainable and has no merits

and in fact, opined that tender has been invited, as per law.

29. The learned Arbitrators, who are the retired Chief Engineers of

the Highways Department has in fact allowed the claim of the petitioner for

the work done. Merely because an application has been filed with abundant

caution, cannot be a ground to hold that the petitioner is automatically

entitled to succeed. This Court is of the considered view that none of the

grounds contemplated under Section 34 of the Act is made out to interfere

with the well reasoned award.

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

30. Accordingly, this Original Petition is dismissed. Consequently,

Application No.850 of 2020 is closed.

9/8/2021

mvs.

N.SATHISH KUMAR,J

mvs.

https://www.mhc.tn.gov.in/judis/ O.P.No.306 of 2015

O.P.No.306 of 2015

9/8/2021

https://www.mhc.tn.gov.in/judis/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter