Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

The District Collector vs K.Natarajan
2021 Latest Caselaw 15657 Mad

Citation : 2021 Latest Caselaw 15657 Mad
Judgement Date : 4 August, 2021

Madras High Court
The District Collector vs K.Natarajan on 4 August, 2021
                                                                              W.A.No.325 of 2021

                                    IN THE HIGH COURT OF JUDICATURE AT MADRAS

                                                  DATED : 04.08.2021

                                                          CORAM

                                      THE HON'BLE MR.JUSTICE M.M.SUNDRESH
                                                       and
                                      THE HON'BLE MRS.JUSTICE S.KANNAMMAL

                                                  W.A.No.325 of 2021
                                               and C.M.P.No.1322 of 2021

                     The District Collector,
                     Dharmapuri District,
                     Dharmapuri.                                                   .. Appellant

                                                           Vs

                     1.K.Natarajan

                     2.Powergrid NM Transmission Ltd.,
                       Rep. by General Manager,
                       No.62, 3rd Cross,
                       MEI Road, Industrial Suburb,
                       Yeswantpur,
                       Bengaluru - 560 022.                                     .. Respondents

                               Appeal filed under Clause 15 of Letters Patent against the order

                     dated 12.04.2019 made in W.P.No.16460 of 2018.


                               For Appellant          :     Mr.D.Ravichander,
                                                            Government Counsel

                               For Respondents        :     Mr.V.Sanjeevi for R1
                                                            Mr.AR.L.Sundaresan, Sr.Counsel
                                                            for Mr.Kalyanaraman
                                                            M/s.Aiyar & Dolia for R2


                     Page 1 of 12


https://www.mhc.tn.gov.in/judis/
                                                                               W.A.No.325 of 2021



                                                      JUDGMENT

(Delivered by M.M.SUNDRESH, J.)

This appeal raises two interesting legal issues. For deciding the

said issues, primary background facts are to be reiterated.

2. This is the second round of litigation between the parties. The

second respondent undertook the project which goes through the State

of Tamil Nadu. The project extends from Nagapattinam - New Salem

(Dharmapuri) in the State of Tamil Nadu and thereafter goes to the

State of Karnataka. While implementing the project, lines were drawn

through the property of the first respondent. In the year 2016,

compensation was given to the first respondent partially which is only

for the building. Accordingly, a sum of Rs.7,17,907/- was paid towards

the value of the building by rejecting the larger compensation sought

for by the first respondent which is inclusive of right of way.

3. The first respondent filed writ petition in W.P.No.7685 of 2016

against the order of the appellant/the District Collector, Dharmapuri

dated 31.12.2015. The following is the relevant portion of the order

passed:-

https://www.mhc.tn.gov.in/judis/ W.A.No.325 of 2021

"8. The second respondent has filed a counter affidavit, justifying their action, which need not be gone into at this stage, since already the work towards the erection of transmission tower is in progress. All that has to be seen is as to the stand taken by the second respondent is with regard to the effect of the guidelines issued by the Government of India, dated 15.10.2015. To find this aspect, it would be suffice to refer to para Nos.14 and 15 of the counter affidavit, wherein, the second respondent has accepted that they would pay the compensation in terms of the guidelines on determination of the same by the District Magistrate/District Collector, however, they seek to restrict only to para 2 (i) of the said guidelines. While the second respondent accepts that they are bound by the abovesaid guidelines, they cannot restrict it by stating that the claim should be made by the petitioner only in terms of para 2 (i) of the guidelines. The petitioner, being the land owner, it is well open to him to invoke all provisions, which according to him, are applicable to the land in question and make a claim for compensation before the District Collector/first respondent.

9. Further, it has to be pointed out that, so far as the award of compensation mentioned in the impugned order, the District Collector in the penultimate para, has made vague observation, stating that the petitioner is entitled to proper compensation. Therefore, to that extent, the order passed by the District Collector is held to be not tenable, as it is inconsistent with regard to the manner in which the compensation has to be determined as per the guidelines framed by the Government of India. Accordingly, while upholding the order passed by the District Collector to the aforesaid extent, there will be a direction to the

https://www.mhc.tn.gov.in/judis/ W.A.No.325 of 2021

petitioner to submit his claim statement before the first respondent/District Collector, in accordance with the guidelines framed by the Government of India, dated 15.10.2015, along with a copy of this order, clearly setting out as to what is the basis of his claim, and the petitioner is entitled to invoke all the clauses under the guidelines. On receipt of such claim statement, the first respondent shall issue notice to the second respondent, and after affording an opportunity to file their reply/counter, and thereafter, shall issue notice to the petitioner and the second respondent, fixing a date for hearing the parties in person, direct the second respondent to produce all documents, including the building valuation report, and after perusing all the documents, hear the parties in full, and pass a reasoned order, by strictly adhering to the guidelines prescribed by the Government of India. The first respondent is directed to give the second respondent, three weeks' time to file reply/counter, and after receipt of the claim statement from the petitioner and after reply/counter affidavit is received from the second respondent, after serving a copy of the same to the petitioner in advance, the first respondent shall fix a date of hearing within a period of 10 days thereafter, and after hearing all the parties in full, shall pass appropriate orders within two months from the date on which hearing is

concluded."

4. In compliance of the order aforesaid which has become final

inter se parties, the first respondent sent his claim statement dated

06.06.2016. The impugned order was passed thereafter rejecting the

request of the first respondent on two grounds, namely, the

https://www.mhc.tn.gov.in/judis/ W.A.No.325 of 2021

Government Order passed in G.O.(Ms).No.63 Energy (A1) Department,

dated 22.11.2017 being prospective in nature does not facilitate the

consideration of the compensation for the right of way and the project

having been introduced by Gazette Publication issued by the Central

Government dated 05.12.2013 with the guidelines issued by the

Ministry of Power providing for damages for the right of way having

come into force on 15.10.2015 being prospective, the request made

was not feasible of consideration.

5. The first respondent once again put to challenge the order of

rejection passed by the appellant. Taking into consideration the earlier

order passed in W.P.No.7685 of 2016, the learned Single Judge was

pleased to set aside the order impugned with the direction to the other

respondents to pay the compensation in tune with the guideline issued

by the Ministry of Power, Government of India dated 15.10.2015,

without going into the applicability of the Government Order in

G.O.(Ms).No.63 Energy (A1) Department, dated 22.11.2017.

Strangely, this order has been put to challenge before us by the

appellant, who is the statutory authority under Section 10 read with

Section 16(3) of the Indian Telegraph Act, 1885. Perhaps, the

contesting respondent has not appealed against the order passed by

https://www.mhc.tn.gov.in/judis/ W.A.No.325 of 2021

the learned Single Judge since the statement made by the learned

Senior Counsel on behalf of the second respondent that the larger

issue on the applicability of the Government Order may be left open

vis-a-vis the guideline of the Central Government dated 15.10.2015 to

be decided in the appropriate case and, therefore, the decision shall

not be quoted as a precedent. However, we find that the learned Single

Judge though took note of the aforesaid submission, did not make any

observation, though the order was passed to consider the claim of the

first respondent on the basis of the guideline of the Central

Government dated 15.10.2015, ignoring the Government Order passed

in G.O.(Ms).No.63 Energy (A1) Department, dated 22.11.2017.

6. Learned Government Counsel appearing for the appellant

reiterated the two grounds indicated in the order of rejection, namely,

(i) the project was earlier in point of time to the guidelines of the

Central Government dated 15.10.2015 being initiated in the year 2013

and (ii) the applicability of the Government Order, being prospective

and having been issued on 22.11.2017.

7. Learned Senior Counsel appearing for the second respondent

submitted that the order passed on the first occasion in W.P.No.7685 of

https://www.mhc.tn.gov.in/judis/ W.A.No.325 of 2021

2016 has to be seen contextually and the remedy open to the first

respondent is by way of filing a suit. In support of his contention,

reliance has been made on the judgment of the Apex Court in

Powergrid Corporation of India Limited Vs. Century Textiles and

Industries Limited and Others ((2017) 5 SCC 143).

8. Per contra, learned counsel appearing for the first respondent

submitted that the Government Order dated 22.11.2017 can only be

applied to the State Government projects per se and not to the Inter-

State projects. The said order is only an adoption of the guidelines of

the Central Government and that too on the basis of the report

submitted by the Chairman, TANTRANSCO. The guidelines are

prospective in nature and, therefore, to be applied to such of those

cases where the compensation has not been determined after it has

come into being. To say, the guidelines are not to be applied to the

project initiated earlier cannot be sustained in the eye of law.

Therefore, it is submitted that the appeal will have to be dismissed.

9. Prima facie, we have our own doubt on the maintainability of

this appeal. We have already indicated the role required to be played

by the appellant either under the Indian Telegraph Act, 1855 or under

https://www.mhc.tn.gov.in/judis/ W.A.No.325 of 2021

the Electricity Act, 2003. The second respondent, who has to pay the

compensation and complete the project was satisfied with the order of

the learned Single Judge. Be that as it may, even on merit, we do not

find any reason to interfere with the order passed by the learned

Single Judge. Though the learned Senior Counsel appearing for the

second respondent submitted that the said issue of application of the

Government Order may be left open, we are constrained to give a

finding since the appeal has been filed by the appellant challenging the

aforesaid finding. It is the case of the appellant that the issue of

compensation cannot be adjudicated upon and, therefore, we have no

other choice except to decide this issue.

10. We have perused the Government Order passed. The said

order merely adopts the decision taken by the Central Government.

Obviously, the State Government does not require to give any

compensation for the project initiated by the second respondent. The

State Government order also was passed on a report submitted by the

statutory body functioning under its authority. Therefore, there is no

difficulty in holding that the said Government order has got no

application. This finding we are constrained to render in view of the

https://www.mhc.tn.gov.in/judis/ W.A.No.325 of 2021

contentions raised by the learned Government Counsel appearing for

the appellant.

11. Coming to the other issue, here again, a strange reasoning

has been adopted by the appellant in passing the impugned order. The

entire case looks strange since at least the second respondent has

understood his own case. That is the reason why, a fair submission has

been made by the learned Senior Counsel appearing for the second

respondent even before the learned Single Judge on the second

occasion. Admittedly, on the date when the compensation was paid

partially for the building, the guidelines of the Central Government

dated 15.10.2015 was in vogue. Initiating a project has got nothing to

do with the owner of the land. The question of compensation has to be

decided based upon the law governing on that date unless a clear

indication is given. Now, we are only concerned with the application of

the guidelines. Certainly, the guidelines are prospective and, therefore,

they should be applied for such of those cases seeking adjudication on

the question of compensation. The appellant is the authority

competent to decide the issue of compensation. Hence, the second

contention based upon which the impugned order was passed is also

rejected.

https://www.mhc.tn.gov.in/judis/ W.A.No.325 of 2021

12. Learned Senior Counsel appearing for second respondent

made reliance upon the judgment of the Apex Court in Power Grid's

case. The facts governing the present case and those involved in the

said case decided are different. In any case, the second respondent

has not challenged the order of the learned Single Judge. Therefore, it

is not open to the second respondent to contend to the contrary. Even

otherwise, we find that Section 16(3) of Indian Telegraph Act only

deals with the issue of sufficiency of compensation. What we are

dealing with is the issue of entitlement of compensation. Perhaps, in

the event of the appellant deciding the compensation which is not

acceptable to the first respondent, then the remedy open to him is to

approach the District Collector in tune with the order of the Apex Court

referred supra but not at this stage.

13. In such view of the matter, we do not find any reason to

interfere with the ultimate conclusion arrived at by the learned Single

Judge.

14. Accordingly, the writ appeal stands dismissed. The appellant

shall give effect to the order of the learned Single Judge within a

https://www.mhc.tn.gov.in/judis/ W.A.No.325 of 2021

period of twelve weeks from the date of receipt of a copy of this

judgment. No costs. Consequently, connected miscellaneous petition is

closed.

                                                               (M.M.S., J.)    (S.K., J.)
                                                                       04.08.2021
                     Index:Yes/No
                     mmi/ssm

                     To

                     The General Manager,
                     Powergrid NM Transmission Ltd.,
                     No.62, 3rd Cross,
                     MEI Road, Industrial Suburb,
                     Yeswantpur,
                     Bengaluru - 560 022.







https://www.mhc.tn.gov.in/judis/
                                         W.A.No.325 of 2021




                                      M.M.SUNDRESH,J.
                                                 and
                                      S.KANNAMMAL,J.

                                                      mmi




                                     W.A.No.325 of 2021




                                             04.08.2021







https://www.mhc.tn.gov.in/judis/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter