Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Orion Contractors Pvt Ltd. Through ... vs Madhya Pradesh Rural Road Development ...
2025 Latest Caselaw 10173 MP

Citation : 2025 Latest Caselaw 10173 MP
Judgement Date : 13 October, 2025

Madhya Pradesh High Court

M/S Orion Contractors Pvt Ltd. Through ... vs Madhya Pradesh Rural Road Development ... on 13 October, 2025

Author: Vivek Rusia
Bench: Vivek Rusia
          NEUTRAL CITATION NO. 2025:MPHC-IND:30097




                                                              1                              WP-220-2025
                              IN     THE      HIGH COURT OF MADHYA PRADESH
                                                     AT INDORE
                                                        BEFORE
                                           HON'BLE SHRI JUSTICE VIVEK RUSIA
                                                           &
                                      HON'BLE SHRI JUSTICE BINOD KUMAR DWIVEDI
                                                 ON THE 13th OF OCTOBER, 2025
                                                 WRIT PETITION No. 220 of 2025
                            M/S ORION CONTRACTORS PVT LTD. THROUGH DIRECTOR AND
                              AUTHORIZED SIGNATORY SHRI DEEPAK SONI KRISHNA T
                                                   Versus
                            MADHYA PRADESH RURAL ROAD DEVELOPMENT AUTHORITY
                            THROUGH THE CHIEF EXECUTIVE OFFICER BLOC TH FLOOR PA
                                                AND OTHERS
                           Appearance:
                                   Shri Aniket Naik - Advocate for the petitioner.
                                   Shri Sanjay Kumar Karanjawala - Advocate for the respondents .

                                                                  ORDER

Per: Justice Vivek Rusia

Petitioner has filed the present petition under Article 226 of the Constitution of India seeking quashment of order dated 04.10.2024 (Annexure P/12), whereby the respondents have declined to release the

security deposit of package No.MP10506.

Facts of the case, in short, are as under:

02. The petitioner is a private limited company incorporated under the Companies Act, 1986 (Now 2013). The respondent No.1 is a registered society entrusted with public / sovereign function of construction and maintenance of public roads and other infrastructure in the State of Madhya

NEUTRAL CITATION NO. 2025:MPHC-IND:30097

2 WP-220-2025 Pradesh. The respondent No.2 is the General Manager concerning with the Project Implementation Unit which allotted Package No.MP10506 to the petitioner.

03. The respondents issued an NIT bearing Package No.MP10506 for construction, upgradation and maintenance of the road for 5 years under Pradhan Mantri Gram Sadak Yojana (PMGSY). The petitioner was awarded the contract vide work order dated 08.06.2015. Indisputably, the petitioner had successfully carried out the said work and also maintained the road for the period of 5 years. The respondent issued a completion certificate dated 05.12.2017 to the petitioner (Annexure P/3). The respondents have not issued any complaint or demand in respect of this work.

04. The petitioner was awarded another works contract vide Package

No.MP10UPG07. Vide notice dated 17.09.2021, the respondents issued a recovery of Rs.59,80,172/- with interest to the petitioner, which was challenged by way of Writ Petition No.19220/2023 inter alia on the ground that the reference is pending before the M.P. Arbitration Tribunal. In the said writ petition, the respondents filed the reply stating that as per the terms and conditions and General Condition of Contract, the recovery can be made from the deposits made for other work / project by the petitioner (Package No.MP10506). Vide order dated 15.12.2023, the writ petition came to be allowed by restraining respondents to recover any amount till the adjudication of reference case by the M.P. Arbitration Tribunal. It has also been observed that the amount of Rs.59,80,172/- is not liable to be recovered from any pending other work or by way of RRC from the petitioner and

NEUTRAL CITATION NO. 2025:MPHC-IND:30097

3 WP-220-2025 amount which has already been recovered shall be subject to the outcome of reference.

05. Thereafter, the petitioner has submitted a representation to the respondent No.2 for release of the security amount of Package No.MP10506. Vide letter dated 04.10.2024, the respondent No.3 informed that in view of the aforesaid order passed by this Court, the remaining amount will be released after the judgment passed by the M.P. Arbitration Tribunal hence, this petition before this Court.

06. The respondents have filed the reply raising an issue of maintainability of the petition and again reiterated that the work awarded vide Package No.MP10UPG07 dated 16.11.2017 has been cancelled on 16.11.2018 due to non-completion of the work. The respondents have already recovered the amount under recovery from the security deposit of Package No.MP10506 before the order dated 15.12.2013 passed by the High Court and now, the said amount is liable to be returned only after the reference is decided by the Tribunal. As per Annexure R/2, the respondents have recovered Rs.23,57,660/- from Package No.MP10506 BW.

07. Learned counsel appearing for the respondents prays from dismissal of the petition.

We have heard learned counsel for the parties and perused the record.

08. The issue which requires consideration is whether the action of the respondent is justified in making recovery of the amount under Package

No.MP10UPG07 from the security deposit of Package No.MP10506.

NEUTRAL CITATION NO. 2025:MPHC-IND:30097

4 WP-220-2025 Admittedly, the petitioner had successfully completed the work of Package No.MP10506 and there is no recovery against the petitioner. The respondents have not brought on record any terms and conditions of the contract executed in Package No.MP10UPG07 which authorizes them to recover any amount of this contract from the security deposit of the other contract.

09. The Clause 43.4 of standard bidding document for PMGSY of a contract of Package No.MP10506, only authorises the respondents to withhold the performance security equal to 5% of a contract price is repaid to the contractor when the period of 5 years fixed for routine maintenance is over and due certification by the Engineer. As per Clause 43.2, on satisfactory completion of the whole of the construction work, half of the total amount retained as security deposit is liable to be repaid to the contractor. As per Clause 43.3, the additional performance security for unbalanced bids as detailed in Clause 46 of the General Condition of Contract is liable to be repaid to the contractor when the construction work is complete. Therefore, there is no such provision brought on record by the respondents which authorizes them to adjust the amount of performance security in the recovery of any other contract.

10. So far as the order passed by this Court in Writ Petition No.19220/2023 is concerned, first time the respondent informed in the said writ petition that the amount of Rs.59,80,172/- recoverable in Package No.MP10UPG07 has been recovered from the security deposit of Package No.MP10506. This Court did not justify their action and only restrained to recover Rs.59,80,172/- till the decision in the pending reference case in view

NEUTRAL CITATION NO. 2025:MPHC-IND:30097

5 WP-220-2025 of the judgment passed by the Hon'ble Apex Court in the cases of Tulsi Narayan Garg V/s M.P. Road Development Authority reported in 2019 SCC OnLine SC 1158 and B.B. Verma V/s State of M.P. reported in (2007) 4 MPLJ 610. Now, the petitioner has challenged the said action in this petition, thus, in absence of any authority or any agreement between the parties, the respondents have wrongly adjusted the amount of Rs.25,06,620/- (or actual amount adjusted).

11. In view of the above, the impugned order dated 04.10.2024 (Annexure P/12) is set aside. The withheld / adjusted security amount of Package No.MP10506 be returned to the petitioner with interest at the rate of 6% per annum from the date of completion of 5 years of maintenance period till payment.

12. With the aforesaid, this Writ Petition stands allowed and disposed of.

Certified copy as per rules.

                                      (VIVEK RUSIA)                         (BINOD KUMAR DWIVEDI)
                                          JUDGE                                     JUDGE
                           Divyansh

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter