Monday, 18, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Rk Constructions A Parternship ... vs The State Of Madhya Pradesh
2025 Latest Caselaw 1777 MP

Citation : 2025 Latest Caselaw 1777 MP
Judgement Date : 5 June, 2025

Madhya Pradesh High Court

M/S. Rk Constructions A Parternship ... vs The State Of Madhya Pradesh on 5 June, 2025

                                                               1                                WP-19918-2025
                                          IN THE HIGH COURT OF MADHYA PRADESH
                                                        AT INDORE
                                                       WP No. 19918 of 2025
                             (M/S. RK CONSTRUCTIONS A PARTERNSHIP FIRM THROUGH ITS PARTNER MAYUR JHALLA Vs THE
                                                   STATE OF MADHYA PRADESH AND OTHERS )



                           Dated : 05-06-2025
                                    Shri Pradyumna Kibe - Advocate for the petitioner.
                                    Shri Bhuwan Gautam - GA for the State.

                                    IA No.5184/2025 is taken up, which is an application for urgent
                           hearing during summer vacation.

                                    2. Considering the reasons assigned in the application IA
                           No.5184/2025 is allowed. The matter is taken up for hearing.
                                    3. Counsel for the petitioner submits that in identical case WP
                           No.19750/2025 (Ms. R.K. Constructions A Partnership Firm through its
                           Partner Mayur Jhalla Vs. The State of M.P. and others) in which notices
                           have been issued and Interim Order has been passed on 02.06.2025.
                                    4. The aforesaid contention is not been disputed by counsel for the
                           State.
                                    5. Learned counsel for the petitioner submits that the petitioner

                           completed the work and thereafter completion certificate was also issued to
                           the petitioner, however, on the basis of the audit report by order dated
                           09.05.2025 recovery has been initiated against the petitioner. Earlier also the
                           petitioner approached this Court by preferring Writ Petition which was
                           decided by order dated 31.01.2025 and petitioner was directed to approach to
                           the competent authority as per the terms of the general conditions of the
                           contract. Thereafter the petitioner approached to the competent authority,

Signature Not Verified
Signed by: AJIT
KAMALASANAN
Signing time: 06-06-2025
13:29:44
                                                               2                           WP-19918-2025
                           however the competent authority by impugned order dated 09.05.2025 has
                           rejected the objections raised by the petitioner and ordered to initiate the
                           recovery against the petitioner.
                                 6.      Learned counsel for the petitioner further submits that the
                           petitioner has already approached M.P. Arbitration Tribunal and filed a
                           reference case which is still pending and during the pendency of the
                           reference case no recovery can be initiated against the petitioner. He relied
                           on the judgment of Supreme Court delivered in the matter of Tulsinarayan
                           Garg V/s. M.P. Road Development Authority, Bhopal and Others 2022 (17)
                           SCC 750 wherein the Apex Court has held that pending the reference case no
                           recovery is permissible. He also relied on the interim order passed by the

                           Vacation Bench of Principal Bench, Jabalpur in W.P. No.19594/2025 on
                           29.05.2025 (M/s. Vishwa Kusum Infratech V/s. M.P. Rural Road
                           Development Authority and Others) whereby the recovery initiated against
                           similarly situated contractor was stayed by the coordinate Bench.
                                 7.   Issue notice.
                                 8.    The notice is accepted by learned Government Advocate Shri
                           Bhuwan Deshmukh on behalf of respondent No.1 on advance copy. Issue

notice to the respondents No.2 to 4 on payment of process fee by tomorrow. Humdast notice be issued to the respondents in addition. The notices be made returnable within two weeks.

9. Considering the judgment delivered by Supreme Court in the matter of Tulsinarayan Garg (supra) and order dated 29.05.2025 passed by the coordinate Bench no coercive action be taken against the petitioner till

3 WP-19918-2025 next date of hearing.

10. List the matter in the week commencing 16.06.2025 alongwith WP No.19750/2025.

C.c. as per rules.

(VIJAY KUMAR SHUKLA) (PAVAN KUMAR DWIVEDI) V. JUDGE V. JUDGE ajit

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : MAIMS

 
 
Latestlaws Newsletter