Citation : 2021 Latest Caselaw 6960 MP
Judgement Date : 28 October, 2021
1 WP 20236-2021
THE HIGH COURT OF MADHYA PRADESH
WP 20236-2021
(Desai Infra Projects (India) Pvt. Ltd. Vs. The State of M.P. & ors.)
Gwalior Dt. 28.10.2021
Shri Manoj Swaroop, learend Senior counsel with Shri
Dharmendra Nayak and Shri Nitin Agarwal, learned counsel for
petitioner.
Shri Ankur Mody, learned Additional Advocate General for
respondents No.1 to 6/State.
Shri Prashant Sharma, learned counsel for respondent No.7.
The instant petition u/Art. 226 of the Constitution is preferred by
Private Limited Company questioning the legality and validity of the
decision of official respondents in rejecting the technical bid of petitioner
submitted for work of Repair and Reconstruction of chambal right main
canal and their structures, Damaged and breached portion of canal by
heavy rainfall and flood in between 0.00 km and 83.00 km with Earth
Work, Raincuts filling, Concrete lining, Duct repair, Structure. Further
prayer is made for restraining the official respondents from executing the
agreement in respect of work with any other bidder and for direction to
decide the objection preferred by petitioner on 17.9.21 vide P/8 against
the impugned decision of disqualifying petitioner on technical aspect.
2. Learned counsel for rival parties are heard on the question of
admission and final disposal.
3. Respondent No.7 to whom the contract has been awarded and is
presently undertaking the work in question has filed a caveat. On supply 2 WP 20236-2021
of copy of petition to the caveator, an application for dismissal of petition
i.e. IA 13410/21 is preferred by respondent No.7. Thereafter petitioner
filed IA 13455/21 for bringing certain additional documents on record
primarily to emphasize the haste with which the official respondents
executed the agreement in favour of respondent No.7. The official
respondents (respondents No.1 to 6) have also filed detailed parawise
reply.
4. With the aforesaid pleadings on record, with consent of learned
counsel for rival parties, this matter was finally heard at the admission
stage.
5. Leanred Senior Counsel Shri Manoj Swaroop alongwith Shri
Dharmendra Nayak and Shri Nitin Agarwal, appearing on behalf of
petitioner has primarily submitted that despite a clear mandate in Clause
19.5 of "Instructions to Bidders" appended to the NIT obliging the official
respondents to record reasons for rejection of any bid, the impugned order
vide P/1 is conspicuoulsy non-speaking. It is further submitted that the
haste with which the entire process of opening and evaluation of technical
and financial bid followed by execution of agreement in favour of
respondent No.7 was undertaken, the same smacks of favouritism. It is
further urged that despite being eligible, petitioner has been intentionally
outsted for reasons untenable in law. Learned Senior Counsel for
petitioner further brings to the notice to this Court that it is wrong on the
part of respondents to contend that tenure of completion of contract is 3 WP 20236-2021
only two months since the tenure as per agreement is 12 months followed
by 24 months of management, operation and maintenance. In this
background, it is submitted by learned Senior Counsel that the reasons of
short tenure of the work assigned by the official respondents to justify
their haste in completing the tender process is untenable. In the aforesaid
factual background, petitioner has sought allowing of this petition.
6. Per contra, learned counsel for official respondents Shri Mody, in
their return revealed that six bids were received. At the first stage of
"envelop A" pertaining to fees, all six tenders were found eligible.
Thereafter at the second stage of "envelop B" containing technical bid out
of six offers including that of petitioner, two tenderers including
petitioner were found disqualified for having not completed experience
criteria of 15 lakh cubic meters of earthworks during any one year in the
last three years. It is further submitted by official respondents that since
petitioner was not eligible to be considered for opening financial bid
"envelop C", the contention of petitioner that its bid was lower than the
bid of respondent No.7 is futile.
6.1 Shri Mody, learned counsel for official respondents, has apprised
this Court that the nature of work in question which related to repairing of
a damaged irrigation canal which had suffered breached at several places
and had to be repaired before the onset of Rabi season, the initial work of
repairing the canal and making it temporarily functional was required to
be done urgently at war-footing and thus the official respondents 4 WP 20236-2021
following the due process of law did not waste any time in the process of
consideration of evaluation of tenders and execution of contract in favour
of respondent No.7 who was found to be lowest qualified bidder. It is
submitted by Shri Mody that the work of concrete lining of the canal was
to be undertaken after the initial repairing work. It is further urged by Shri
Mody that since the State of M.P. is predominantly an agrarian State
where more than 70% of economy is agriculture based, the work of
repairing the breached canal had to be undertaken urgently to make the
canal functional for the flow of water required during Rabi season which
commences immediately after Dusshera season. As such it is emphasized
that looking to the emergent nature of work, the time period provided for
completing evaluation of tender may appear to be a bit short but looking
to the object behind the work in question, the tight time schedule is
justified. For this purpose, Shri Mody relies upon Clause 5.0 of the
conditions of contract Part II (special condition of contract) which
provides thus:-
5.0 The tenderer shall be responsible to restore/repair the
entire canal system with inline structure to provide irrigation
from October, 2021.
6.2 Shri Mody has also pointed out that the petitioner was not eligible
since the certificate of experience in regard to 20 different earthworks
undertaken in 2019-20 did not sum up to the minimum eligibility criteria
of 15 lakh cubic meters of earthworks. It is revealed by Shri Mody that 5 WP 20236-2021
out of the 20 earthworks relied upon by petitioner for claiming eligibility,
details of several of these did not mention the quality but only the value of
work done. It is submitted that after excluding the work in which only
value and not the quantum of earthwork was shown, the sum total of the
experience of petitioner came to be less than 15 lakh cubic meters. Lastly,
Shri Mody submits that due to changed circumstances, inasmuch as
exeuction of contract in favour of respondent No.7 and also completion of
the first stage of restoring/repairing the entire canal system, the remedy of
judicial review u/Art. 226 of the Constitution is not available to petitioner
who should be relegated to avail the remedy under private law.
7. Learned counsel for respondent No.7 Shri Prashant Sharma has
raised certain preliminary objections in its application for dismissal of the
petition by contending that the power of attorney, in the given facts and
circumstances does not authorise the power of attorney holder to file this
petition. For this purpose, reference is made to the special Power of
Attorney Annexure P/3 which according to learned cousnel for respondent
No.7 empowers the Power of Attorney holder to assail the tender process
only on the occasion of the bid of petitioner being successful. It is
contended by Shri Prashant Sharma that since petitioner's bid was
rejected, there was no occasion for invoking the Power of Attorney and
therefore, this petition is infructuous.
8. Leanred Senior Counsel Shri Manoj Swaroop alongwith Shri
Dharmendra Nayak and Shri Nitin Agarwal, learned counsel appearing for 6 WP 20236-2021
petitioner supplementing his arguments submits that Annexure P/1
impugned herein is non-speaking as it fails to assign reason behind the
rejection of technical bid and therefore, is in breach of Clause 19.5 of NIT
instructions. Learned Senior Counsel in regard to merits of the alleged
ineligibility of petitioner qua technical bid, submits by referring to IA
13548/21 that the official respondents have intentionally misread and
misinterpreted the certificate of earthwork experience submitted by
petitioner in respect of 20 different earthworks undertaken in the year
2019-20. It is submitted by learned Senior Counsel that the work
completion certificate was furnished to the official respondents in support
of technical bid in the format as it was received from the
person/institution for whom/which the work in the year 2019-20 was
executed. Learned Senior Cousnel drawing attention of this Court to the
excavation of earthwork experience certificate submits that the cost of
work was though mentioned in the tabular illustration but the quantity of
earthwork in cubic meter was also mentioned. It is submitted that the
official respondents to extend undue favour to respondent no.7,
intentionally turned a blind eye towards the experience certificate which
was explicit in respect of quantum of earthwork. Learned Senior Counsel
thus submits that if the certificates had been read in entirety with an
honest and impartial intention then there was no occasion or cause to
declare the petitioner ineligible. Learend counsel for petitioner has relied
upon Harminder Singh Arora Vs. Union of India 1986 (3) SCC 247 7 WP 20236-2021
Para 19, 24 and 25, Union Bank of India & ors. Vs. Jai Prakash Singh
& Anr. 2007 (10) SCC 712 Para 7.
8.1 As regards the two decision of Apex Court in the case of
Harminder Singh (supra) and Jai Parakash (supra), the earlier one
i.e. Harminder Singh (supra) a case where NIT was issued inviting
application to supply fresh buffalo and cow milk. The petitioner before
the Supreme Court whose petition had been dismissed by the High
Court, was though found to be L-1 and suitable, but the concerned
official respondent therein found that it would be economically more
beneficial to receive pasteurized milk rather than fresh buffalo/cow
milk and therefore, tender of petitioner despite being technically and
financially eligible was rejected and instead L-2 who had no expertise
of supplying fresh cow and buffalo milk was chosen for award of
contract. The Supreme Court while allowing the petition held that the
original terms and conditions of NIT of supplying fresh cow/buffalo
milk could not have been altered during process of evaluation of
tender and therefore, held grant of contract to L-2 to be unlawful. In
this background, it was inter alia held by Supreme Court that the State
and its instrumentalities are required to act in accordance with the
conditions laid down in the tender notice. The factual matrix attending
the case before the Apex Court in Harminder Singh (supra) is diverse
to the factual matrix attending the instant case and therefore, the said
case is of no avail to petitioner.
8 WP 20236-2021 8.2 The other case i.e. J.P. Singh (supra) is also relied upon by
petitioner in support of proposition that rejecting the offer pursuant to
NIT is necessarily to be attended with reasons. In the said case of J.P.
Singh (supra) the Apex Court while upturning the decision of
Allahabad High Court rejecting the petition, found that High Court
wrongly held policy to be arbitrary under which petitioner was seeking
remedy. The Apex Court also noticed that despite there being no
challenge to the policy in question, the High Court travelled beyond its
brief to hold the policy to be arbitrary. The Apex Court also found that
High Court did not afford any opportunity to the petitioner to file
counter affidavit before striking down the policy which was not even
challenged. Thus, the factual matrix attending the case of J.P. Singh
(supra) is also diverse and not even similar to the facts attending the
present case and thus this citation further does not assist the petitioner.
9. Learned counsel for the official respondents on the other hand has
relied upon Jagdish Mandal Vs. State of Orissa & Ors. 2007 (14) SCC
517 Para 22.
10. This Court, after having heard learned counsel for rival parties, to
begin with would not like to enter into hypertechnical objections raised by
learned counsel for respondent No.7 since this court intends to consider
the merits of the matter.
11. Law in regard to scope of judicial review in matters of tender
or award of contract except matters pertaining to blacklisting or 9 WP 20236-2021
imposition of penal consequences on a tenderer / contractor or
distribution of State largesse (allotment of sites / shops, grant of
licences, dealerships and franchises) stand on a different footing as
they may require a higher degree of fairness in action. Therefore, a
Court before interfering in tender or contractual matters in exercise
of power of judicial review, should pose to itself the following
questions :
"(i) Whether the process adopted or decision made by the authority is mala fide or intended to favour someone ?
(ii) Whether the process adopted or decision made is so arbitrary and irrational that the Court can say: "the decision is such that no responsible authority acting reasonably and in accordance with relevant law could have reached such a decision ?
(iii) Whether public interest is adversely affected or not ?"
12. A bare perusal of Annexure P/1 further indicates in regard to
grounds raised by petitioner that no reason has been assigned for
taking the impugned decision does not appeal to this Court, since
the impugned order P/1 reflects that petitioner was not technically
qualified. The impugned information vide P/1 may not be as explicit
as expected by petitioner but mere non-assigning or non-
communication of reasons by itself can not vitiate the process of
evaluation and award of contract in favour of respondent No.7,
especially in the face of paramount consideration of public interest 10 WP 20236-2021
which eclipses the personal interest of petitioner.
13. The requirement in the NIT was to furnish quantum of earthwork
which should be atleast 15 lakh cubic meters in any one year during last
three years. The requirement was not to mention the value/price of work
undertaken by petitioner. Petitioner has not only mentioned the price/cost
of earthwork undertaken but has also mentioned the quantum of
earthwork and therefore, it appears that the official respondents without
seeking any clarification from petitioner went ahead to disqualify
petitioner from the tender evaluation process by rejecting the technical
bid. The action of official respondents therefore, prima facie appears to be
unreasonable.
13.1 However, the supervening factor which outweighs the breach of
personal right caused to petitioner due to rejection of its technical bid is
that the work of the first stage of repairing the breaches in the canal has
progressed to a considerable extent and is likely to be over within a week.
Moreso, if the work in progress is now hindered then the prospects of a
healthy Rabi crop would suffer irreparably damage. Looking to the nature
of the work in question, it needs completion within a time frame. Any
delay at any stage of the work would deprive thousands of farmers of
water- the lifeblood for Rabi crop. The cumulative effect of the damage
would not only be to thousands of farmers but also millions of foodgrain
consumers in and around Madhya Pradesh which has now become the
leading wheat producer in the nation. The public interest involved in the 11 WP 20236-2021
timely and uninterrupted completion of the work in question, is
paramount which cannot be made subservient to the personal interest of
petitioner.
14. The aforesaid analysis of the factual matrix attending the present
case reveals that there does not appear to be any mala fide or favour
extended to respondent no.7. This Court further finds that decision to
reject the technical offer of petitioner to be not arbitrary. The decision
taken in the given facts and circumstances to award contract in favour of
respondent No.7 where breaches in the canal had to be repaired before the
onset of Rabi season, cannot be termed to be such which a responsible
authority would not take. Moreso the reason assigned by the official
respondents to award contract and work order to respondent No.7 is in
public interest as explained above. Therefore, the aforesaid three
questions are answered in the negative an therefore, this Court declines to
exercise power of judicial review in favour of petitioner.
15. The Apex Court in Bharat Coking Coal Ltd. Vs. AMR Dev
Prabha & Ors. (2020) 16 SCC 759 has held that interference in matters
of tender is to be sparingly made and if and when made, the Courts ought
to keep in mind that the public interest is protected even at the cost of
sacrificing personal interest. Relevent Para 33 of the said judgment is
reporduced below for ready reference and convenience:-
"33. Such a proposition has been noticed by this Court even earlier in Jagdish Mandal Vs. State of Orissa & Ors. 2007 (14) SCC 517 in the following words:
12 WP 20236-2021
"22. Judicial review of administrative action is intended to prevent arbitrariness, irrationality, unreasonableness, bias and mala fides. Its purpose is to check whether choice or decision is made "lawfully" and not to check whether choice or decision is "sound". When the power of judicial review is invoked in matters relating to tenders or award of contracts, certain special features should be borne in mind. A contract is a commercial transaction. Evaluating tenders and awarding contracts are essentially commercial functions. Principles of equity and natural justice stay at a distance. If the decision relating to award of contract is bona fide and is in public interest, courts will not, in exercise of power of judicial review, interfere even if a procedural aberration or error in assessment or prejudice to a tenderer, is made out. The power of judicial review will not be permitted to be invoked to protect private interest at the cost of public interest, or to decide contractual disputes. The tenderer or contractor with a grievance can always seek damages in a civil court. Attempts by unsuccessful tenderers with imaginary grievances, wounded pride and business rivalry, to make mountains out of molehills of some technical/procedural violation or some prejudice to self, and persuade courts to interfere by exercising power of judicial review, should be resisted. Such interferences, either interim or final, may hold up public works for years, or delay relief and succour to thousands and millions and may increase the project cost manifold." (emphasis supplied)
16. From the above discussion and analysis of facts and submissions of
learned counsel for rival parties, this Court declines interference in the
matter but affords liberty to the petitioner to seek his remedy in private
law domain in accordance with law.
17. Consequently, present petiiton stands dismissed with the aforesaid
liberty, sans cost.
(Sheel Nagu) (Deepak Kumar Agarwal)
Judge Judge
ojha 28/10/2021 28/10/2021
YOGENDRA OJHA
2021.10.28
17:43:31 +05'30'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!