Citation : 2021 Latest Caselaw 1973 MP
Judgement Date : 17 May, 2021
HIGH COURT OF MADHYA PRADESH PRINCIPAL SEAT AT JABALPUR
ARBITRATION APPEAL 52/2013
NO.
Parties Name NORTHERN COAL FIELDS LIMITED
VS.
M/S MADHUCON PROJECT LTD.
Bench Constituted Single Bench
Judgment delivered By HON'BLE SHRI JUSTICE VISHAL DHAGAT
Whether approved for YES/NO
reporting
Name of counsel for parties For petitioner: Shri Greeshm Jain, Advocate.
For Respondent : Shri N. S. Ruprah, Advocate
Law laid down Significant paragraph number
(O R D E R ) 17/05/2021
Appellant has preferred this appeal under section 39 of
Arbitration and Conciliation Act, 1940 (hereinafter referred to as
the Act of 1940').
2. Respondent M/s Madhucon Project Ltd., had filed an
application under sections 14 and 17 of the Arbitration and
Conciliation Act, 1940. Appellant has invited tender for
construction of 120 "B" Type quarters in Nigahi Project.
Agreement was entered between appellant and respondent on
11.4.1991. Said work is to be completed with investment of
Rs.1,82,14,000/-. A dispute was raised by respondent that site
was not made available in time and there was no approach road
which resulted in delay in execution of work. Unnecessary
reductions were made from the running bills for which
respondent raised objection which resulted in dispute.
Sole Arbitrator Shri B. L. Agrawal was appointed to resolve
the dispute. Final award was passed on 20.2.1999 and copy of
the same was sent to the parties by Registered post. Same was
received by the parties on 23.2.1999. Sole Arbitrator passed an
award of Rs.14,37,317/- in favour of respondent M/s Madhucon
Project Ltd. It was further ordered to return security amount of
Rs.1,00,000/- to respondent, thus total award of Rs.15,37,317/-
was passed in favour of respondent. Respondent filed an
application to make the award rule of law.
3. Learned Court of First Additional District Judge, Sidhi in Civil
Suit No.2B/2002 made the award rule of law and passed a decree
in favour of respondent vide order dated 2.9.2003. It was
ordered that amount mentioned in award dated 20.2.1999 i.e.
amount of Rs.15,37,317/- shall be paid to respondent with
interest @ 12% per annum till date of decree and from date of
decree till actual payment @ 8% annual interest is to be paid to
respondent. Cost of Rs.2,500/- was also awarded.
4. Appellant has challenged the order dated 2.9.2003 passed
in Case No.2B/2002 on the ground that award has been passed
dehors the terms of agreement; learned Arbitrator has erred in
rejecting the counter claim filed by the appellant; contractor was
not entitled to get any damages for short supply and non-supply
of any material including cement; no cogent reasons have been
assigned by Arbitrator in passing the award; order passed by sole
Arbitrator was perverse; Court below ought to have seen that
quality clearing certificate was must before payment was made
and it was submitted that impugned order is patently illegal,
erroneous and contrary to law.
5. Learned counsel appearing for the respondent submitted
that appeal against order in setting aside or refused to set aside
Arbitration award has been provided in Section 39 of the Act of
1940. It is submitted that once a decree is passed as per an
award, no appeal shall lie from said decree except on the ground
that it is excess of or not in accordance with the award. Civil
Court can set aside the award on the ground that Arbitrator or
umpire has misconducted himself or the proceedings, award had
been made after issue of an order by the court superseding the
Arbitration or after arbitration proceedings have become invalid
under section 35, and award has been improperly procured or is
otherwise invalid. The appellate court can examine whether Civil
Court committed an error in not setting aside the award though
grounds mentioned in Section 30 was available to the Court for
setting aside the award. In view of the aforesaid provisions,
there is no merit in the appeal filed by the appellant and appeal
may be dismissed.
6. Heard the counsel for appellant as well as respondents.
7. Before coming to the arguments raised by the parties, it is
necessary to outline the scope of interference by this court in
arbitration appeal. Sections 30 and 39 of Arbitration Act 1940 is
quoted as under:-
"30. Grounds for setting aside award:- An award shall not be set aside except on one or more of the following grounds, namely:-
(a) that an arbitrator or umpire has misconducted himself or the proceedings,
(b) that an award has been made after the issue of an order by the Court superseding the arbitration or after arbitration proceedings have become invalid under section 35;
(c) that an award has been improperly procured or is other- wise invalid.
39. Appealable orders. -(1) An appeal shall lie from the following orders passed under this Act (and from no others) to the Court authorised by law to hear appeals from original decrees of the Court passing the order:- An order-
(i) superseding an arbitration;
(ii) on an award stated in the form of a special
case;
(iii) modifying or correcting an award;
(iv) filing or refusing to file an arbitration
agreement;
(v) staying or refusing to stay legal proceedings
where there is An arbitration agreement;
(vi) setting aside or refusing to set aside an award;
Provided that the provisions of this section shall not apply to any order passed by a Small Cause Court.
(2) No second appeal shall lie from an order passed in appeal under this section, but nothing in this section shall affect or take away any right to appeal to the Supreme Court."
8. This court is also required to see whether the principle of
natural justice is violated or not. Considering the aforesaid law,
the grounds raised by appellant and respondent was considered.
9. Learned court below, after considering the arbitration
award, has come to a conclusion that there was delay on part of
appellant in providing hurdle free approach road due to agitation
of villagers and there was no delay on part of contractor in
making construction, therefore, counterclaim of appellant has
rightly been rejected. It was also held that arbitrator has not
exceeded his jurisdiction in going beyond the agreement in
passing the award.
10. If Arbitrator has passed an award lumpsum without giving
reasons then it cannot be said that he has misdirected himself or
has passed award contrary to agreement or exceeding the
agreement. Arbitration Act 1940 does not provide for giving
reason for passing the award. Further there was no agreement or
direction given to sole arbitrator to pass the award with reasons.
In view of same none of the grounds of Section 30 is available to
appellant for setting aside the award or remanding the matter
back to the sole arbitrator. Appellant as well as respondent was
given proper opportunity of hearing and both the parties adduced
their evidence, therefore, basic principle of natural justice has
been followed by the arbitrator. Arbitrator has not travelled
beyond the agreement in passing the award. Award has not been
made contrary to the terms of agreement.
11. Considering the aforesaid facts and circumstances of the
case there is no jurisdictional error in the award. Neither
Arbitrator nor umpire has misconducted himself or the
proceedings. Proper opportunity of hearing has been given to
both the parties.
12. In view of the aforesaid facts and circumstances of the
case, arbitration appeal filed by the appellant, is dismissed.
(VISHAL DHAGAT) JUDGE mms
Digitally signed by MONSI M SIMON Date: 2021.05.18 11:54:42 +05'30'
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!