Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

A.Ibrahimkutty vs The State Of Kerala & 3 Others
2026 Latest Caselaw 1835 Ker

Citation : 2026 Latest Caselaw 1835 Ker
Judgement Date : 19 February, 2026

[Cites 8, Cited by 0]

Kerala High Court

A.Ibrahimkutty vs The State Of Kerala & 3 Others on 19 February, 2026

Author: Sathish Ninan
Bench: Sathish Ninan
R.F.A.No.682/2010
                                           1


                                                                     2026:KER:14556

                    IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                     PRESENT

                    THE HONOURABLE MR. JUSTICE SATHISH NINAN

                                           &

                THE HONOURABLE MR.JUSTICE P. KRISHNA KUMAR

      THURSDAY, THE 19TH DAY OF FEBRUARY 2026 / 30TH MAGHA, 1947

                              RFA NO. 682 OF 2010

          AGAINST THE JUDGMENT DATED 10.06.2010 IN OS NO.194 OF 2000 OF

ADDITIONAL SUB COURT,KOLLAM

APPELLANT/PLAINTIFF:
           A.IBRAHIMKUTTY, GOVERNMENT CONTRACTOR
           VALIYATH HOUSE, PUTHENCHANTHA P.O., CHAVARA,
           KOLLAM-691587.

              BY ADVS.
              SRI.K.BABU THOMAS
              SMT.MARYKUTTY BABU


RESPONDENTS/DEFENDANTS:
     1     THE STATE OF KERALA , REPRESENTED BY THE
           SECRETARY TO GOVERNMENT (IRRIGATION DEPARTMENT),
           WATER RESOURCES DEPARTMENT,
           SECRETARIAT, TRIVANDRUM.

      2       THE CHIEF ENGINEER, IRRIGATION PROJECT III,
              PULAMON P.O., KOTTARAKKARA, KOLLAM.

      3       THE SUPERINTENDING ENGINEER
              KIP CIRCLE, KOLLAM.

      4       THE EXECUTIVE ENGINEER, KIP LB
              DIVISION NO.VII, KOTTIYAM, KOLLAM.

              BY SPECIAL GOVERNMENT PLEADER (IRRIGATION)
              SRI.P.I.DAVIS
      THIS     REGULAR    FIRST   APPEAL       HAVING   COME   UP   FOR   HEARING   ON
17.02.2026, THE COURT ON 19.02.2026 DELIVERED THE FOLLOWING:
 R.F.A.No.682/2010
                                          2


                                                                 2026:KER:14556



                 SATHISH NINAN & P. KRISHNA KUMAR, JJ.
                 = = = = = = = = = = = = = = = = = =
                         R.F.A.No.682 OF 2010
                 = = = = = = = = = = = = = = = = = =
              Dated this the 19th day of February, 2026

                                     JUDGMENT

P.Krishna Kumar, J.

The unsuccessful plaintiff in a suit for declaration and

recovery of money under a PWD works contract, is the

appellant. He challenges the impugned judgment by which the

reliefs sought by him were declined by the Sub Court.

2. For ease of reference, the parties are hereinafter

referred to as they were arrayed in the suit. The plaintiff

is an A-grade construction contractor to whom the work of

formation of a canal (KIP & TDCP LBC formation of Pallimon

distributory from Ch. 0 m to 7000 m, including CD works) was

awarded by the Public Works Department (PWD) pursuant to a

tender submitted on 21.02.1995. As per the letter of

acceptance dated 19.04.1995, he was informed that his tender

was accepted at (+) 35% above the estimated rate based on the

2026:KER:14556

1992 PWD Schedule of Rates. Accordingly, on 21.04.1995, he

executed an agreement with the third defendant, stipulating a

contract period of 18 months from the date of handing over

possession of the work site. Possession of the site was

handed over on the following day, i.e., 22.04.1995, and the

stipulated contract period was therefore to expire on

21.10.1996.

3. Briefly stated, the work involved earthwork

excavation for the formation of a canal and allied works. The

earthwork excavation was estimated at 2,00,650 cubic metres.

According to the plaintiff, commencement of the work was

delayed as the defendants took the initial levels for

excavation only on 01.11.1995. He further contended that the

defendants were bound to provide a dump yard for disposal of

surplus spoil obtained during excavation, as evidenced by

Ext.X2(a), pages 166 and 167. By Ext.A2 letter dated

03.11.1995, the plaintiff requested the defendants to provide

a dump yard at the earliest or, alternatively, to pay Rs.100

per cubic metre towards transportation of surplus spoil with

an average lead of 20 km from the site, as no disposal yard

2026:KER:14556

was available at a shorter distance.

4. Pursuant to Ext.A2, the plaintiff further contended

that the fourth defendant addressed the Special Tahsildar

(LA), Kottiyam, requesting acquisition of 20 acres of land

near the canal alignment for disposal of surplus spoil. The

Special Tahsildar reportedly intimated that acquisition would

require at least six months and would entail considerable

cost. The plaintiff alleges that the Chief Engineer and

subordinate officers thereafter inspected the site and the

dumping area suggested by him (with an average lead of 20 km

from the site, as stated in Ext.A2), and consequently

approved a rate of Rs.91.81 per cubic metre for conveyance of

the spoil (Ext.B7).

5. Meanwhile, the site was inspected by two Chief

Engineers, the Additional Secretary (Law Department), and the

Additional Secretary (Finance Department), along with other

senior PWD officials. They reportedly found that no land was

available for disposal of surplus spoil and recommended

payment of conveyance charges to the plaintiff. It is further

2026:KER:14556

alleged that the foundation of an aqueduct was set out and

measurements recorded on 06.03.1996, and that designs and

drawings were finalised introducing extra items, thereby

increasing the value of the work from Rs.4,76,63,804/- to

Rs.6,54,25,509/-. Although the contract period expired on

21.10.1996, the plaintiff was permitted to continue the work,

allegedly due to delays attributable to the defendants.

6. On 18.06.1997, the plaintiff addressed Ext.A17 letter

to the Minister for Irrigation and Labour, with copies to the

second and third defendants, stating that failure to provide

a dump yard had resulted in idling of men and machinery

deployed at the site, causing a loss of Rs.30,000/- per day

from April 1995 to November 1995. He further pointed out that

shortage of cement supply had also caused delays, resulting

in additional loss. On these grounds, he requested

enhancement of the agreement value by 40% (which would

effectively amount to 75% above the 1992 Schedule of Rates).

Alternatively, he sought to be relieved from his contractual

obligations upon payment of reasonable compensation for the

losses sustained.

2026:KER:14556

7. On 05.11.1997, the plaintiff submitted Ext.A19

representation to the Minister seeking payment of at least

75% of the conveyance charges. According to him, instead of

closing the agreement as requested in Ext.A17, the defendants

issued Ext.A26 letter dated 26.05.1999 threatening

termination of the contract. Thereafter, on 31.05.2000, the

plaintiff instituted the suit, principally seeking payment of

the unpaid value of the work already executed and recovery of

other outstanding amounts. He asserts that the value of work

carried out between 21.10.1996 and 01.07.1999 amounts to

Rs.4,23,55,521/-.

8. The plaintiff quantified the damages allegedly

suffered by him as follows:

a) Increased cost incurred for work executed beyond 21.10.1996 - Rs.1,75,74,616/-. He contends that the value of work executed within the original agreement period was only Rs.205 lakhs and, therefore, for the amount already paid to him (Rs.4,23,55,521/-), he is entitled to an additional 50% of the net value, which comes to Rs.3,51,49,232/-.

b) Increased cost of work executed beyond 27.03.1999 - Rs.14,10,000/-, calculated at 117.5% over and above the agreement rates, for work valued at Rs.12,00,000/-.

2026:KER:14556

c) Additional establishment charges beyond 21.10.1996 - Rs.16,80,000/-, computed at Rs.40,000/- per month for 42 months beyond 21.10.1996.

d) Compensation for conveyance and disposal of surplus spoil

- Rs.3,05,71,536/-, calculated on the basis that for excavation of 2,46,664 cubic metres (including bulkage), he is entitled to Rs.91.81 per cubic metre, also applying the revised schedule rate at Rs.123.94 per cubic metre.

e) Idling charges for men and machinery at site - Rs.22,50,000/-, calculated at Rs.30,000/- per day for 175 days, though the claim is restricted to the above amount.

The total amount claimed is Rs.5,56,86,152/-.

9. The plaintiff also sought a declaration that the

undertakings/supplementary agreements executed by him for

extension of time were vitiated by undue influence, coercion,

and duress. He further prayed for a declaration that the

defendants had flagrantly violated the terms of the contract

and unlawfully prolonged the contract period beyond

21.10.1996, thereby rendering themselves liable to reimburse

the increased cost as reflected in the revised Schedule of

Rates of 1996 and 1999.

10. The defendants contended that the suit was not

2026:KER:14556

maintainable and that the claims raised in the plaint were

baseless. According to them, the contract period was extended

up to 31.10.1999 at the request of the plaintiff, who had

failed to execute the work within time due to his own

shortcomings. The work had not been completed even at the

time of filing the suit. The contract amount as per the

original agreement was Rs.3,72,80,974/-. The plaintiff had

thereafter requested extension of time up to 30.06.2001 for

completion of the work.

11. The department asserted that all materials,

including cement, were supplied promptly, and that 11 part

bills had been prepared and payments made in time. Despite

all facilities being extended by the department, the

plaintiff failed to complete the work within the stipulated

period. As per Clause 16 of the Special Conditions of Form

No.83, which formed part of the agreement, it was the

responsibility of the plaintiff to obtain land for stacking

excess cut earth. Therefore, the defendants had no obligation

to provide a dump yard. The PWD had provided lorry conveyance

up to 5 kilometres to transport earth to a dumping yard to be

2026:KER:14556

arranged by the plaintiff.

12. The plaintiff had informed the department that he

could acquire a dumping yard situated more than 20 kilometres

away, alleging scarcity of dumping sites along the canal

banks or within 5 kilometres. The Chief Engineer, Project III

(Kallada), inspected the canal site and discussed the matter

of conveyance. Upon receipt of a letter from the plaintiff,

the same was forwarded to the Tahsildar (LA), who reported

that land valued at Rs.3,000/- to Rs.5,000/- per cent was

available within a 5-kilometre radius. This, according to the

defendants, demonstrated that the contractor could have made

his own arrangements within the permissible distance.

13. Senior departmental officials inspected the site and

considered allowing conveyance up to 20 kilometres at

Rs.49.80 per cubic metre (after deducting the cost of earth

and minimum lorry conveyance for 5 kilometres), subject to

completion of the work within the stipulated period of

21.10.1996. However, the Government rejected the proposal. By

that time, the contractor had completed only 50% of the total

earthwork, and the shortfall was allegedly due to his

2026:KER:14556

negligence.

14. Thereafter, the agreement period was extended at the

plaintiff's request. The defendants contended that, having

executed supplementary agreements undertaking to carry out

the work at the agreed rates, the plaintiff was not entitled

to any additional amount. It was further argued that a

contractor is required to quote rates after studying the

specifications and site conditions at the time of tender

submission, and therefore the plaintiff cannot seek extra

payment on the ground of increased conveyance expenditure.

Moreover, the plaintiff had not disclosed the exact location

of his alleged dumping yard, making it impossible to verify

the actual distance or quantity of earth dumped there, which

was mandatory under the agreement.

15. During trial, the plaintiff examined himself as PW1

and marked Exts.A1 to A35. The defendants examined DW1 to DW6

and marked Exts.B1 to B37. In addition, Ext.C1 Commission

Report and Exts.X1 to X11 series were marked in evidence.

Upon conclusion of the trial, the learned Sub Judge found

that the plaintiff had failed to establish his case and

2026:KER:14556

consequently dismissed the suit.

16. We have heard Sri Babu Thomas K., learned counsel

for the appellant, and Sri P.I. Davis, Special Government

Pleader (Irrigation).

17. In view of the rival contentions, the following

points arise for consideration in this appeal:

1. Whether the plaintiff is entitled to any compensation for conveyance and disposal of surplus spoil?

2. Who is responsible for the delay in execution of the work within the stipulated period?

3. Whether the plaintiff is entitled to any additional amount as compensation for the work executed beyond the agreed period?

18. One of the principal disputes raised by the

plaintiff relates to the amount allegedly payable to him

towards conveyance and disposal of surplus spoil, on account

2026:KER:14556

of the defendants' failure to provide a dumping yard within 5

kilometres. The claim pertains to the expenditure allegedly

incurred by him in transporting the spoil from the work site

to three dumping yards identified by him, said to be situated

at an average distance of 20 kilometres from the site. The

plaintiff contends that, although the defendants were bound

to provide dumping yards, they failed to do so, compelling

him to locate alternative dumping sites and transport the

spoil thereto.

19. The plaintiff relied upon Clause 2 of the

Specification for the canal work under the Kallada Irrigation

Project and contended that the land required for the works to

be constructed under the contract, including necessary borrow

pits, channels, spoil banks, drains, etc., would be provided

by the Government. It was argued that only a limited quantity

of surplus spoil could be accommodated along the canal banks

and, therefore, in the absence of a dumping yard, the

contractor could not have proceeded with the work.

20. The defendants resisted the said claim, contending

2026:KER:14556

that it was the contractor's responsibility to arrange his

own dumping yard. Relying on Clause 16 of the Special

Conditions forming part of the agreement, it was argued that

the duty to secure land for stacking excess cut earth rested

with the contractor. Clause 16 reads as follows:

"16. It will be the responsibility of the contractor to obtain necessary land for stacking the materials for arranging the work."

The learned Government Pleader further submitted that the

quantity of excavated earth had to be measured strictly in

accordance with the agreement. According to him, the contract

provided for payment of conveyance charges only up to 5

kilometres, and the report of the Tahsildar (LA) indicated

availability of private lands suitable for dumping the spoil

within that radius. Therefore, the plaintiff could have made

arrangements accordingly. It was also contended that,

although the plaintiff claimed to have established dumping

yards 20 kilometres away from the work site, he did not

disclose the precise location of such dumping yards at any

point of time, except when he sought appointment of a

2026:KER:14556

Commissioner.

21. The first aspect that arises for determination is

whether the defendants were bound to provide dumping yards.

The appellant contends that Clause 2 of the Specification

obliges the Department to provide spoil banks, thereby

requiring it to make available the necessary dumping yards.

We are unable to accept this contention. "Spoil banks" refer

to places adjacent to the canal formation site where the

excavated soil is deposited. No specific clause imposing an

obligation upon the defendants to provide separate dumping

yards has been brought to our notice. Hence, we find no basis

to hold that the defendants were bound to provide dumping

yards.

22. However, that alone does not conclude the issue. It

is undisputed that the contract rates for excavation and

removal of spoil included conveyance charges only up to 5

kilometres. According to the plaintiff, since the defendants

were unable to provide dumping yards within that distance, he

was compelled to transport and dump the spoil at locations

2026:KER:14556

situated 20 kilometres away. In this context, a High-Level

Committee consisting of Government Secretaries, Chief

Engineers of the Department, the District Collector, and

other officials was constituted. After examining the matter,

the Committee submitted Ext.A5 report dated 20.06.1996.

23. The Committee noted that no land was available

within a 5-kilometre radius for use as a dumping yard and

that acquisition of land was the only option. As the

acquisition process would be both expensive and time-

consuming, the Chief Engineer recommended that the contractor

be directed to arrange his own dumping yard and proposed a

rate of Rs.49.80 per cubic metre (after deducting the value

of the spoil and the conveyance charges for 5 kms). Although

this recommendation was subsequently rejected by the

Government, the plaintiff contends that he is entitled to

compensation at least at the rate recommended by the Chief

Engineer.

24. Merely because Engineers or other senior officials

made such recommendations, in the absence of any contractual

2026:KER:14556

provision obligating the Government to arrange a dumping

yard, the plaintiff cannot stake a claim upon such

recommendations, especially when the recommendation is not

made according to the contractual terms. The plaintiff cannot

claim any additional amount for a work that falls within the

basic scope of the contract awarded to him. In the absence of

a specific stipulation to the contrary, it was necessarily

the obligation of the contractor to secure a suitable place

at his own cost. In this regard, the observations of the

trial court are apposite:

"As rightly contended by the learned government pleader, spoil bank-drains is a separate work that is meant to catch and resist water from entering into the canal. So there is no basis or foundation for the plaintiff's case that the defendants agreed to provide dumping yard for the excess spoil. On the other hand, in Ext.B9 estimate report in appendix L(a) canal formation it is specifically the quantity of the earth that can be accommodated at site is ascertained by calculating the area of spoil bank available and provision for conveying the balance quantity to contractors own dump yard outside is given. So in the estimate itself it is provided that the excess spoil is to be dumped in the contractors own dumping yard. In Ext.B1(n) it is provided that the spoil will be deposited on the banks or at places pointed out by the engineer in charge with all leads and lifts. That means the conveyance is to be made by the contractor himself.

Ext.B9 estimate report coupled with Ext.B12 circular of the government makes it very clear that when the contract was entered into between the plaintiff and 3rd defendant, the intention of the government who is the owner of the work was

2026:KER:14556

to render the plaintiff responsible for taking the excess spoil and dumping the same. It is true that the officers of defendants 2 to 4 inspected the site and noted the absence of acquired land for dumping yard for disposal of surplus soil. It is equally true that a high level committee was constituted and the committee recommended for acquiring land for providing dump yard. But these act of the officers of defendants 2 to 4 will not give any authority to the plaintiff to claim that he is entitled to dump yard at the instance of the defendants. The plaintiff failed to prove that there is such a stipulation in the contract."

As certain trial court records, including those referred to

in the above observations, were reportedly missing from the

court, the significance of the above findings is further

accentuated. In any event, it can safely be concluded that

the contractor is not entitled to claim compensation based

solely on the recommendations of officials that were

ultimately rejected by the Government.

25. The learned Government Pleader raised an additional

contention that the contractor had sold the surplus spoil. It

was pointed out that the Chief Engineer fixed the conveyance

rate at Rs.49.80 per cubic metre after deducting the value of

the spoil, which implied that the spoil was at the

contractor's disposal. It was argued that, if the contractor

had sold the spoil, he could not claim any conveyance

2026:KER:14556

charges. However, there is no material on record to

substantiate this contention. Moreover, it is seen that this

plea was introduced by the defendants by way of amendment to

the written statement only after the conclusion of final

arguments.

26. Be that as it may, the plaintiff has failed to

establish that he actually transported the spoil to distant

locations. The fact that he did not disclose the alleged

dumping sites even in Ext.A28 suit notice casts serious doubt

on his claim. In the plaint as well, precise locations were

not specified; only the names of certain places were

mentioned. This aspect assumes considerable significance. The

plaintiff asserts that those sites were situated at an

average distance of 20 kilometres from the canal site. As

rightly contended by the learned Government Pleader, apart

from vague pleadings in the plaint, there is no material to

show that the plaintiff had, at any point, intimated the

defendants regarding the alleged dumping sites.

27. In an attempt to prove that he transported the spoil

to the three locations mentioned in the plaint, the plaintiff

2026:KER:14556

took out a Commission, which resulted in Ext.C1 report.

Significantly, the trial court found the report unreliable.

We also find that the evidence of the Expert Commissioner,

examined as DW5, does not inspire confidence. He claimed to

have seen documents showing that the plaintiff had intimated

the defendants about the three dumping sites. However, no

such document is forthcoming. The learned counsel for the

plaintiff fairly conceded that no such document exists and

that the locations were mentioned for the first time in the

plaint. On the materials available, we are unable to conclude

that the spoil was in fact transported and dumped by the

plaintiff at the three locations stated in the plaint,

allegedly situated more than 20 kilometres from the canal

site.

28. Sri Babu Thomas, learned counsel appearing for the

plaintiff, contended that since the total stretch of the work

extended to 7 kilometres, the plaintiff would necessarily

have had to transport the spoil for a distance exceeding 5

kilometres at least at certain points. We are unable to

accept this submission as a matter of inevitability. The

2026:KER:14556

distance required for conveyance would depend upon the

precise location where the spoil was ultimately dumped. It is

conceivable that the spoil could have been deposited at a

point situated between the two farthest ends of the stretch.

Therefore, it cannot be presumed that dumping the spoil

necessarily required transportation beyond 5 kilometres.

29. When the plaintiff claims damages on the ground that

he carried out additional work by transporting spoil to a

distant location, it was incumbent upon him to establish the

same with precision and cogent evidence. In the absence of

satisfactory proof regarding the actual place and distance of

dumping, the claim cannot be sustained. Accordingly, we

conclude that the plaintiff is not entitled to any amount

towards conveyance and disposal of surplus spoil.

30. The next issue to be considered is as to who was

responsible for the delay in execution of the work. It is

undisputed that the original contractual period expired on

21.10.1996. It is equally undisputed that the plaintiff

executed supplementary agreements/undertakings seeking

extension of time for completion of the work, agreeing

2026:KER:14556

therein that he would not claim any additional amount for the

extension of time.

31. At the same time, the evidence indicates that, for a

considerable period, both parties were genuinely uncertain as

to the location where the surplus spoil was to be dumped,

particularly when it became evident that the entire quantity

of excavated earth could not be accommodated along the canal

banks. It took several months to resolve this issue.

32. Further, Ext.A7 reveals that the Chief Engineer,

Project III (Kallada), Kottarakkara, addressed a

communication dated 03.07.1996 to the Chief Engineer, Project

III, Thiruvananthapuram, stating that there was no stock of

cement available in any of the KIP stores and that the work

had remained at a standstill for the preceding four months.

The letter further requested urgent supply of 4,855 metric

tonnes of cement for the work. (It is noteworthy that Ext.A7

was produced before the court in its original form, even

though a copy had not been marked to the plaintiff. Learned

counsel on both sides were unable to explain how the original

came into the plaintiff's possession. However, as the

2026:KER:14556

document was marked in evidence without objection, this

circumstance is of no consequence.) Though the trial court

observed that as per paragraph 39 of Ext.B1(c) notice

inviting tender, the plaintiff could not have made a claim

for extra payment on account of the delay in supply of

materials, the fact that non-supply of materials caused delay

in completing the work, is a factor relevant for the present

consideration.

33. Similarly, DW2, the Superintending Engineer of the

Public Works Department, discloses in cross examination that

there was some delay in taking level measurements and

completing the related formalities, which were essential

prerequisites for commencement of the contractual work.

34. However, referring to Ext.B16 and B20, the learned

Government Pleader contended that the delay in taking level

measurements was attributable solely to the plaintiff's

failure to appoint a Site Engineer. Engagement of a Site

Engineer prior to commencement of level measurement was

mandatory under the agreement, it was pointed out.

2026:KER:14556

35. Placing reliance on the decision of the Hon'ble

Supreme Court in State of Kerala and Another v. M.A. Mathai

(AIR 2007 SC 1537), the learned Government Pleader further

submitted that, under Sections 55 and 56 of the Indian

Contract Act, 1872, delay in performance may give rise to a

claim for compensation or frustration of contract. However,

where the contractor seeks extension of time and undertakes

to execute the work without claiming any additional amount,

he is estopped from subsequently raising such claims.

36. According to the learned Government Pleader, in view

of the undertakings contained in Ext.B27 and other

supplementary agreements, wherein the plaintiff expressly

agreed not to seek any further claim for extension of the

contractual period, no additional amount can be awarded to

him on that ground.

37. Relying on the decision of the Hon'ble Supreme Court

in General Manager, Northern Railway and Another v. Sarvesh

Chopra [(2002) 4 SCC 45], Sri Babu Thomas K., learned counsel

for the plaintiff, contended that even where a contract

contains a clause under which the contractor undertakes not

2026:KER:14556

to make any claim for delay attributable to the employer,

such a claim would nevertheless be maintainable if the

contractor repudiates the contract or clearly communicates

that escalation of rates or compensation for delay must be

granted by the employer.

38. The learned counsel placed reliance on Ext.A17

letter addressed by the plaintiff to the Minister, with a

copy to the Chief Engineer, to substantiate his contention

that the plaintiff had made his position explicit. In the

said communication, the plaintiff stated that, if he were to

proceed further with the contract, additional charges on

account of delay and related expenses would have to be paid.

Alternatively, he expressly sought to be relieved of his

contractual obligations upon payment of reasonable

compensation.

39. Upon evaluating all the circumstances brought to our

attention, we find that the delay in execution of the work

was occasioned partly by lapses of the defendants and of

course, the plaintiff could not claim to be fully absolved

from it. Undoubtedly, the plaintiff executed Ext.B27 and

2026:KER:14556

other supplementary agreements on various dates seeking

extension of time, undertaking that he would not claim any

additional amount on account of delay. At the same time, we

notice that the element of economic duress pervades these

transactions, as evidenced by the fact that part bills were

mostly passed only after execution of such undertakings.

Though part bills could have been encashed monthly, they

were, in certain instances, encashed only after the plaintiff

furnished corresponding undertakings. DW2, a senior officer

of PWD, deposed in cross-examination as follows:

"21.10.96 ൽ വവാദദിയ്ക്കു പണദിചചെയ്തതദിൽ വച്ചു ചകവാടുകവാൻ ഉണവായദിരുന്ന 5381185/- രൂപ വവാദദിയ്ക്കു ചകവാടുകവാചത പ്രതദികൾ 28.12.96 വചരെയയും പദിടദിച്ചു വചദിരുന്നദിലല്ലേ (Q) പദിടദിച്ചു വചദില്ലേ, ചകവാടുതദിരുന്നദില്ലേ."

(Page 7)

"ഈ Ext .A 26 notice issue ചചെയ്തു 26-5-99 ൽ പ്രതദികൾ വവാദദിയ്ക്കു പണദി ചചെയ്തതദിൽ വച്ചു ചകവാടുലകണ Rs 4162276/- വവാദദിയ്ക്കു ചകവാടുകവാചത പദിടദിച്ചു വചദിരുന്നലല്ലേവാ എന്നു പറഞവാൽ ശരെദിയലല്ലേ (Q) മനപ്പൂർവയും ചകവാടുകവാതദിരുന്നതല്ലേ (A). "

(Page 11)

"Ext .B 1 (f) ൽ ഒപദിടദില്ലേവായദിരുചന്നങദിൽ ഈ രൂപ 7124565/- pay ചചെയദില്ലേവായദിരുന്നലല്ലേ (Q) പണയും release ചചെയദില്ലേവായദിരുന്നലല്ലേവാ (Q) പണയും release ചചെയദില്ലേവായദിരുന്നു.

Supplementary agreement sign ചചെയണമവായദിരുന്നു (A)"

(Page 11)

Thus, DW2 conceded that the department would not have passed

2026:KER:14556

the bills for the work already executed by the plaintiff

unless he furnished the undertakings, and that the bills were

kept pending for some time, obviously without any justifiable

reason. Hence, the plaintiff's contention that he was

compelled to execute the undertakings to secure clearance of

his bills appears probable. This circumstance must be read in

conjunction with the stand adopted by the plaintiff in

Ext.A17, wherein he unequivocally conveyed as follows:

"The schedule of rates has been revised upward by the department with affect from 7/96 and the increases is about 40%. Considering all these facts I am entitle to get enhanced rates at the current schedule of rates (revised rates) + 75% excess for all the times of works being executed in the extra contractual period. Since the delay in the completion of the work with in the stipulated programme is solely due to the slackness from the part of the department........

Otherwise, I request to relieve me from the contractual obligations which are violated by the department with reasonable compensation to me for the losses sustained by me which are explained above."

40. These circumstances lead us to conclude that,

notwithstanding the execution of undertakings while seeking

extension of time, the plaintiff is entitled to some

compensation for the delay in completion of the work. The

presence of economic duress is discernible from the attendant

2026:KER:14556

facts and circumstances. When such undertakings are executed

under economic duress, they do not preclude the plaintiff

from claiming reasonable compensation for the losses suffered

due to the delay. In Central Inland Water Transport

Corporation Ltd. & Anr. v. BrOjo Nath Ganguly & Anr. [(1986)

3 SCC 156), the Hon'ble Supreme Court held that courts would

not enforce an unfair or unconscionable term of contract, if

the bargaining power of parties is unequal, and especially

where the inequality of bargaining power is the result of the

great disparity in the economic strength of the contracting

parties. In M/s. Ambica Construction v. Union of India [2006

(13) SCC 475], also the Hon'ble Supreme Court adopted a

similar view. In State of Kerala v. P.P.Thomas (2024 KHC

801), this Court held that when parties are not on equal

footing with respect to the bargaining power and when one

party is in a position to exploit the other party, the

supplementary agreements signed by vulnerable party without

free consent is not legally enforceable as the same is

opposed to public policy and void in the eyes of law.

41. We shall now determine the quantum of such

2026:KER:14556

compensation. Ext.A17 indicates that a substantial portion of

the work had been completed by the time the plaintiff issued

the said letter. Although the plaintiff contended that

certain works continued up to 2003 and that some spill-over

works were undertaken even in 2006, the evidence suggests

that these were minor in nature and that the substantial part

of the work had been completed by 1997-98.

42. The learned counsel for the plaintiff relied upon

the decision in P.M. Paul v. Union of India [(1989) Supp. 1

SCC 318], wherein the Hon'ble Supreme Court observed that

price escalation is a normal incident arising from the lapse

of time in performing contracts in an inflationary economy,

and upheld the grant of 20% compensation for delay in

performance. It was further contended that, having regard to

the revised PWD Schedule of Rates (Ext.A34) brought into

effect from 01.07.1999, compensation ought to be fixed at 15%

per annum.

43. However, as noted earlier, the plaintiff also

contributed to the delay. Taking into account the totality of

2026:KER:14556

circumstances, we consider it just and reasonable to award

compensation to the plaintiff at 10% over and above the

awarded amount. Admittedly, the original amount awarded

(Rs.4,76,63,804/-) was revised to Rs.6,54,25,509/- by

24.04.1996 and the same was later further revised to

Rs.7,32,12,545/- [Ext.X5(a)]. Thus, the plaintiff is entitled

to get Rs.73,21,254.5/-, being the 10% of Rs.7,32,12,545, the

amount awarded under the contract.

44. There is no reason to decline interest on the said

amount, from the date of suit. Granting interest at 6% would

be just and reasonable.

In the result, the appeal is allowed in part and the

impugned judgment is set aside. The appellant/plaintiff is

entitled to get Rs.73,21,254.5/-, with 6% interest from the

date of the suit. The appellant is entitled to get

proportionate costs throughout. Sd/-


                                                         SATHISH NINAN, JUDGE



sv                                                                  Sd/
                                                       P. KRISHNA KUMAR,JUDGE
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter