Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

John Mathew vs J.M.Titus
2025 Latest Caselaw 9013 Ker

Citation : 2025 Latest Caselaw 9013 Ker
Judgement Date : 22 September, 2025

Kerala High Court

John Mathew vs J.M.Titus on 22 September, 2025

RFA 251/2006


                                    1

                                                            2025:KER:70417

                 IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                   PRESENT

               THE HONOURABLE MR. JUSTICE C.PRATHEEP KUMAR

     MONDAY, THE 22ND DAY OF SEPTEMBER 2025 / 31ST BHADRA, 1947

                            RFA NO. 251 OF 2006

                 OS NO.89 OF 1999 OF SUB COURT, PATHANAMTHITTA


APPELLANT/DEFENDANT

               JOHN MATHEW,
               ANUGRAHA VADAKKETHIL HOUSE, ATTARIKAM MURI, OMALLUR
               VILLAGE, KOZHENCHERRY TALUK, PATHANAMTHITTA DISTRICT.

               BY ADVS.
               SRI.R.D.SHENOY (SR.)
               SRI.MATHEW JOHN (K)
               SHRI.SUJESH MENON V.B.
               SRI.S.VINOD BHAT
               SMT.V.NAMITHA
               KUM.ANAGHA LAKSHMY RAMAN
               SMT.GITANJALI SADAN PILLAI


RESPONDENT/PLAINTIFF

               J.M.TITUS, S/O MATHAI JOSEPH,
               ULUVATH BUNGLOW, THATTARAMPALAM, KUNNAMANGALAM VILLAGE,
               MAVELIKKARA TALUK, ALAPPUZHA DISTRICT.

               BY ADVS.
               SHRI.LAL K.JOSEPH
               SMT.ROSHAN THOMAS
               SRI.RAKESH DAWNY KOKKATTU
               SMT.M.C.SANITHA


       THIS    REGULAR   FIRST   APPEAL   HAVING   BEEN   FINALLY   HEARD   ON
11.9.2025, THE COURT ON 22.09.2025 DELIVERED THE FOLLOWING:
 RFA 251/2006


                                          2

                                                                 2025:KER:70417

                                      JUDGMENT

Dated : 22nd September, 2025

The defendant in O.S. 89/1999 on the file of the Sub Court, Pathanamthitta

is the appellant. (For the purpose of convenience, the parties are hereafter referred

to as per their rank before the trial court).

2. The plaintiff is a contractor who had entered into an agreement with

the defendant for constructing a residential building for the defendant. As per the

contract, the construction was to be carried out in accordance with the approved

plan. The construction charges for every stage of work was mentioned in the

contract. According to the plaintiff, as per the oral agreement he has made

additional constructions also, such as construction of compound wall, courtyard

etc. The defendant paid an amount of Rs.3,12,500/- as construction charge of the

outhouse. The plaintiff used to put his signature in the account book maintained by

the defendant for receipt of every payment. The plaintiff completed the

construction of the main building by the end of April 1998 using high quality

materials and skilled labourers. The defendant paid a total sum of Rs.20,05,000/- to

the plaintiff in seven instalments. The defendant had to pay an amount of

Rs.25,000/- to the sub contractor, Mani and Rs.20,000/- to the tarring contractor.

The value of the materials supplied by the defendant is calculated at Rs.73,265/-.

As per the measurements, the actual amount to be paid by the defendant is

2025:KER:70417

Rs.24,92,640/- and the amount due for the additional work will come to

Rs.3,06,044/-. Therefore, the total amount due to the plaintiff will come to

Rs.28,85,207/- including Rs.41,523/- paid to the sub contractors. However, the

defendant paid only a sum of Rs.21,23,265/- to the plaintiff, leaving a balance

amount of Rs.7,61,942/-. Therefore, the plaintiff filed the suit for realising the said

amount from the defendant.

3. The defendant filed a written statement admitting the agreement

entered into with the plaintiff. However, he denied having any oral agreement with

the plaintiff. According to the defendant, he had supplied Teak-wood for making

doors and windows, instead of Anjili wood. Out of 131.5 cubic feet of Teak-wood

supplied to the plaintiff, he had used only 80 cubic feet and the defendant is

entitled to realise a sum of Rs.90,075/- from the plaintiff being the value of the

above Teak-wood. The plaintiff and defendant together have not engaged any sub

contracts as alleged. After the completion of the construction, when the defendant

measured out the plinth area of the house with the assistance of an engineer of

GCDA, it was found that there was marked variation in the measurement taken by

the plaintiff. As per the measurement by the plaintiff, the plinth area of the ground

floor is 2855.5 sq. feet and that of the first floor is 2583.5 sq.feet. But the actual

measurement of the ground floor is 2356.5 sq.feet and the first floor is 1742 sq.feet

and there is a difference of 1340.5 sq. feet, for which he is entitled to get only a

sum of Rs.18,44,325/-. In fact, the defendant paid an excess amount to the plaintiff.

2025:KER:70417

According to the defendant, though as per the agreement, enamel pointing work of

the doors and windows of the grills are to be done by the plaintiff, while those

works were done by the defendant himself. The plaintiff/defendant had done

painting work of the grills and compound walls having area of 384 sq. feet and

hence the defendant is entitled to get a sum of Rs.20,984/- from the plaintiff in that

account. The defendant spent a total sum of Rs.47,240/- for snow-sum painting

which is liable to be realised from the plaintiff. Though the plumbing work for the

water supply was done by the plaintiff, it was defective and rendered unfit for use,

due to poor workmanship. The defendant had to spend Rs.12,380/- for rectifying

the defect in the plumbing work. The floor of the bathroom was done by the

defendant spending Rs.47,000/-. The defendant supplied hinges and locks for the

door worth Rs.4,065/-. The construction and roofing of the building was highly

defective. There was leaking from the roof concrete slabs and in order to rectify the

same, the defendant spent an amount of Rs.1,80,000/-. He also spent a sum of

Rs.4,000/- for replacing the defective water tank constructed by the plaintiff. He

had spend a sum of Rs.10,000/- for repair of the approach road towards his house.

Therefore, the defendant claimed that he is entitled to get a total sum of

Rs.4,05,714/- from the plaintiff and the same was raised as a counter claim.

4. The plaintiff filed a written statement to the counter claim denying

the claims made in the counter claim. The trial court framed three issues. The

evidence in the case consists of the oral testimonies of PWs1 and 2 and DWs1 to

2025:KER:70417

3, Exts.A1 to A4 and B1 to B5 were marked. After hearing both sides and

evaluating the evidence on record, the trial court decreed the suit in part allowing

the plaintiff to realise a sum of Rs.4,97,635/- along with interest at the rate of 12%

per annum and dismissed the counter claim. Aggrieved by the above judgment and

decree of the trial court, the defendant preferred this appeal raising various

grounds.

5. Now the point that arises for consideration is the following :

Whether the impugned judgment and decree of the trial court calls for any

interference in the light of the grounds raised in the appeal ?

6. Heard Sri.S.Vinod Bhat, the learned counsel for the appellant and

Sri.Lal K.Joseph, the learned counsel for the respondent.

7. The point :- Admittedly, the plaintiff entered into Ext.A1 agreement

with the defendant for the construction of a residential building for the defendant.

As per the terms of Ext.A1, the construction of the residential building is to be

carried out as per the approved plan and the rate fixed for the construction is

Rs.450/- per sq.feet. With regard to the total extent of the construction there is

dispute between the parties. According to the plaintiff, the area of the ground floor

is 2855.5 sq. feet and that of the first floor is 2583.5 sq.feet. However, according to

the defendant, the area of the ground floor is 2356.5 sq.feet and that in the first

floor is 1742 sq.feet. In the above circumstances, a Commissioner was deputed and

he filed a report which was marked as Ext.C1. The Commissioner was also

2025:KER:70417

examined as PW2. As per the commission report, the area of the ground floor is

2370 sq.feet and of the ground floor is 2254 sq.feet. Therefore, the total constructed

area in both the floors will come to 4624 sq.feet. Accepting the above measurement

taken by the Advocate Commissioner with the help of an expert engineer, the trial

court has found that the total extent of construction is 4624 sq.feet and I do not find

any grounds to disbelieve the above area fixed by the trial court. Therefore, the cost

of construction of the first floor and ground floor as per the agreement as fixed by

the trial court does not call for any interference.

8. For the construction of the car porch, the area of passage (open space)

and area of balcony, the trial court has granted only 60%, 50% and 50%

respectively of the agreed rate. Such a rate was fixed on the ground that those

constructions do not require supporting walls and as such, the value for the above

constructions fixed by the trial court also appears reasonable and does not call for

any interference.

9. In the plaint the plaintiff claims that in addition to the constructions

specified in Ext.A1 agreement as per the oral understanding with the defendant, he

had carried out several additional works which are specified as items 2 to 4 in the

plaint. Though in the written statement, the defendant denied having entered into

such oral agreement, at the time of evidence the defendant as DW1 fairly conceded

that all the works mentioned in items 2 to 4, except serial No.23 in item No.2, was

constructed by the plaintiff at his request. In the above circumstances, the cost of

2025:KER:70417

construction assessed by the trial court for the above additional constructions after

deducting serial No.23 in item No.2, also does not call for any interference.

10. At the time of arguments, the main ground raised by the learned

counsel for the appellant is with regard to the rejection of the counter claim.

According to the learned counsel, several works proposed to be done by the

plaintiff were to be carried by the defendant and as such the defendant is entitled to

get the said amount adjusted as claimed in the counter claim. However, according

to the learned counsel for the respondent/plaintiff, none of the works undertaken by

the defendant are part of Ext.A1 agreement, but interior works which come beyond

the scope of Ext.A1. Therefore, according to the learned counsel for the plaintiff,

the defendant is not entitled to adjust the amount spent by him for interior

decoration, from the amount due to the plaintiff.

11. The learned counsel for the appellant has relied upon the evidence of

DW3 and Ext.B4 series of receipts to substantiate his claim regarding the counter

claim. However, during the cross-examination of DW1 he admitted that he himself

has assessed the cost of construction of the building and found that the amount

quoted by the plaintiff was 30% more than the actual amount and as such, he has

deducted 30% from the amount paid to the plaintiff. Out of the counter claim raised

by the defendant, a sum of Rs.1,80,000/- is towards the amount required for

rectification of the defective construction, Rs.4000/- is for replacement of defective

water tank and Rs.90,075/- is towards the value of Teak-wood supplied. In this

2025:KER:70417

case, there is absolutely no reliable evidence to prove that there was any defect in

the construction carried out by the plaintiff so as to require such a huge amount for

rectification. Similarly, there is no reliable evidence to prove that the Teak-wood

supplied by the defendant was not used for the construction of the residential

building and that it was misappropriated by the plaintiff. Similarly there is also no

evidence to prove that he had to replace the defective water tank as claimed. The

remaining amount claimed are towards enamel painting, cost of snow-sum

painting, cost of hinges and locks, cost incurred by the defendant for re-installation

of the plumbing work and cost incurred for flooring of the bathrooms and walls etc.

In the plaint itself the plaintiff has admitted the cost of some materials supplied by

the defendant. In order to prove that the defendant has incurred additional

expenditure in respect of the work undertaken by the plaintiff, there is no reliable

evidence. In the above circumstances, the trial court was justified in holding that

the defendant has failed in proving the counter claim. I do not find any grounds to

interfere with the above finding of the trial court as well.

12. With regard to the total amount paid by the defendant to the plaintiff

also, there is dispute. According to the plaintiff, he received only Rs.20,05,000/-,

but according to the defendant he paid a sum of Rs.20,95,000/-. According to the

plaintiff, whenever he received payment, he put his signature in the register

maintained by the defendant. Ext.B5 is the copy of the account book maintained by

the defendant in that respect. On a perusal of Ext.B5 it can be seen that in the above

2025:KER:70417

register, the plaintiff has affixed his signature only for the period upto 14.4.1997.

Thereafter, in the remaining entries there is no signature of the plaintiff. In the

above circumstances, it is to be held that Rs.20,05,000/- as admitted by the plaintiff

alone is to be taken as the amount paid by the defendant. Therefore, the finding of

the trial court in that respect also does not call for any interference.

13. At the time of argument, the learned counsel for the appellant

submitted that the trial court has awarded interest at the rate of 12% per annum,

which is on the higher side. Considering the fact that this is only a suit filed for the

amount spent for the construction of the residential building and not a business

transaction, I hold that interest awarded by the trial court at the rate of 12% is on

the higher side and I hold that interest at the rate of 9% will be reasonable. I do not

find any grounds to interfere with the other findings of the trial court. Points

answered accordingly.

14. In the result, this appeal is dismissed, subject to the condition that the

rate of interest is reduced from 12% to 9% per annum. Considering the facts,

parties are directed to bear their respective costs in this appeal.

All pending interlocutory applications in the appeal will stand dismissed.

Sd/-

C.Pratheep Kumar, Judge Mrcs/15.9.25

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter