Sunday, 19, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

B Tech Engineering vs State Of Kerala
2025 Latest Caselaw 409 Ker

Citation : 2025 Latest Caselaw 409 Ker
Judgement Date : 1 July, 2025

Kerala High Court

B Tech Engineering vs State Of Kerala on 1 July, 2025

Author: N.Nagaresh
Bench: N.Nagaresh
                                                        2025:KER:47409


               IN THE HIGH COURT OF KERALA AT ERNAKULAM

                               PRESENT

                 THE HONOURABLE MR.JUSTICE N.NAGARESH

        TUESDAY, THE 1ST DAY OF JULY 2025 / 10TH ASHADHA, 1947

                       WP(C) NO. 17391 OF 2025

PETITIONERS:

    1       B TECH ENGINEERING
            BUILDING NO.39/386-4, KATTUKKARA MURI,
            THIRUVALLA P.O., PATHANAMTITTA DISTRICT,
            REPRESENTED BY MANAING PARTNER BOBY T.KURIAKOSE.
            PIN - 689 101.

    2       BOBY T. KURIAKOSE
            AGED 52 YEARS
            LATE T.O. KURIAKOSE,
            THOTTATHILPUTHENPURAYIL HOUSE,
            THURUTHICADU P.O., THIRUVALLA,
            PIN - 689 597.


            BY ADV SRI.K.N.RADHAKRISHNAN(THIRUVALLA)

RESPONDENTS:

    1       STATE OF KERALA
            REPRESENTED BY SECRETARY,
            IRRIGATION DEPARTMENT,
            THIRUVANANTHAPURAM, PIN - 695 001

    2       KERALA WATER AUTHORITY
            REPRESENTED BY MANAGING DIRECTOR,
            JALABHAVAN, KERALA WATER AUTHORITY,
            VELLAYAMBALAM, THIRUVANANTHAPURAM,
            PIN - 695 033.

    3       SUPERINTENDING ENGINEER
            PUBLIC HEALTH CIRCLE,
                                            2025:KER:47409
W.P.(C) No.17391/2025
                           :2:


          KERALA WATER AUTHORITY,
          THIRUVANANTHAPURAM, PIN - 695 033.

    4     THE EXECUTIVE ENGINEER
          WATER SUPPLY DIVISION,
          NEYYATTUMKARA P.O.,
          THIRUVANANTHAPURAM DISTRICT,
          PIN - 695 121.


          BY ADVS.
          SRI.JUSTINE JACOB
          SRI.P.M.JOHNY
          SRI.DHEERAJ A.S., GOVERNMENT PLEADER


     THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY
HEARD ON 12.06.2025, THE COURT ON 01.07.2025 DELIVERED
THE FOLLOWING:
                                                                2025:KER:47409
W.P.(C) No.17391/2025
                                      :3:




                           N. NAGARESH, J.

         `````````````````````````````````````````````````````````````
                     W.P.(C) No.17391 of 2025

          `````````````````````````````````````````````````````````````
                 Dated this the 1st day of July, 2025


                            JUDGMENT

~~~~~~~~~

The 1st petitioner, an A Class Contractor,

who has undertaken work of the 2nd respondent-Kerala Water

Authority, is aggrieved by the forfeiture of Bank Guarantee

and other Guarantees furnished for a contract work. The 2 nd

petitioner is the Managing Director of the 1 st petitioner-

Company.

2. The 1st petitioner quoted ₹2,76,52,109/- for

the work of Jal Jeevan Mission (JJM) 2023-2024-Maranalloor

Panchayat Phase III - Restoration of tar cut portion in PWD

roads - General Civil Work. The work was allotted to the 1st 2025:KER:47409

petitioner. On 04.09.2023, Ext.P1 Letter of Acceptance was

issued. The work was to be completed in nine months from

the date of handing over the site. The petitioners were

required to deposit ₹13,82,605/- as Performance Guarantee

and the petitioners provided security deposit of ₹4,63,400/-

by way of Treasury Savings Bank Deposit. A Bank

Guarantee of ₹4,14,800/- was also given. Ext.P5 agreement

was executed by the petitioners on 20.09.2023. Though the

petitioners requested the 3rd respondent to handover site for

performance of contract, the site was not handed over. On

19.06.2024, the petitioners sent Ext.P8 registered notice

stating that the inordinate delay in handing over the site will

cause heavy loss to the petitioners. The petitioners

requested to pre-close the contract and release the security

amount without any risk and cost.

3. To Ext.P8, the petitioners were served with

Ext.P9 communication dated 11.11.2024 directing them to

complete the work urgently. By Ext.P10 reply, the petitioners 2025:KER:47409

pointed out that the pipeline work was not yet completed by

the Contractor who undertook that work. The petitioners

again requested pre-closure of contract on account of delay

in handing over the site. Ext.P10 was followed by Ext.P11,

yet another request dated 03.02.2025.

4. The petitioners were thereupon served with

Ext.P12 communication stating that the pipe installation work

is nearing completion and the petitioners have to start the

work urgently, failing which the work will be rearranged at the

risk and cost of the petitioners. The petitioners state that

Ext.P12 communication is highly illegal and arbitrary. The

petitioners were ready to perform their part of the contract

and complete the work within nine months as agreed. But,

the Kerala Water Authority failed to handover the site.

Therefore, Ext.P12 demand is illegal and unjust.

5. Respondents 2 to 4 resisted the writ petition.

The respondents stated that the petitioners executed Ext.P5

agreement on 20.09.2023. Due to delay in obtaining road 2025:KER:47409

cutting permission from PWD, the pipeline works were

postponed. The road cutting permission was granted by the

National Highway only on 20.11.2024 on condition that the

road restoration work should be completed within three

months.

6. The respondents submitted that the

petitioners were aware of the situation and the Kerala Water

Authority was making efforts to obtain required permission.

Despite the delay, the petitioners were instructed to

commence the work immediately after the completion of the

pipeline works. As per Ext.P12, the petitioners were informed

that the failure to start work would lead to the work being

rearranged at their risk and cost. The petitioners' continued

non-performance has hindered progress of the Jal Jeevan

Mission work intended to provide functional household tap

connections to every rural household. The writ petition is

therefore liable to be dismissed.

2025:KER:47409

7. I have heard the learned counsel for the

petitioners, the learned Government Pleader appearing for

the 1st respondent and the learned Standing Counsel

appearing for respondents 2 to 4.

8. The pleadings would indicate that the

petitioners had executed Ext.P5 agreement for the work of

Jal Jeevan Mission (JJM) 2023-2024-Maranalloor Panchayat

Phase III - Restoration of tar cut portion in PWD roads -

General Civil Work, on 20.09.2023. As per the terms of

Ext.P5, the Kerala Water Authority was bound to handover

the site to the petitioners immediately and the petitioners

were bound to complete the work within nine months. It is

evident from the pleadings that the pipeline work on the road

entrusted with another Contractor was not completed in time

and therefore the petitioners requested pre-closure of

contract on account of delay in handing over the site, on

14.11.2024.

2025:KER:47409

9. It is to be noted that the agreement was

signed on 20.09.2023 and the work had to be completed

within nine months. Even after more than one year, the site

was not handed over to the petitioners. Evidently, the

petitioners sent Ext.P10 letter dated 14.11.2024 seeking pre-

closure of contract after more than one year. Ext.P10 was

sent on 14.11.2024. On 24.04.2025, after more than two

months from the date of Ext.P10, the petitioners were

directed to start the work urgently as per Ext.P12. Even

when Ext.P12 was issued, the pipe installation work was not

completed.

10. Respondents 2 to 4 would submit that

though pipeline work was not completed, the petitioners were

required to start the work. The petitioners could have started

the work only on completion of the pipeline work and only on

handing over hindrance free site to the petitioners, which was

not done. The petitioners had sought for pre-closure of

contracts after more than one year of executing agreement.

2025:KER:47409

The respondents cannot expect the petitioners to carry out

the work at the agreed rates long after the execution of

agreement. The writ petition is therefore liable to be allowed.

11. It is declared that the petitioners are not

liable for any penalty, risk or cost for non-performance of

contract due to the non-handing over of site. Ext.P12 is

quashed to the extent it stipulates that the Contractor is liable

for risk and cost. The 3rd respondent is directed to consider

Ext.P13 and release the Bank Guarantee and other

Guarantees to the petitioners within a period of two months.

The writ petition is disposed of as above.

Sd/-

N. NAGARESH, JUDGE aks/27.06.2025 2025:KER:47409

APPENDIX OF WP(C) 17391/2025

PETITIONER'S EXHIBITS

Exhibit P1 THE TRUE COPY OF ACCEPTANCE ISSUED BY THE THIRD RESPONDENT DATED 04.09.2023.

Exhibit P2 THE TRUE COPY OF TREASURY SAVING DEPOSIT RECEIPT NO.0960203 DATED 16.092023.

Exhibit P3 TRUE COPY OF TREASURY SAVING DEPOSIT RECEIPT NO.0960218 DATED 19.09.2023. Exhibit P4 THE TRUE COPY OF BANK GUARANTEE DATED 15.09.2023 BY THE FEDERAL BANK LTD., THIRUVALLA BRANCH.

Exhibit P5 THE COPY OF AGREEMENT EXECUTED BY THE PETITIONERS IN FAVOUR OF WATER AUTHORITY DATED 20.09.2023.

Exhibit P6 THE TRUE COPY OF LETTER SEND TO THE THIRD RESPONDENT DATED 22.01.2024.

Exhibit P7 THE TRUE COPY OF LETTER SEND TO THE THIRD RESPONDENT DATED 08.04.2024.

Exhibit P8 THE TRUE COPY OF LETTER DATED 19.06.2024 ADDRESSED TO THE THIRD RESPONDENT.

Exhibit P9 THE TRUE COPY OF COMMUNICATION DATED 11.11.2024 FROM THE OFFICE OF FOURTH RESPONDENT.

Exhibit P10 THE TRUE COPY OF LETTER DATED 14.11.2024 ADDRESSED TO THE FOURTH RESPONDENT.

Exhibit P11 THE COPY OF LETTER DATED 03.02.2025 ADDRESSED TO THE FOURTH RESPONDENT.

Exhibit P12 THE COPY OF COMMUNICATION DATED 24.04.2025 ISSUED BY THE OFFICE OF THIRD RESPONDENT.

Exhibit P13 THE COPY OF LETTER DATED 29.04.2025 ADDRESSED TO THIRD RESPONDENT.

RESPONDENT'S EXHIBITS

Exhibit R2(A) true copy of minutes of meeting held under the MLA of Kattakkada dated 20.11.2024

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter