Citation : 2025 Latest Caselaw 4218 Ker
Judgement Date : 19 February, 2025
2025:KER:14303
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE P.G. AJITHKUMAR
WEDNESDAY, THE 19TH DAY OF FEBRUARY 2025 / 30TH MAGHA,
1946
CRL.APPEAL NO. 2906 OF 2008
AGAINST THE JUDGMENT DATED 02.12.2008 IN CC NO.23 OF 2001
OF THE ENQUIRY COMMISSIONER & SPECIAL JUDGE,
THIRUVANANTHAPURAM
APPELLANT/ACCUSED:
K.T.KURIAKOSE
S/O THOMAS, KARUTHEDATHU,
THIRUVANIYOOR(VIA),PUTHENCRUZ,ERNAKULAM,
(GOVT.CONTRACTOR).
BY ADVS.
SRI.VIVEK VARGHESE P.J.
SRI.P.J.VINOD JOSEPH
SRI.GEO PAUL
SRI.C.R.PRAMOD
SHRI.JACOB GEORGE PALLATH
SHRI.NAVEEN T.U.
SMT. JANE MARIA TOMY
2025:KER:14303
2
Crl.Appeal No.2906 of 2008
RESPONDENT/COMPLAINANT:
STATE OF KERALA
REP.BY THE SUPERINTENDENT OF POLICE, VACB, SIT,
KIP, KOLLAM.
SMT REKHA S, SR PUBLIC PROSECUTOR
SRI A RAJESH, SPL PUBLIC PROSECUTOR (VIG)
THIS CRIMINAL APPEAL HAVING COME UP FOR FINAL
HEARING ON 24.01.2025, THE COURT ON 19.02.2025 DELIVERED
THE FOLLOWING:
2025:KER:14303
3
Crl.Appeal No.2906 of 2008
P.G. AJITHKUMAR, J.
-----------------------------------------------------------
Crl.Appeal No.2906 of 2008
-----------------------------------------------------------
Dated this the 19th day of February, 2025
JUDGMENT
The 1st accused in C.C.No.23 of 2001 on the files of the
Court of Enquiry Commissioner and Special Judge,
Thiruvananthapuram is the appellant. He along with the 2 nd
accused was tried for offences punishable under Sections 13(1)
(d) read with Section 13(2) of the Prevention of Corruption Act,
1988 (PC Act) and Section 120B of the Indian Penal Code, 1860
(IPC). The Special Court as per the judgment dated 02.12.2008
convicted and sentenced the appellant for both the offences,
however, acquitted the 2nd accused. Challenging his conviction
and sentence, the appellant filed this appeal under Section
374(2) of the Code of Criminal Procedure, 1973 (Code).
2. Heard the learned counsel for the appellant and the
learned Special Public Prosecutor (Vigilance).
3. The case of the prosecution is the following:
The appellant was the contractor of the work "KIP RBC
Formation of Vallikunnam Distributory Package-I from Ch.40-M to 2025:KER:14303
2000-M including CD works", an agreement in regard to the work
was executed on 12.11.1987. Several additional works were to
be undertaken. Regarding each such work, separate
supplemental agreement was executed. One of such additional
work was construction of toe wall and drain regarding which
supplemental agreement No.5 dated 11.12.1990 was executed
between the appellant and the then Superintending Engineer. In
terms of that, additional work was undertaken.
4. The allegation is that the appellant, the 2nd accused
and the then Superintending Engineer hatched a conspiracy
and the said additional work, which was estimated at
Rs.13,57,688/- was allotted to the appellant after negotiation,
for an amount of Rs.21,07,050/-. Although the Chief Engineer
authorised the Superintending Engineer to get the work done
after negotiation through the appellant, fixing the price of
work at such an exorbitant amount was unauthorised. By
allotting the work at such a rate, the Government sustained a
loss of Rs.9,91,533.81. The then Superintending Engineer and
the 2nd accused misused their position as public servants in
allotting the work at such a higher rate and in consequence 2025:KER:14303
thereof, the appellant obtained pecuniary advantage of the
aforesaid amount. Thereby, they have committed the
aforementioned offences.
5. Based on the aforesaid allegations, a charge was
framed and read over to the appellant and the 2 nd accused.
They pleaded not guilty. Therefore, the prosecution has
examined PWs.1 to 9 and proved Exts.P1 to P28. After closing
the prosecution evidence, the appellant and the 2 nd accused
were examined under Section 313(1)(b) of the Code. They
denied the incriminating circumstances appeared against
them in evidence. In the statement submitted by the
appellant, he justified the supplemental agreement as lawful.
He maintained that he quoted a reasonable rate for the work
in the negotiation and the Superintending Engineer after
deliberations fixed the price even at a lower rate. He
contended that there was no element of mischief in the said
contract. He added that more than Rs.12 lakhs remained due
to him for the work in question and even if any amount is due
from him, the Government can well realise the same from
that sum. He, however, did not adduce any evidence.
2025:KER:14303
6. The Special Judge considered the entire evidence in
detail. After quantifying the amount paid in excess to the
appellant as Rs.9,89,913.81/-, it was concluded that the
appellant and the then Superintending Engineer hatched a
conspiracy resulting in execution of supplemental agreement
No.5, which is Ext.P3(e). It was also held that the said
conspiracy fructified in undertaking the work and resultant
loss of such an amount to the State amounting an offence
under Section 13(1)(d) of the PC Act. The 2 nd accused was,
however, found not guilty.
7. The learned counsel for the appellant would submit
that the view taken by the Special Court regarding financial
powers of the Superintending Engineer and application of
Ext.P26 Government Order to the work in question, which was
undertaken utilising the World Bank aid is incorrect. The Local
Competitive Bidding (LCB) guidelines appended to the
contract were alone applicable. As per Clauses 31 and 32 in it,
the Superintending Engineer had every authority to fix the
rate on negotiation. Therefore, the finding that the
Superintending Engineer exceeded his authority and therefore 2025:KER:14303
the contract underlying Ext.P3(e) is illegal, does not stand
scrutiny of law.
8. It is submitted that the original contract was
awarded to the appellant at a rate 53.20% in excess of the
estimated amount and as such no irregularity can be
attributed to Ext.P3(e) agreement. When the Chief Engineer,
PW1 empowered the Superintending Engineer as per
Ext.P4(d) to negotiate and award the work to the appellant,
the supplemental agreement No.5 did not suffer from any
vice. It is further submitted that the Special Court gave over-
emphasise to the evidence of PW5, a II Grade Draftsman and
PW6, a Financial Assistant in defining the powers of the
Superintending Engineer, which is palpably wrong. Non-
examination of Sri.Suredran Pillai, with whom the appellant
executed the original agreement, Ext.P3(a), is fatal to the
prosecution. PW1, the Chief Engineer and PW2, the Executive
Engineer did not state that the Superintending Engineer did
not have the authority to negotiate and fix the rate, which he
deemed appropriate. In the light of the said evidence, the
court below ought not have held that Ext.P3(e) agreement 2025:KER:14303
was unauthorised or illegal. It is further submitted that even if
the Superintending Engineer exceeded his authority, the
consequence is only an action for irregularity in the process
and not a criminal prosecution. Thus, it is maintained that the
conviction is incorrect and not based on any legal evidence.
9. The learned Public Prosecutor, on the other hand,
submitted that when Ext.P26 G.O. restricted powers of the
Superintending Engineer, the same applies to every decision
he takes and all agreements he enters into. When Ext. P3(e)
contract was awarded without obtaining sanction from the
Government, the dishonest intention to award the work at an
exorbitant rate and thereby to enable the appellant to obtain
pecuniary advantage is quite clear. The learned counsel for
the appellant urged that Ext.P26 was not duly proved and
therefore the same could not be acted upon. In answer, the
learned Special Public Prosecutor submitted that it being a
Government Order issued under due authority, no formal
proof is necessary to act it upon. Of course, it is a photocopy,
but when its existence is not disputed, it could be received in
evidence. In the above regard, the learned Special Public 2025:KER:14303
Prosecutor placed reliance on Union of India v. Nihar Kanta
Sen and others [(1987) 3 SCC 465] and Venture Global
Engineering LIC v. Tech Mahindra Ltd. and another
[(2018) 1 SCC 656].
10. Several facts forming the basis of the accusation
are not in dispute. The Superintending Engineer with whom
the appellant entered into Ext.P3(e) agreement, was a public
servant, such an agreement was executed in connection with
additional work of construction of toe wall and drain, the
contract price was Rs.21,07,050/-, the work was executed by
the appellant, he received an amount of Rs.27,92,180/-,
including for the additional quantity of work, and the contract
price was fixed as Rs.21,07,050/- on the basis of negotiation
are not disputed. Those facts are borne by records, which are
duly proved by the prosecution also.
11. PW1 was the Chief Engineer. PW2 was the
Superintending Engineer. PW5 was the II Grade Draftsman,
who was dealing with the file relating to the contract. She also
was a witness to the original agreement, Ext.P3(a) as well as
the 12 supplemental agreements including Ext.P3(e). PW6 2025:KER:14303
was the Financial Assistant in the office of the Superintending
Engineer, and he deposed about Ext.P4 file which contains
correspondences culminating in execution of Ext.P3(e).
Evidence of these witnesses proved the aforementioned facts.
12. PW7 was the Assistant Engineer of Karunagappally
KIP RB Circle No.38/25. It was he who submitted the proposal
for the additional work in question. He estimated the cost of
work at Rs.16,86,428/- and forwarded to the 2 nd accused, who
was then the Executive Engineer. He in turn forwarded it to
the Superintending Engineer, who modified the estimate and
refixed the value at Rs.16,76,738/-. The estimate was
computed based on the 1990 PWD schedule of rates. The
estimate was submitted to the Chief Engineer, PW1. He
reduced the estimate to Rs.13,57,688/- and the basis for the
same was PWD schedule of rates, 1996. Accordingly, the work
was sanctioned and the then Superintending Engineer was
empowered to have negotiation and get executed the work
through the same contractor-appellant.
13. The Superintending Engineer was thus having
sufficient authority to award the contract at the rate to be fixed 2025:KER:14303
after negotiation. The case of the prosecution is that the
Government delineated the powers of Engineers at every level for
granting escalation from the estimated rates. The power invested
on the Superintending Engineer was upto Rs.2,500/- or 25%
above the estimated amount. When that was the financial power
of the Superintending Engineer, any escalation above that limit
should have been with the permission of the Government only.
Work awarded as per Ext.P3(e) supplemental agreement to the
appellant was at a rate more than 50% of the estimate. But no
sanction from the Government was obtained.
14. The definite contention of the appellant is that
Ext.P26 was not duly proved and therefore the same could not
be used in evidence. It was also contended that it was not
Ext.P26, but the LCB specifications was applicable to the world
bank works. Going by clause 31 of the LCB specifications,
negotiation could be done and the revised rates could be fixed
by the Superintending Engineer, having he been authorised by
PW1. Clauses 31 and 32 in LCB specifications read:-
"31. Schedule of Quantities:- Variation in the quantities of work in the Bill of quantities shall not vitiate the contract. The 2025:KER:14303
rates quoted for the individual items shall apply for the quantities of work increased or decreased by not more than thirty percent for each of the items. Should quantities of work actually involved under any item exceed quantities provided in the tender by more than thirty percent the rate of such excess over thirty percent of quantity provided in the tender may be revised in accordance with the procedure indicated under clause "Extra items". However, the said revised item rate shall not exceed the item rate quoted, subject to adjustment in accordance with price adjustment clauses. Should the quantity of work actually involved under any item be reduced by more than thirty percent of quantity provided in the tender, the bid unit price for the affected item may be revised in accordance with the procedure indicated under "Extra Items". However the total cost of such items should not exceed the cost of seventy percent of the item quoted, subject to adjustment in accordance with price adjustment clauses. The payment for the item will continue to be made at the original rate until the revised rate is decided.
32. Extra Items: Extra items of work shall not vitiate the contract. The Contractor shall be bound to execute extra items of work as directed by the ........................ The rates for extra items are to be mutually agreed."
15. Going by the aforesaid clauses, the cost of an item
in the extra work should not exceed 70% of the item quoted,
subject to adjustments in accordance with price adjustment
clauses. The question was whether the Superintending 2025:KER:14303
Engineer could have given escalation in terms of the said
clause or he was obliged to confine to the limits in Ext.P26.
The question immediately arises is whether Ext.P26 could be
relied on for want of its formal proof.
16. The Apex Court in Nihar Kanta Sen (supra)
considered whether formal proof was required to rely on a
notification issued by the Government. That was a notification
published in the gazette. The Apex Court held that having
published in the gazette, the court should have taken judicial
notice of the notification. In Venture Global Engineering
(supra) the question was regarding the requirement of formal
proof of certain facts which acquired the character of
notorious facts. It was held that no court should insist on
formal proof, by evidence, of notorious facts of history, past or
present. The date of poll, the passing away of a man of
eminence, events that have rocked the nation, etc. need no
proof and are judicially noticeable. Judicial notice, in such
matters, takes the place of proof and is of equal force.
17. Ext.P26 is a Government Order issued, inter alia,
fixing the financial powers of the Engineers in the PWD.
2025:KER:14303
Although the Kallada Irrigation Project was financed by the
World Bank and the LCB specifications were issued regarding
implementation of the project, the Engineers who
implemented the work continued to be in the service of the
PWD. Their financial powers can certainly be restricted as per
the orders of the Government. Although Ext.P26 is a
photostat copy, PW5 and PW6, who are attached to PWD and
also other witnesses deposed about such financial powers. It
cannot be said that they have no direct knowledge about the
order fixing the financial powers. Similar is in the case of the
appellant who is a licensed PWD contractor.
18. PWs.5 and 6 spoke about contents of Ext.P26.
Production of Ext.P26, dehors it is only a photostat copy,
establishing its existence. Therefore, the contents of the said
document can certainly be acted upon and used to corroborate
what PW5 and PW6 deposed about the financial powers of the
Superintending Engineer. Engineers and the contractors of the
PWD cannot feign ignorance of the said Government Order, as
though it may not have the character of a notorious fact. In the
above circumstances the court can place reliance on Ext.P26.
2025:KER:14303
19. When Ext.P26 contains the general powers of the
Superintending Engineer, Clauses 31 and 32 in the LCB
specifications deal with specific instances concerning extra
items of work. The limitation imposed is that the cost should
not exceed 70% of the item quoted. It was, however, insisted
that unless the rate is revised, the payment of the item should
be at the original rate. The decision taken by the
Superintending Engineer after negotiation with the appellant
to fix the rate of additional work as Rs.21,07,050/- has to be
considered in the light of the aforesaid aspects.
20. As deposed by PW5 the contract excess for the
original contract covered by Ext.P3(a), excluding the cost of
articles supplied by the Government, was 53.20%. Whereas,
the overall excess quoted by the appellant for the original
work was 34.73%. As stated, PW1 revised the estimate for
the additional work and cost was reduced to Rs.13,57,688/-.
The total excess cost while awarding the work to the appellant
for Rs.21,07,050/- is therefore Rs.7,49,362/-. That is more
than 50% of the estimated cost. It may be noted that PW1
fixed the estimated amount taking into account the 1986 PWD 2025:KER:14303
schedule of rates. Whereas, the Superintending Engineer
adopted the 1990 PWD schedule of rates and estimated the
price of work at Rs.16,76,368/-.
21. The additional work was awarded to the appellant
as per Ext.P3(e) on 11.12.1990. So, following the 1990 PWD
schedule of rates was apposite. Of course, going by the LCB
specifications, the original rate should have been followed.
Whether there was a criminal conspiracy to allow excess cost
for the work in question has to be determined bearing in mind
the above aspects.
22. In the above context, the following observations of
the Special Court, while arriving at the conclusion that there
was criminal conspiracy, are relevant:
"A1 was fully aware of the amounts fixed in Ext.P3(a) the original agreement and also amount suggested by the then E.E., A2 herein, the S.E. and that approved by the C.E. So the execution of this supplemental agreement No.5 is sufficient evidence to prove the conspiracy entered between A1 and late Varghese Mathew. So the prosecution succeeded in proving that late Sri.Varghese Mathew and A1 conspired together and executed Ext.P3(e) supplemental agreement by which A1 by corrupt or illegal means obtained pecuniary advantage to the tune of Rs.9,89,913.81."
2025:KER:14303
23. The Special Court placed reliance on the law laid
down by the Apex Court in Bhagwan Swarup Lal Bishan
Lal v. State of Maharashtra [AIR 1965 SC 682] and
V.C.Shukla v. State (Delhi Administration) [(1982) 2
SCC 665] to conclude so. The view taken in Bhagwan
Swarup (supra) is that in the light of the provisions of
Section 10 of the Evidence Act, the things done or written by
any party to the alleged conspiracy in reference to their
common intention is relevant and can be used to prove the
existence of the conspiracy. As explained in V.C.Shukla
(supra), a meeting of mind resulting in ultimate decision
taken by the conspirators regarding the commission of the
offence has to be proved. The prosecution should show that
the circumstances give rise to a conclusive or irresistible
inference of the agreement between the persons to commit an
offence.
24. As stated, the additional work in question was
awarded to the appellant for an amount of Rs.21,07,050/- in
violation of Ext.P26 and to a certain extent the LCB
specifications. But when PW1 empowered the Superintending 2025:KER:14303
Engineer as per Ext.P4(e) to get the work executed through
the appellant after negotiation, it was not a case of lack of
empowerment. Even though there was no insistence in
Ext.P4(e), the Superintending Engineer should have obtained
sanction from the Government for awarding work at a cost
above 25% of the estimate, which was above his power. All
the same, when the original work contract covered by
Ext.P3(a) allowed contract excess, after deducting cost of
departmental material, of 53.20%, no dishonest intention in
fixing the price for the additional work covered by Ext.P3(e) at
Rs.21,07,050/- can readily be inferred. So, it cannot be said
that from the circumstances which culminated in execution of
Ext.P3(e) agreement and that appeared in evidence in this
case, a criminal conspiracy is proved.
25. It can be seen from Ext.P4 file that the appellant
was invited for a negotiation [Ext.P4(f)]. He offered his rate
and that after due deliberation in the negotiation with
reference to each item of work, the final amount was arrived
at. It was not a secret affair. Various correspondences
concerning execution of Ext.P3(e) contract are reflected from 2025:KER:14303
Ext.P4 file. All persons, who were dealing with the said file,
including PW5 and PW6, were in the know of those
correspondences and the incidents transpired. When that
much transparency was there, it is incorrect to say that
execution of Ext.P3(e) was the result of a criminal conspiracy.
26. A similar situation was considered by the Apex
Court in C.Chenga Reddy v. State of A.P. [(1996) 10 SCC
193]. In that case the contract was awarded in violation of
the regulations. It was considered whether in the absence of
circumstances sufficient to prove the guilt of criminal
misconduct could there be a conviction. The following
observations are relevant:
"22. On a careful consideration of the material on the record, we are of the opinion that though the prosecution has established that the appellants have committed not only codal violations but also irregularities by ignoring various circulars and departmental orders issued from time to time in the matter of allotment of work of jungle clearance on nomination basis and have committed departmental lapse yet. non of the circumstances relied upon by the prosecution are of any conclusive nature and all the circumstances put together do not lead to the irresistible conclusion that the said circumstances are compatible only with the hypothesis of the guilt of the appellant and wholly incompatible with 2025:KER:14303
their innocence. In Abdulla Mohammed Pagarkar v. State (Union Territory of Goa, Daman and Diu), [1980] 3 SCC 110, under somewhat similar circumstances this Court opined that mere disregard of relevant provisions of the Financial Code as well as ordinary norms of procedural behaviour of government officials and con-tractors, without conclusively establishing, beyond a reasonable doubt, the guilt of the concerned officials and contractors, may give rise to a strong suspicion but that cannot be held to establish the guilt of the accused. The established circumstances in this case also do not establish criminality of the appellants beyond the realm of suspicion and, in our opinion, the approach of the trial court and the High Court to the requirements of proof in relation to a criminal charge was not proper. xx xx" (underline added)
27. From the discussions made above, it can certainly
be said that the Superintending Engineer (who was arraigned
as an accused, but expired before filing of the final report),
violated Ext.P26 and to a limited extent of Clause 31 in the
LCB specifications. Therefore, there is violation of the
Government directions on his part. But the circumstances
brought on record are insufficient to conclude that Ext.P3(e)
was executed in consequence of a criminal conspiracy and an
offence of criminal misconduct was committed concerning
execution of Ext.P3(e) and undertaking of that work.
2025:KER:14303
Therefore, the conviction of the appellant for the offence
under Section 13(1)(d) read with Section 13(2) of the PC Act
and Section 120B of the IPC is liable to be set aside.
28. Although the appellant is entitled for an acquittal,
the loss of the Government in respect of the additional work
covered by Ext.P3(e) is required to be made good, since there
was no Government sanction for the same. It is, therefore,
made clear that the acquittal of the appellant does not fetter
the Government from recovering the loss as it quantified in
respect of the said work, in accordance with law.
Accordingly, the appeal is allowed. The conviction of the
appellant in C.C.No.23 of 2001 on the file of the Court of
Enquiry Commissioner and Special Judge, Thiruvananthapuram
and consequent sentence are set aside. The appellant is
acquitted and set at liberty.
Sd/-
P.G. AJITHKUMAR, JUDGE dkr
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!