Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

C.K.Abdul Rahman vs The Kerala State Electricity Board
2025 Latest Caselaw 8136 Ker

Citation : 2025 Latest Caselaw 8136 Ker
Judgement Date : 26 August, 2025

Kerala High Court

C.K.Abdul Rahman vs The Kerala State Electricity Board on 26 August, 2025

                                                      2025:KER:65227
W.P.(C).Nos.17906 & 40877 of 2016
                                    1


               IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                PRESENT

                  THE HONOURABLE MR. JUSTICE S.MANU

     TUESDAY, THE 26TH DAY OF AUGUST 2025 / 4TH BHADRA, 1947

                       WP(C) NO. 17906 OF 2016


PETITIONER:

             THE ASSISTANT ENGINEER
             KERALA STATE ELECTRICITY BOARD LTD.,
             ELECTRICAL SECTION NO.1, KODUNGALLUR-680664.


             BY ADVS.
             SHRI.JAICE JACOB,SC,KERALA STATE ELECTRICITY BOARD
             SRI.AJIT JOY
             SRI.ANEESH JAMES



RESPONDENTS:

     1       C.R.ABDUL RAHMAN
             S/O. KOCHAHAMMED, ADMINISTRATIVE OFFICER & DIRECTOR,
             MEDICARE HOSPITAL, TKS PURAM, KODUNGALLUR-680664.

     2       KERALA STATE ELECTRICITY APPELLATE AUTHORITY
             CC 51/52, NEAR 110 KV SUBSTATION, VYTTILA,
             KOCHI-682019.


             BY ADV SHRI.R.S.KALKURA


         THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
26.08.2025, ALONG WITH WP(C).40877/2016, THE COURT ON THE SAME
DAY DELIVERED THE FOLLOWING:
                                                      2025:KER:65227
W.P.(C).Nos.17906 & 40877 of 2016
                                    2


             IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                PRESENT

                 THE HONOURABLE MR. JUSTICE S.MANU

     TUESDAY, THE 26TH DAY OF AUGUST 2025 / 4TH BHADRA, 1947

                       WP(C) NO. 40877 OF 2016


PETITIONER:
           C.K.ABDUL RAHMAN
           AGED 78 YEARS
           S/O.KOCHAHAMAD, AGED 78 YEARS,
           ADMINISTRATIVE OFFICER & DIRECTOR, MEDICARE HOSPITAL,
           T.K.S.PURAM, KODUNGALLUR.
              BY ADVS.
              SRI.R.S.KALKURA
              SRI.HARISH GOPINATH
              SRI.M.S.KALESH


RESPONDENTS:
     1     THE KERALA STATE ELECTRICITY BOARD
           REPRESENTED BY ITS SECRETARY, VYDYUTHI BHAVAN,
           PATTOM, THIRUVANANTHAPURAM.
     2     THE ASSTT. ENGINEER
           ELECTRICAL SECTION NO.1 KERALA STATE ELECTRICITY
           BOARD, KODUNGALLUR - 680 664.
     3     THE SENIOR SUPERINTENDENT ELECTRICAL SECTION NO.1
           KERALA STATE ELECTRICITY BOARD,
           KODUNGALLUR - 680 664.
     4     KERALA STATE ELECTRICITY APPELLATE AUTHORITY
           CC 51/52, NEAR 110 KV SUBSTATION VYTILLA,
           KOCHI - 682 019.
             BY ADVS.
                SRI.AJIT JOY
                SRI.ANEESH JAMES


      THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
26.08.2025, ALONG WITH WP(C).17906/2016, THE COURT ON THE SAME
DAY DELIVERED THE FOLLOWING:
                                                       2025:KER:65227
W.P.(C).Nos.17906 & 40877 of 2016
                                    3




                            S.MANU, J.
           ------------------------------------------------
               W.P.(C).Nos.17906 & 40877 of 2016
           ------------------------------------------------
             Dated this the 26th day of August, 2025

                             JUDGMENT

First respondent is running a hospital. Electricity supply

under LT-VIB Tariff in three phases with sanctioned load 74kW

was availed by the 1st respondent. In an inspection conducted

by Vigilance Special Squad led by Anti Power Theft Squad,

Palakkad unit in the premises of the 1 st respondent on

27.3.2003, additional load of 46kW over and above registered

load of 74kW was detected. Penalty was imposed and the same

was remitted by the 1st respondent. Though it was directed to

regularise the unauthorised additional load, same was not done

by the 1st respondent for a long time. The supply was not

disconnected, however, charges for additional load continued to

be demanded and paid by the 1st respondent.

2. According to the KSEB penal portion of fixed charges

from June 2008 to March 2011 and energy charges from June 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

2007 to April 2011 were not included in the monthly demands

by mistake. It was noticed in the audit of accounts. Thereafter,

a demand was issued for the escaped charges on 30.10.2011.

The bill was for an amount of Rs.18,58,537/-. First respondent

challenged the demand in W.P.(C)No.30946/2011. The writ

petition was disposed of by judgment dated 8.11.2013.

Impugned demand was set aside and Board was given liberty to

impose penalty in compliance with Section 126 of the Electricity

Act.

3. First respondent submitted a representation on

17.7.2014 to the Assistant Engineer requesting to drop the

demand. Thereafter, Ext.P6 order was issued by the Assistant

Engineer directing to remit the amount as per the final bill. A

detailed split up was also furnished along with the order. First

respondent challenged the order by approaching the appellate

authority under Section 127 of the Electricity Act. The appellate

authority after considering the matter, by order dated

23.12.2015 allowed the appeal. Final assessment order was set 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

aside and Board was directed to refund the amount already

deposited by the 1st respondent with interest. W.P.

(C)No.17906/2016 was filed by the Board challenging the order

of the appellate authority. First respondent filed W.P.

(C)No.40877/2016 seeking direction to refund an amount of

Rs.9,29,300/- deposited with interest at the rate of 21% per

annum from 1.9.2014. Since the writ petitions are inter-related

they were heard together and are being disposed by this

common judgment. Parties are being referred as they are

arrayed in W.P.(C)No.17906/2016. Reference to the documents

is also as marked in the said writ petition.

4. Learned Standing Counsel for the KSEB Sri.Ajit Joy

contended that the order of the appellate authority is illegal. He

submitted that the consumer had indulged in unauthorised use

of energy. 46 kW was the unauthorised load. Though the

penalty was paid, 1st respondent failed to regularise the

additional load. Steps were taken by the 1st respondent much

later for regularisation of unauthorised load. First respondent is 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

liable to pay penalty for the unauthorised additional load until

the additional load is removed or regularised as per the Rules.

Due to inadvertence at the time of computerization fixed

charges from 6/2008 to 3/2011 and energy charges from

6/2007 to 4/2011 were omitted when monthly demands were

raised. Bill for an amount of Rs.18,58,537/- was issued on

31.10.2011 when the omission was noticed. The demand so

raised was in accordance with the relevant Regulations and

Rules. Therefore, the demand was in fact an assessment made

for escaped charges for a period during which the energy

charges and fixed charges were omitted to be demanded. The

learned Standing Counsel referred to Regulation 51(2) of the

Kerala State Electricity Board Terms and Conditions of Supply,

2005 which provides that the penalty for unauthorised

additional load shall be levied till the unauthroised additional

load is removed or regularised. The learned Standing Counsel

submitted that the impugned order of the appellate authority is

illegal and perverse as the appellate authority arrived at an 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

erroneous conclusion that the procedure under Section 126 of

the Electricity Act was not followed. He referred to Section 126

of the Act and contended that assessing officer can come to a

conclusion regarding unauthorised use of electricity after

inspection of records also and it is not necessary that inspection

of place or premises or of the equipment, gadgets, machines or

devices shall be made. He hence submitted that the final bill in

the case at hand was issued and the final assessment was made

on the basis of inspection of records and hence there was due

compliance of the provisions of the Section 126 of the Act. He

also submitted that the inspection was held by Vigilance Squad

in the year 2003 in which unauthorised load was detected and

penalty was paid by the 1 st respondent. Hence, the 1st

respondent cannot be permitted to contend that there was no

unauthorised use of electricity. So also it cannot be disputed

that unauthorised load was removed or regularised during the

period with respect to which the assessment was made for

escaped charges. Hence, he contended that the appellate 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

authority ought to have upheld the final assessment and by

interfering with the same, the said authority has committed a

grave error in exercising the powers under Section 127 of the

Act.

5. The learned Standing Counsel further submitted that

the demands are not hit by limitation under Section 56(2) of the

Act. He relied on judgment of the Hon'ble Supreme Court in

Assistant Engineer(D1), Ajmer Vidyut Vitran Nigam

Limited and Another v. Rahamatullah Khan Alias

Rahamjulla [(2020)4 SCC 650]. About the contention of the

respondent that for issuing the disputed demand notices fresh

compliance of the requirements of Section 126 was essential, he

pointed out judgment of a Division Bench of this Court in

W.A.No.975/2014. He contended that for issuing further

demands on the basis of an inspection and assessment under

Section 126 of the Electricity Act, no fresh compliance with the

procedure under Section 126 is essential in view of the

judgment of the Division Bench.

2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

6. Learned counsel for the 1st respondent submitted that

Ext.P2 bill was issued on 31.10.2011 without giving any

opportunity to the respondent to explain. No opportunity was

provided to contest the calculation of the alleged dues. The

Board has violated provisions of Section 126 while issuing the

disputed bill. In W.P.(C)No.30946/2011 this Court quashed the

bills and held that KSEB could impose penalty only after

complying with all the procedural formalities under Section 126

of the Act. Thereafter, fresh provisional assessment bill was

issued on 14.7.2014 reiterating the claim raised earlier. Since

this Court directed the KSEB in Ext.P4 judgment to comply with

the procedure under Section 126 of the Electricity Act, the

Board ought to have followed the same. The judgment had

become final and being an inter-party judgment the Board as

well as the consumer are bound by the said judgment. By

issuing the final assessment bill without complying with the

procedure under Section 126 of the Act, the Board had flouted

the directions in Ext.P4 judgment. The appellate authority 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

therefore rightly interfered and set aside the final assessment

and bill. He also submitted that the demand was hit by

limitation. According to the learned counsel, the maximum

previous period with respect to which the claim can be raised

under Section 126 of the Act is 12 months and hence the

demand is clearly untenable. The Board ought to have complied

with the direction of the appellate authority to refund the

amount deposited by the 1 st respondent. The learned counsel

also submitted that the judgment of Division bench of this Court

in W.A.No.975/2014 is distinguishable on facts. He therefore

prayed that the challenge by the Board may be repelled and it

may be directed to refund the amount deposited by the

respondent at the earliest.

7. The main issue to be addressed in view of the

contentions of both sides is as to whether the procedure

adopted by the Board in issuing final assessment order was

proper or not. In W.P.(C)No.30946/2011 filed by the consumer

this Court set aside Ext.P2 bill and held as follows:-

2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

".............Even though Regulation 51 (2) of the KSEB Terms and Conditions Supply, 2005 provides that penalty for unauthorized additional load shall be levied till the said unauthorized additional load is removed or regularized, the said regulation does not authorizes any person to make an assessment of such penalty without following the comprehensive procedure contemplated under Section 126, which are mandatory in nature. Merely because once the unauthorized use of electricity was detected and penalty was imposed, the authorities of the Board are not entitled to continue the penalization automatically for any further period, without following procedure prescribed under Section 126. On an equitable basis, the authorities of the Board are not supposed to permit the consumer to continue the unauthorized usage indefinitely, without insisting upon to dismantle the unauthorized additional load or without insisting upon regularization of such additional load. Even if no such action was taken from the side of the Board, and even if the consumer had failed to remove or regularize the additional load, penalty alleging continuance of such unauthorized usage can be made only by completing separate assessment, after complying 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

with all the procedural formalities requisite under Section 126. The impugned bills issued merely demanding payment of penalty without issuing any provisional order and without affording any opportunity to the consumer to raise objections and without affording any opportunity for personal hearing, as required under Section 126 (2) and (3), cannot be sustained legally.

5. Under the above mentioned circumstances, the writ petition is allowed and Exhibit P1 and P4 bills are hereby quashed. It is made clear that the respondents will be at liberty to impose penalty on the petitioner, if sustainable under law, after complying with all the procedural formalities enumerated under Section 126. However, if any such steps are initiated, the petitioner will be at liberty to challenge/object such proposal on all available grounds, including the question of limitation if any provided under the relevant provisions."

8. This Court thus held that the Board will be at liberty

to impose penalty on the consumer, if sustainable under law,

after complying with all the procedural formalities enumerated

under Section 126. Learned counsel for the petitioner 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

vehemently contended that no fresh inspection was conducted

by the Board and ignoring the specific direction to comply with

the procedure under Section 126 of the Act, the Board

proceeded in violation of the directions issued by this Court. The

learned Standing Counsel addressed the said contention by

arguing that it is not necessary to conduct a fresh inspection for

assessment under Section 126(1) of the Act. He pointed out

that inspection of records maintained is also sufficient for

effecting assessment under Section 126 of the Act. For ready

reference Section 126(1) is extracted hereunder:-

"Section 126. Assessment. (1) If on an inspection of any place or premises or after inspection of the equipments, gadgets, machines, devices found connected or used, or after inspection of records maintained by any person, the assessing officer comes to the conclusion that such person is indulging in unauthorised use of electricity, he shall provisionally assess to the best of his judgment the electricity charges payable by such person or by any other person benefited by such use."

2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

9. A careful reading of the provision shows that

assessing officer can come to the conclusion that there is

unauthorised use of electricity either, 1) on an inspection of any

place or premises, 2) or after inspection of the equipments,

gadgets, machines, devices found connected or use, 3) or after

inspection of records maintained by any person. Language of

the provision makes it clear that the assessing officer can arrive

at a conclusion if he finds that there is unauthorised use of

electricity on inspection in any of the three modes provided

under Section 126(1). Each mode of inspection is independent

and separate. Therefore, it cannot be said that inspection of the

place or premises is mandatory or that the assessment cannot

be done without such an inspection.

10. The learned Standing Counsel submitted that in the

instant case unauthorised use of electricity was detected in the

inspection conducted in the premises in 2003. Penalty imposed

was paid by the 1st respondent. Penal charges were also being

paid. It is also not disputed that the unauthorised load was not 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

removed and regularised before or during the period with

respect to which Ext.P2 bill was issued. He hence submitted that

inspection of records was sufficient in the case at hand for

assessment pursuant to which Ext.P2 was issued. It is to be

noted that Ext.P2 as well as Ext.P6 were issued for the fixed

charges and energy charges which were omitted to be

demanded along with penal charges. In the nature of the

charges which were omitted and later demanded it cannot be

said that any fresh inspection of the premises was required.

Consumption will be recorded periodically for the purpose of

issuing bills. Therefore, records available with the Board were

sufficient to find out the escaped fixed charges and electricity

charges. Direction issued by this court in WP(C).No.30946 of

2011 was to comply with the requirements of S.126 as

discernible from paragraph 5 of the judgment. Inspection of the

records was hence sufficient for issuing Exts.P2 and P6.

Therefore it cannot be said that the Board did not comply with

the requirements under Section 126 of the Electricity Act when 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

it issued Ext.P6. Hence, the contention of the consumer that the

Board violated the directions issued by this Court as well as the

provisions of Section 126 is without merit.

11. The next aspect to be considered is as to whether

the Board was justified in raising demands in 2014 for the

period from 6/2007 to 4/2011 and 6/2008 to 3/2011. The

learned counsel for the consumer contended that under Section

126(5) of the Act, the assessment shall be limited to a period of

12 months immediately preceding the date of inspection. He

also pointed out that the limitation under Section 56(2) also

may apply. The learned Standing Counsel on the other hand

submitted that the said limitation would apply only when the

period during which unauthorised use of electricity had taken

place could not be ascertained. Section 126(5) is extracted

hereunder: -

"Section 126. Assessment......... (5) If the assessing officer reaches to the conclusion that unauthorised use of electricity has taken place, the assessment shall be made for the entire period during which such unauthorised use of 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

electricity has taken place and if, however, the period during which such unauthorised use of electricity has taken place cannot be ascertained, such period shall be limited to a period of twelve months immediately preceding the date of inspection."

12. It is clear from the reading of the provision that the

period of assessment shall be limited to 12 months immediately

preceding the date of inspection only if the period during which

unauthorised use of electricity has taken place cannot be

ascertained. In the present case period during which the Board

omitted to demand electricity charges and fixed charges is

clearly ascertainable and hence the provisions of Section 126(5)

of the Act have no application. As rightly contended by the

learned Standing Counsel, even the limitation under Section

56(2) will not apply in the case in view of the categorical

declaration by the Hon'ble Supreme Court in Assistant

Engineer(D1), Ajmer Vidyut Vitran Nigam Limited and Another

v. Rahamatullah Khan Alias Rahamjulla [(2020)4 SCC 650].The

Hon'ble Supreme Court held as under:-

2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

"9. Applying the aforesaid ratio to the facts of the present case, the licensee company raised an additional demand on 18-3-2014 for the period July 2009 to September 2011. The licensee company discovered the mistake of billing under the wrong Tariff Code on 18-3-2014. The limitation period of two years under Section 56(2) had by then already expired.

9.1. Section 56(2) did not preclude the licensee company from raising an additional or supplementary demand after the expiry of the limitation period under Section 56(2) in the case of a mistake or bona fide error. It did not, however, empower the licensee company to take recourse to the coercive measure of disconnection of electricity supply, for recovery of the additional demand.

9.2. As per Section 17(1)(c) of the Limitation Act, 1963, in case of a mistake, the limitation period begins to run from the date when the mistake is discovered for the first time. In Mahabir Kishore v. State of M.P. [Mahabir Kishore v. State of M.P., (1989) 4 SCC 1] , this Court held that : (SCC p. 11, para 22) "22. Section 17(1)(c) of the Limitation Act, 1963, provides that in the case of a suit for relief on the ground of mistake, the period of limitation does not begin to run until the plaintiff had discovered the mistake or could with reasonable diligence, have discovered it. In a case where 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

payment has been made under a mistake of law as contrasted with a mistake of fact, generally the mistake becomes known to the party only when a court makes a declaration as to the invalidity of the law. Though a party could, with reasonable diligence, discover a mistake of fact even before a court makes a pronouncement, it is seldom that a person can, even with reasonable diligence, discover a mistake of law before a judgment adjudging the validity of the law.

(emphasis supplied)"

9.3. In the present case, the period of limitation would commence from the date of discovery of the mistake i.e. 18-3-2014. The licensee company may take recourse to any remedy available in law for recovery of the additional demand, but is barred from taking recourse to disconnection of supply of electricity under sub-section (2) of Section 56 of the Act."

(Emphasis supplied)

13. The appellate authority allowed the appeal by Ext.P8

order holding that for assessment invoking Section 126 of the

Act, all the procedure under the said Section shall be complied

with, which would commence with the site inspection and

preparation of detailed site mahazar. As found already, for 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

assessment under Section 126 of the Act, inspection of the

premises is only one of the methods provided under Section

126(1). Observation of the appellate authority that every

assessment under Section 126 shall commence with inspection

and preparation of mahazar is therefore erroneous. The

appellate authority relied on the judgment of this Court in

Luqman Ali Muhammed v. Kerala State Electricity Board

[2013 SCC OnLine Ker 24478:2014 (2) KLT 833]. This Court

held that penalty for continued unauthorised extension can be

imposed only if the assessing officer is convinced that such

extension had actually continued during any period after the

date of inspection that too after complying with the procedure

under Section 126 of the Act. In the facts of the instant case the

unauthorised use of electricity was conceded by the consumer

by paying the penalty and by continuing to pay penal charges

for a long period. The Board has contended that it repeatedly

directed the consumer to dismantle the unauthorised load or to

regularise the same. The consumer has no case that it 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

disconnected the unauthorised load or regularised it before or

during the period with respect to which Ext.P6 was issued. In

such a situation, in my view, there was no requirement to

conduct any fresh inspection before issuing Ext.P6. Hence, the

reasoning of the appellate authority obtained from Ext.P8

cannot be sustained. It is liable to be set aside.

In the result, WP(C).No.17906/2016 is allowed. Ext.P8

order in appeal No.67/2015 is set aside. WP(C).No.40877/2016

is dismissed.

Sd/-

S.MANU JUDGE skj 2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

APPENDIX OF WP(C) 17906/2016

PETITIONER'S EXHIBITS

EXHIBIT P1 A TRUE COPY OF THE SITE MAHASSAR DATED 27-03-2003.

EXHIBIT P2 A TRUE COPY OF THE SAID BILL DATED 30- 10-2011 ALONG WITH THE CALCULATION STATEMENT.

EXHIBIT P3 A TRUE COPY OF THE REPRESENTATION FILED BEFORE THE ASSISTANT EXECUTIVE ENGINEER ON 10-05-2013.

EXHIBIT P4 A TRUE COPY OF THE JUDGMENT IN WPC 30946/2011 DATED 08-11-2013.

EXHIBIT P5 A TRUE COPY OF THE OBJECTION FILED BY THE 1ST RESPONDENT ON 17-07-2014.

EXHIBIT P6 A TRUE COPY OF THE FINAL ORDER PASSED ON 08-08-2014.

EXHIBIT P7 A TRUE COPY OF THE APPEAL PREFERRED BEFORE THE APPELLATE AUTHORITY.

EXHIBIT P8 A TRUE COPY OF THE ORDER PASSED BY THE APPELLATE AUTHORITY UNDER S. 127 OF THE ACT IN OP NO. 67 OF 2015 DATED 23-12- 2015.

2025:KER:65227 W.P.(C).Nos.17906 & 40877 of 2016

APPENDIX OF WP(C) 40877/2016

PETITIONER'S EXHIBITS

EXT.P1: TRUE COPY OF THE BILL DATED 18/07/2011 ISSUED BY THE 3RD RESPONDENT TO THE PETITIONER.

EXT.P2: TRUE COPY OF THE NOTICE DATED 04/08/2011 ISSUED BY THE PETITIONER'S COUNSEL TO THE RESPONDENTS 1 AND 2.

EXT.P3: TRUE COPY OF THE POSTAL ACKNOWLEDGEMENT EVIDENCING THE RECEIPT OF THE NOTICE ISSUED BY THE PETITIONER'S COUNSEL.

EXT.P4: TRUE COPY OF THE FINAL BILL DATED 31/10/2011 ISSUED BY THE 3RD RESPONDENT TO THE PETITIONER.

EXT.P5:                TRUE COPY OF THE STATEMENT OF ACCOUNTS
                       ISSUED    BY   THE  RESPONDENTS    TO   THE
                       PETITIONER.
EXT.P6:                TRUE COPY OF THE JUDGMENT IN WRIT
                       PETITON    (CIVIL)   NO.30946/2011    DATED
                       08/11/2013.
EXT.P7:                TRUE COPY OF THE BILL ALONG WITH THE
                       CALCULATION SHEET ISSUED BY THE 2ND
                       RESPONDENT TO THE PETITIONER.
EXT.P8:                TRUE COPY OF THE ORDER DATED 08/08/2014
                       ISSUED BY THE 2ND RESPONDENT.
EXT.P9:                TRUE COPY OF THE MEMORANDUM OF APPEAL
                       IN ITS FORMAT AND THE CONTENTS OF THE
                       APPEAL.
EXT.P10:               TRUE COPY OF THE DEMAND DRAFT NO.903050
                       DATED 01/09/2014 ISSUED IN FAVOUR OF
                       THE RESPONDENT FOR RS.9,29,300/-
EXT.P11:               TRUE COPY OF THE ORDER DATED 23/12/2015
                       OF    THE    KERALA   STATE    ELECTRICITY
                       APPELLATE AUTHORITY IN APPEAL NO.67 OF
                       2015.
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter