Saturday, 16, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Shwas Builders & Developers Pvt Ltd ... vs Premchand Surendran
2024 Latest Caselaw 26467 Ker

Citation : 2024 Latest Caselaw 26467 Ker
Judgement Date : 5 September, 2024

Kerala High Court

M/S. Shwas Builders & Developers Pvt Ltd ... vs Premchand Surendran on 5 September, 2024

MSA No. 22 of 2024
                                              ::1



                                                                         2024:KER:66964
                      IN THE HIGH COURT OF KERALA AT ERNAKULAM                        CR
                                            PRESENT

                      THE HONOURABLE MR. JUSTICE M.A.ABDUL HAKHIM

            THURSDAY, THE 5TH DAY OF SEPTEMBER 2024 / 14TH BHADRA, 1946

                                   MSA NO. 22 OF 2024

            AGAINST THE ORDER DATED 28.06.2024 IN REFA NO.48 OF 2023 OF

KERALA REAL ESTATE APPELLATE TRIBUNAL, ERNAKULAM ARISING OUT OF THE

ORDER       DATED    05.07.2023   IN   CO   NO.37   OF   2023   OF   KERALA   REAL   ESTATE

REGULATORY AUTHORITY, THIRUVANANTHAPURAM


            APPELLANTS/APPELLANT NOS 1 TO 4/RESPONDENTS NO. 1 TO 4:

        1           M/S. SHWAS BUILDERS & DEVELOPERS PVT LTD , REPRESENTED BY
                    MANAGING DIRECTOR
                    GROUND FLOOR, MYSTIC HEIGHTS PHASE-1, KANIYAMPUZHA BRIDGE,
                    KANIYAMPUZHA ROAD, EROOR P.O., ERNAKULAM DISTRICT, PIN -
                    682036

        2           SREENI PARAMESWARAN
                    AGED 47 YEARS
                    DIRECTOR, M/S. SHWAS BUILDERS & DEVELOPERS PVT LTD GROUND
                    FLOOR, MYSTIC HEIGHTS PHASE-1, KANIYAMPUZHA BRIDGE,
                    KANIYAMPUZHA ROAD, EROOR P.O., ERNAKULAM DISTRICT, PIN -
                    682036

        3           PARAMESWARAN NAIR
                    DIRECTOR, M/S. SHWAS BUILDERS & DEVELOPERS PVT LTD , GROUND
                    FLOOR, MYSTIC HEIGHTS PHASE-1, KANIYAMPUZHA BRIDGE,
                    KANIYAMPUZHA ROAD, EROOR P.O., ERNAKULAM DISTRICT., PIN -
                    682036

        4           SHEEJA P,
                    MITHILA, 104 5TH CROSS, RELIABLE TRANQUIL, HARALUR,
                    SOMASUNDRA PALAYA, BANGALORE, PIN - 560102
 MSA No. 22 of 2024
                                     ::2



                                                          2024:KER:66964
            BY ADVS.
            S.S.ARAVIND
            P.B.KRISHNAN (SR.)(K/1193/1994)




RESPONDENT/RESPONDNET/COMPLAINANT:

             PREMCHAND SURENDRAN
             B-23, JALVAYU VIHAR, PANAMPILLY NAGAR SHIHAB THANGAL ROAD,
             ERNAKULAM, PIN - 682036



      THIS MISC. SECOND APPEAL HAVING BEEN FINALLY HEARD ON 30.08.2024
ON 05.09.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 MSA No. 22 of 2024
                                      ::3



                                                               2024:KER:66964




                                                                         CR

                                JUDGMENT

1. The respondents 1 to 4 in Complaint No.37/2023 of the Kerala Real

Estate Regulatory Authority (the K-RERA) are the appellants in the

Miscellaneous Second Appeal filed under Section 58 of the Real

Estate (Regulation and Development Act, 2006 (the RERA). The

respondent is the complainant in the said complaint.

2. The parties are referred to according to their status before the K-

RERA.

3. The complainant is an allottee in the Villa Project by name 'Epcot

County' launched by the 1st respondent. The 1st respondent is a

private limited company engaged in the business of development

and construction of real estate projects. The respondents 2 to 4 are

::4

2024:KER:66964 its Directors. The 4th respondent is the landowner of the Project

also. The 5th respondent is another private limited company, which

is a sister concern of the 1st respondent.

4. The complainant filed the complaint claiming amounts under

various heads from the respondents alleging various defects,

deficiency and delay from the part of the respondents with respect to

the real estate project.

5. When the complaint was taken on file, the K-RERA found that the

Real Estate Project of the 1st respondent requires registration under

S.3 of the RERA and accordingly issued Show Cause Notice dt

06.03.2023 in the Complaint itself calling upon the respondents to

explain why action should not be initiated for violation of S.3 of the

RERA.

6. The Respondents did not file a Reply to the Show Cause Notice.The

K- RERA found that the Building Permit was issued on 28.11.2015

and since no documents were produced by the respondents to prove

::5

2024:KER:66964 that the villas and common areas in the real estate project were

completed before 01.05.2017, the K-RERA issued Interim Order dt

25.04.2023 directing the respondents to appear in person on

30.05.2023 at 11.00 a.m at its Head Office along with all the

relevant documents to explain as to why penalty as per S.59(1) of

the RERA shall not be imposed. The respondents filed a Reply to

the Show Cause Notice on 29.05.2023.

7. After considering the contentions of the respondents the K-RERA

passed interim order dt 05.07.2023 ordering the respondents to

register the real estate project within 30 days from the date of

receipt of the said order, imposing a penalty of Rs.2.59 lakhs, being

0.5% of the estimated cost of the real estate project and further

ordering that if the promoter fails to pay the penalty and continue to

violate S.3 even after 30 days from the date of receipt of the said

order, proceedings under S.59(2) shall be initiated.

::6

2024:KER:66964

8. The respondents filed Appeal before the Kerala Real Estate

Appellate Tribunal (the Tribunal) as REFA No. 48/2023 challenging

the said order dt 05.07.2023 of the K-RERA. The Tribunal vide its

order dt 28.06.2024 allowed the appeal in part confirming the order

with respect to the registration of the real estate project, setting

aside the imposition of penalty and exonerating the 5 th respondent.

It is also ordered that K-RERA shall take appropriate steps under

S.59(1) of the K-RERA at the appropriate stage if the contravention

is brought to its notice. The respondents are given one month's time

from the date of the Appellate Order to register the real estate

project with the K-RERA. The penalty was set aside on the ground

that penalty could not be imposed simultaneously with the direction

for registration. The 5th respondent was exonerated from the liability

on the ground that it has no connection whatsoever with the real

estate project launched by the 1st respondent.

::7

2024:KER:66964

9. I heard the learned Senior Counsel for the appellants Sri.P.B

Krishnan instructed by Adv. Sri.S.S.Aravind.

10. When the appeal came up for admission on 16.08.2024, the learned

Senior Counsel submitted that the impugned order dt.05.07.2023

passed by the K-RERA is unsustainable on account of jurisdictional

error since the same was passed by a Single Member of the K-RERA

which is impermissible under S.29 of the RERA. In view of the said

submission, a Report from the K-RERA was called for and the K-

RERA submitted a Report dt. 22.08.2024 stating that individual

members of the K-RERA are given powers by the K-RERA in its

meeting held on 27.11.2021 by delegation in the exercise of the

powers under S.81 of the RERA. The scope of Section 81 is

considered by the Hon'ble Supreme Court in Newtech

Promoters and Developers Pvt.Ltd. V. State of U P

and others [2021 SCC online SC 1044]. It is

::8

2024:KER:66964 apposite to extract Paragraph 112 of the said

decision.

112. S.81 of the Act 2016 empowers the authority, by

general or special order in writing, to delegate its powers

to any member of the authority, subject to conditions as

may be specified in the order, such of the powers and

functions under the Act. What has been excluded is the

power to make regulations under S.85, rest of the

powers exercised by the authority can always be

delegated to any of its members obviously for

expeditious disposal of the applications / complaints

including complaints filed under S.31 of the Act and

exercise of such power by a general and special order to

its members is always permissible under the provisions

of the Act.

::9

2024:KER:66964

11. Hence, the Single Member of K-RERA has the power and

jurisdiction to consider a complaint as it is perfectly within his

jurisdiction in view of the delegation of power by the K-RERA in

exercise of its powers under S.81 of the RERA.

12. The learned Senior Counsel further contended that the appellants are

only contractors as the land on which the villa of the complainant

was constructed belonged to the complainant as per the sale deed

executed by the 4th respondent landowner. The status of the

respondents is that of a contractor and not a promoter and the

respondents are not promoters as defined under S.2(zk) of the

RERA. On transfer of title as per S.17, the real estate project comes

to an end, thereafter, there could not be any registration of the real

estate project. The real estate project could not be treated as an

ongoing project since the project was completed on 24.05.2019, i.e.,

much before the establishment of K-RERA in Kerala. The direction

to register the project is a direction to do an impossible act. The

::10

2024:KER:66964 impugned order passed by the K-RERA is in the nature of an interim

order, the said order was passed without complying the procedure

under S.36 of the RERA which deals with the power of the K-RERA

to issue interim orders. The K-RERA ought to have conducted an

enquiry giving sufficient opportunity for the respondents to produce

documents and ought to have accepted the documents produced by

the respondents by marking the same in evidence. The prayers in the

complaint are not maintainable in view of the provisions under S.18.

13. It is revealed from the admitted pleadings in the case that the 1 st

respondent launched a villa project by name, 'Epcot County'

consisting of 15 twin villas (30 villas) in a land having an extent of

49.60 Ares owned by the 4th respondent. Building Permit was issued

for the project on 28.11.2015. An agreement for sale was executed

with the complainant on 01.06.2016. The Construction Agreement

was executed with the complainant and 1st respondent on

30.12.2016. The complainant agreed to purchase Plot No.11 having

::11

2024:KER:66964 an extent of 2.91 cents from the 4th respondent. The entire

construction of the villas was completed by the 1st respondent in

January, 2019. The Villa of the complainant was handed over on

12.02.2019. The Construction Agreement clearly mentions that the

1st respondent made a scheme to construct villas in the real estate

project; that the project is managed by the 1st respondent; that the

common area, common amenities and facilities proposed in the

village project shall be completed and handed over by the 1 st

respondent. The aforesaid clauses clearly indicate that the 1st

respondent is a promoter with respect to the real estate project. The

1st respondent is not a mere contractor engaged by the complainant

to construct his individual villa. The status of the 1 st respondent is

that of a promoter within the meaning of Se.2(zk) of the RERA and

not of a contractor.

14. The learned Senior Counsel contended that in the case of the villa

of the complainant, the occupancy certificate would be obtained by

::12

2024:KER:66964 the complainant on completion of the villa, and the 1 st respondent

has nothing to do with the matter. It is true that when the promoter

is not the owner of the land, the documents like building permits,

completion certificates, etc., are obtained in the name of the

landowners. But it does not in any way absolve the liability of

respondents 1 to 4 as a promoter of the project.

15. Proviso to S.3(1) of the RERA provides that the promoter shall

make an application for registration of the real estate project if the

project is ongoing on the date of commencement of the RERA and

for which completion certificate has not been issued. Admittedly,

the 1st respondent had not completed the project as on 01.05.2017,

ie, the date of commencement of the RERA. The 1st respondent does

not have a case that it has received the Completion Certificate with

respect to the real estate project prior to the commencement of the

RERA in order to avoid registration in view of S.3(2) (b) of the

RERA. Gong by the scheme of registration as provided in Section 3

::13

2024:KER:66964 of the RERA, with respect to a real estate project existing as on the

date of commencement of the RERA, the only two material factors

which are to be considered is whether the project was an ongoing

project as on the date of commencement of the RERA and whether

the Promoter has received Completion Certificate before the

commencement of the RERA. The date of establishment of the K-

RERA is not relevant and material in the statutory scheme to decide

whether a project is liable to be registered or not. Since the subject

real estate project was admittedly an ongoing one as on the date of

commencement of the Act, the respondents 1 to 4 are liable to

register the same under S.3 (1) of the RERA.

16. I am unable to accept the contention of the learned Senior Counsel

that the real estate project is concluded on the transfer of title as per

S.17 of the RERA and that since the transfer was done before

01.05.2017, there could not be any direction to register the project.

As per the statutory scheme of the RERA, it is the completion of the

::14

2024:KER:66964 project, what is relevant and material and not the transfer of title.

The RERA is enacted essentially to protect the interests of the

allottees of a real estate project. Their interests are to be protected

till the handing over of the agreed allotted apartment, villa or plot

with title over the same after completion of the project. The

adjudicatory mechanisms are provided for addressing all their

grievances till the handing over of the agreed allotted apartment,

villa or plot with title over the same after completion of the project.

The allottees of the real estate project may purchase divided or

undivided shares in the project by registered conveyances much

before the completion of the real estate project. Sometimes, such

registered conveyances are required for the allottees to create

mortgages for availing loans for payments to the promoter. It could

not be said that on the execution of the conveyance deed transferring

the title of the land, the real estate project would come to an end

even if the construction was not completed. There is no indication

::15

2024:KER:66964 in S.17 that once the transfer of title is made in favour of the

allottee, the real estate project has come to an end. If such a

contention is accepted it is easy for every promoter of a real estate

project to defeat the provisions of the RERA by transferring the title

of the land to the allottee before completion of the project. The

question of whether the project land is transferred to the allottee or

not is not a relevant factor for deciding whether the real estate

project is complete or not.

17. It is true that the impugned order dt 05.07.2023 is titled as an interim

order, but it could not be said that it is an interim order passed by K-

RERA invoking its power under S. 36. It is an order passed by K-

RERA when it is noticed that the real estate project of the

respondents is not registered under S.3 of the RERA. It is a

proceeding independent of the complaint. The said proceeding ends

with an order on the finding whether the project is registrable or not.

It has nothing to do with the allegations and claims in the complaint

::16

2024:KER:66964 which are proceeded and decided in the complaint itself. True, the

K-RERA ought to have initiated the proceedings under a separate

numbering either as suo motu or as I.A in order to avoid technical

objection. But failure to do so will not affect the nature and character

of the said order. It is essentially an order in an independent

proceedings and it does not have the trappings of an interim order

and hence compliance of the provisions in S. 36 of the RERA is not

necessary for passing orders under Ss.3 and 59 of the RERA.

18. In the case on hand, the impugned order was passed after giving

sufficient opportunities to the respondents to submit necessary

pleadings and evidence from their part. The said order is based on

material details, which are relevant for considering whether a real

estate project is liable for registration. It could not be said that the

respondents could not submit any relevant materials for the

adjudication of whether the real estate project is liable for

registration. All the contentions raised by the respondents were

::17

2024:KER:66964 considered on the basis of the admitted pleadings from the parties.

The respondents could not point out any material document which

could not be produced by them before the K-RERA in the matter of

registration.

19. As stated earlier, with respect to a real estate project existing as on

the date of commencement of the RERA, what is relevant is whether

it is an ongoing project and whether the completion certificate with

respect to the project is issued. The K-RERA is perfectly justified in

adjudicating the question of whether registration is required or not

when these two relevant materials are available. No prejudice

whatsoever is caused to the respondents.

20. Though the learned Senior Counsel advanced arguments with

respect to the sustainability of the claims of the complaint with

reference to S.18 of the RERA, I do not propose to consider the

same in this appeal as the said contentions are to be considered by

::18

2024:KER:66964 the K-RERA while considering the complaint. The impugned order

is limited to the question of registration of the project.

21. The K-RERA as well as the Tribunal considered all the contentions

of the respondents on the basis of the pleadings and evidence in the

case. The order of the K-RERA and the order of the Tribunal do not

require any interference. No substantial question of law arises in the

matter for invoking the jurisdiction of this Court under S.58 of the

RERA Act. The Miscellaneous Second Appeal is liable to be

dismissed.

22. Since the time of one month granted by the Tribunal to respondents

1 to 4 to register the real estate project with the K-RERA has

already expired, one month time from the date receipt of the

certified copy of this judgment is granted to the respondents 1 to 4

to register the real estate project with the K-RERA.

23. Since no separate procedure is prescribed for adjudicating the

question as to the registration of real estate projects under S.3, and

::19

2024:KER:66964 for adjudicating the imposition of penalty under S.59, the K-RERA

is free to adopt a procedure of its own in full compliance of the

principles of natural justice. Of course, a uniform procedure is to be

adopted by the K-RERA in all cases. Since the question of

registration of a project is to be adjudicated independently of the

allegations and claims in the main complaint, hereafter the K-RERA

shall initiate separate suo motu proceedings when the K-RERA is

prima facie of the view that a real estate project is liable for

registration, in the absence of any prayer with respect to the same in

the complaint.

24. The Miscellaneous Second Appeal is dismissed without costs.

Sd/-

M A ABDUL HAKHIM, JUDGE jma

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter