Citation : 2024 Latest Caselaw 32377 Ker
Judgement Date : 8 November, 2024
2024:KER:83429
WP(C).NO.20160/2024
1
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE MOHAMMED NIAS C.P.
FRIDAY, THE 8TH DAY OF NOVEMBER 2024 / 17TH KARTHIKA, 1946
WP(C) NO. 20160 OF 2024
PETITIONER:
T.BHASKARAN, AGED 75 YEARS,
S/O T.KRISHNAN, SANTHIVAN NIRMALAGIRI, KUTHUPARAMBA,
KANNUR, PIN - 670701.
BY ADVS. M/S.P.S.ANISHAD, LIMNA BHASKARAN,
ARCHANA MITHRAN O.K. & AISWARYA K.S.
RESPONDENTS:
1 THALASSERY MUNICIPALITY,
THALASSERY, KANNUR DISTRICT, PIN - 670101, REPRESENTED
BY ITS SECRETARY.
2 KERALA COASTAL ZONE MANAGEMENT AUTHORITY,
DIRECTORATE OF ENVIRONMENT AND CLIMATE CHANGE,4TH
FLOOR, KSRTC BUS TERMINAL, THAMPANOOR,
THIRUVANANTHAPURAM, PIN - 695001, REPRESENTED BY ITS
SECRETARY.
SRI. PRAKASH M P, SC
SRI.I.V.PRAMOD, SC
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY HEARD ON
08.11.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
2024:KER:83429
WP(C).NO.20160/2024
2
MOHAMMED NIAS C. P. , J.
============================
W. P. (C) No. 20160 of 2024
============================
Dated this the 8th day of November, 2024
JUDGMENT
The learned counsel for the petitioner seeks permission to withdraw this
Writ Petition without prejudice to his right to file a fresh writ petition in case a
fresh cause of action arises.
Permission granted. The Writ Petition is dismissed as withdrawn.
Sd/-
MOHAMMED NIAS C. P., JUDGE
MMG 2024:KER:83429
APPENDIX OF WP(C).NO.20160/2024
PETITIONER'S EXHIBITS:
EXHIBIT P1 A TRUE COPY OF THE DOCUMENT NO.1795/1982 OF THALASSERY SRO DATED 01.12.1982
EXHIBIT P2 A TRUE COPY OF THE FACTORY CLOSURE CERTIFICATE NO. E-1951/2019 K.DIS DATED 12/06/2019 ISSUED BY THE KOZHIKODE FACTORIES AND BOILERS JOINT DIRECTOR
EXHIBIT P3 A TRUE COPY OF THE RECEIPT OF THE PAYMENT DONE TO THE THALASSERY MUNICIPALITY DATED 12/12/2018
EXHIBIT P4 A TRUE COPY OF THE AGE CERTIFICATE OF BUILDING ISSUED BY THE THALASSERY MUNICIPALITY DATED 31/01/2020
EXHIBIT P5 TRUE COPY OF THE BUILDING PERMIT ISSUED BY THE MUNICIPAL COUNCIL, THALASSERY DATED 06/07/2019
EXHIBIT P6 A TRUE COPY OF ROOF CHANGING PLAN AND ELEVATION SANCTIONED BY THE THALASSERY MUNICIPALITY
EXHIBIT P7 A TRUE COPY OF THE OCCUPANCY CERTIFICATE ISSUED BY THE MUNICIPAL COUNCIL THALASSERY DATED 27.11.2019
EXHIBIT P8 A TRUE COPY OF THE SITE APPROVED PLAN, ELEVATION AND THE BUILDING PERMIT ISSUED BY THE MUNICIPAL OFFICE THALASSERY DATED 16.10.2020
EXHIBIT P9 A TRUE COPY OF THE LETTER DATED 23.11.2022 ISSUED FROM THE 2ND RESPONDENT
EXHIBIT P10 TRUE COPY THE LETTER FROM THE KERALA COASTAL ZONE MANAGEMENT AUTHORITY DATED 04/07/2023 2024:KER:83429
EXHIBIT P11 A TRUE COPY OF THE LETTER DATED 20.02.2024
EXHIBIT P12 A TRUE COPY OF THE LETTER DATED 08.05.2024 ISSUED BY THE 2ND RESPONDENT
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!