Friday, 08, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Kerala State Electricity Board Ltd vs The Kerala State Electricity Appellate ...
2024 Latest Caselaw 13711 Ker

Citation : 2024 Latest Caselaw 13711 Ker
Judgement Date : 28 May, 2024

Kerala High Court

Kerala State Electricity Board Ltd vs The Kerala State Electricity Appellate ... on 28 May, 2024

Author: Dinesh Kumar Singh

Bench: Dinesh Kumar Singh

               IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                PRESENT
            THE HONOURABLE MR. JUSTICE DINESH KUMAR SINGH
        TUESDAY, THE 28TH DAY OF MAY 2024 / 7TH JYAISHTA, 1946
                        WP(C) NO. 8072 OF 2020

PETITIONER:

            KERALA STATE ELECTRICITY BOARD LTD.,
            VYDYUTHI BHAVANAM, PATTOM, THIRUVANANTHAPURAM,
            REPRESENTED BY ITS SECRETARY.

            BY ADV.
               SRI. B. PREMOD


RESPONDENTS:

    1       THE KERALA STATE ELECTRICITY APPELLATE AUTHORITY
            (CONSTITUTED UNDER SECTION 127 OF THE ELECTRICITY
            ACT 2003), CC 51/52, NEAR 110 KV SUB STATION,
            VYTTILA, KOCHI - 682019.

    2       THE ASSESSING OFFICER (ASSISTANT ENGINEER),
            ELECTRICAL SECTION, KSEBL MUDAPPALLUR,
            PALAKKAD DISTRICT- 678014.

    3       K. P. SIYAD,
            M/S. GR TIMBER AND SAW MILL, IX/247B,
            PANTHAPARAMBU, MUDAPPALLUR P. O.,
            PALAKKAD DISTRICT - 675705.


     THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
28.05.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C) NO. 8072 OF 2020

                                     2


                    DINESH KUMAR SINGH, J.
                            --------------------------
                         W.P.(C) No. 8072 of 2020
                             -------------------------
                    Dated this the 28th day of May, 2024

                                JUDGMENT

1. Despite service of notice as per office report dated

01.09.2021 on the 3rd respondent, no one has put in appearance

on behalf of the 3rd respondent.

2. The present writ petition has been filed by the KSEB

impugning the Order dated 04.11.2017 passed by the Kerala

State Electricity Appellate Authority constituted under Section

127 of the Electricity Act, 2003 (hereinafter referred to as the

'Electricity Act' for short) in appeal No. 219/2017.

3. The 3rd respondent, a consumer was given LT IV A

industrial tariff with a sanctioned connected load of 77.875 KW

and contract demand of 87 KVA. This electricity connection was

meant to run a saw mill in the name and style of "G. R. Timbers &

Saw Mill". The energy charges were to be collected under LT IV

A, industrial tariff. Anti Power Theft Squad (APTS), Palakkad

unit of KSEB Ltd. along with the officials of Electrical Section

conducted a surprise inspection at the premises of the 3 rd

respondent on 08.06.2017. Site mahazar was prepared by the WP(C) NO. 8072 OF 2020

Assistant Engineer and provisional assessment of Rs. 9,33,276/-

was issued to the 3rd respondent on 12.06.2017. The allegation

against the 3rd respondent that, he had connected unauthorised

additional load of 89.783 KW over and above the sanctioned

load of 77.875 KW. The provisional assessment was confirmed

by the final assessment order dated 10.07.2017.

4. The 3rd respondent approached this Court by filing W.P.(C)

No. 25716 of 2017 (L). However, this Court vide Judgment and

Order dated 03.08.2017 directed the 3rd respondent to file

appeal before the appellate authority under the provisions of

Section 127 of the Electricity Act. The 3 rd respondent was

directed to remit only 50% of the fixed charges of the

assessment of the total assessed amount.

5. In view of the liberty granted by this Court, the 3 rd

respondent filed appeal No. 219/2017 before the Electricity

Appellate Authority. The Electricity Appellate Authority

considering the provisions of Section 126 of the Electricity Act

and Regulation 153 (15) of Kerala Electricity Supply Code 2014

as well as Judgment of this Court in Executive Engineer &

Another v. M/s. Sri Seetaram Rice Mill [2011 STPL (Web) 942

SC] held that the assessment in cases where usage of electricity WP(C) NO. 8072 OF 2020

was deducted to be completed twice the amount for the fixed

charges only. The appellate authority while coming to the said

conclusion has made the following observations;

"The above judgment made it clear that the assessment under Section 126 of the 2003 Act for the UAL detected shall be made at twice the rate under applicable tariff for the fixed charges only and not for the energy charges unless regularisation of such UAL or enhancement of contract demand necessitates upgradation of the existing distribution system or enhancement of voltage level of supply. In the case at hand, as the UAL of 89.783 KW has been found used for the functioning of the same industrial unit, the tariff applicable for the assessment is LT IV A industrial. The appellant had connected UAL of 89.783 KW over and above the sanctioned load, resulting in a total load of 167.658 KW, with the maximum demand recorded in the premises 91.6 KVA. As per Regulation 11 (1) of the Kerala Electricity Supply Code 2014, the maximum contract demand permissible for low tension consumer who avails power under demand based metering shall be 100 KVA, irrespective of his connected load. Hence it is observed that regularisation of the UAL with a WP(C) NO. 8072 OF 2020

maximum contract demand of 91.6 KVA, in the premises of LT consumer number 7719 does not necessitate any enhancement of voltage level of supply.

But the respondent argued that to regularise the unauthorised additional load the existing 100 KVA transformer has to be enhanced to 160 KVA and hence an upgradation of the distribution system is required. The respondent argued that the actual maximum demand in the premises is not recorded in the meter as it is of 30 minutes time integration type and the load of shorter duration do escape from recording and hence the recorded maximum demand of 91.6 KVA was not the actual demand occurred in the premises. The respondent further argued that the failure of the 100 KVA transformer, exclusively feeding this premises, on 05.06.2017 and also the frequent blowing off the drop out fuses of the transformer were due to that excess loading. But it is observed that the maximum demand has been defined vide Regulation 2(56) of Supply Code 2014 as "maximum demand" means the highest average load measured in KVA or KW at the point of supply of a consumer during a consecutive period of thirty minutes or such other consecutive period as specified by the Commission; during the billing WP(C) NO. 8072 OF 2020

cycle.' In this circumstances the considered view of the Authority is that there is no relenence in the argument of the respondent that the maximum demand recorded in the meter with 30 minutes integration was not the actual maximum demand. The respondent has failed to establish that the 100 KVA transformer (exclusively feeding the premises) has to be enhanced to 160 KVA for regularising the UAL with a maximum contract demand of 91.6 KVA. Hence the neccessity for any upgradation of the existing distribution system to regularise the UAL could not been proved by the respondent. In this circumstance, the Authority is of the view that the assessment under Section 126 of 2003 Act for the UAL detected shall be made at twice the rate under LT IV A, industrial tariff for the fixed charges only and not for the energy charges. The assessment may be revised accordingly. Since the period of unauthorised use has not been ascertained, the same shall be limited to twelve months immediately preceding the date of inspection by virtue of Section 126 (5) of the 2003 Act."

6. The appellate authority set aside the final assessment and

directed the assessing authority to revise the assessment within WP(C) NO. 8072 OF 2020

a period of fifteen days at twice the rate under LT IV A tariff for

the fixed charges only on account of the unauthorised

additional load (UAL) of 89.783 KW, for a period of twelve

months prior to the date of inspection.

7. As can be seen from the extracted part of the Order of the

appellate authority, the appellate authority placed reliance on

the Judgment of this Court in W.P.(C) No. 6993 of 2013.

8. The learned Counsel for the petitioner Board has

submitted that the said Judgment has been overruled by the

Supreme Court in the case of Kerala Electricity Board vs.

Thomas Joseph alias Thomas M. J. and others [2022 SCC

Online 1737].

9. The Supreme Court after considering the provisions of

Section 126 as well as 45(3)(a) of the Electricity Act has

categorically held that, the charges for electricity certified by a

distribution lincensee include fixed charges in addition to

charges for the equal electricity supplied and consumed. Tariff

includes both fixed charges and energy charges and once the

assessing authority arrives at the conclusion that unauthorised

use of electricity has taken place, he is obliged to make

assessment charge equal to twice the tariff applicable which WP(C) NO. 8072 OF 2020

includes dues payable towards the energy charges also.

Paragraph 88 of the said Judgment which is relevant for the

purposes of the present writ petition is extracted hereunder;

"88. A plain reading of Section 45(3)(a) of the Act 2003 referred to above would indicate that the charges for electricity certified by a distribution licensee include the fixed charges, in addition to the charges for the actual electricity supplied and consumed. In such circumstances, it can be said that the tariff includes both, fixed charges and energy charges and once the assessing officer arrives at the conclusion that unauthorised use of electricity has taken place, he is obliged to make the assessment charge equal to twice the tariff applicable, which includes the dues payable towards the energy charges also."

10. Sub-section (5) of Section 126 of the Electricity Act

empowers the assessing authority to assess the misuse of

electricity twice the rate applicable for connection of the

consumer. It further provides that if the time period for misuse

is not determinable, then the said charges will be confined to

twelve months preceding the date of inspection. Otherwise it

would be leviable for the entire period of misuse. The plain

reading of Sub-section (5) of Section 126 read with Section 45(3)

(a) of the Electricity Act would make it clear that, for misuse of

the electricity, all the charges are to be assessed at twice which WP(C) NO. 8072 OF 2020

would include the energy charge and fixed charge as held by the

Supreme Court.

11. In view thereof, the impugned Order in Exhibit P-7 passed

by the appellate authority is unsustainable and same is set

aside. As a result thereof, the final assessment order in Exhibit

P-4 would stand survived.

In the above view, the present writ petition is allowed.

Sd/-

DINESH KUMAR SINGH JUDGE Svn WP(C) NO. 8072 OF 2020

APPENDIX OF WP(C) 8072/2020

PETITIONER'S EXHIBITS

EXHIBIT P1 THE TRUE COPY OF THE MAHAZAR DATED 08/06/2017.

EXHIBIT P2 THE TRUE COPY OF THE PROVISIONAL BILL ISSUED DATED 08/06/2017.

EXHIBIT P3 THE TRUE COPY OF THE OBJECTION FILED BY THE 3RD RESPONDENT DATED 19/06/2017.

EXHIBIT P4 THE TRUE COPY OF THE FINAL ASSESSMENT ORDER ISSUED BY THE 2ND RESPONDENT ASSESSING OFFICER DATED 20/07/2017.

EXHIBIT P5 THE TRUE COPY OF THE APPEAL MEMORANDUM SUBMITTED BY THE 3RD RESPONDENT BEFORE THE KERALA STATE ELECTRICITY APPELLATE AUTHORITY.

EXHIBIT P6 THE TRUE COPY OF THE REPORT / STATEMENT FILED BY THE ASSESSING OFFICER IN THE ABOVE APPEAL.

EXHIBIT P7 THE TRUE COPY OF THE ORDER OF THE KERALA STATE ELECTRICITY APPELLATE AUTHORITY.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter