Citation : 2024 Latest Caselaw 5449 Ker
Judgement Date : 16 February, 2024
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
FRIDAY, THE 16TH DAY OF FEBRUARY 2024 / 27TH MAGHA, 1945
CRP NO. 370 OF 2021
AGAINST THE ORDER/JUDGMENT OPELE 623/2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
SUNI BABU
AGED 50 YEARS
EETTUNGAPADI, CHERANELLOOR, KOOVAPPADY VILLAGE,
KUNNATHUNAD TALUK 683 544
BY ADV P.T.JOSE
RESPONDENT/S:
1 POWER GRID CORPORATION OF INDIA
CONSTRUCTION AREA OFFICE, KAKKANAD, NOW IN
PAO/400, 220KV SUBSTATION, KUMARAPURAM P.O.,
PALLIKARA, KOCHI 682 303, REP.BY DEPUTY MANAGER
2 THE SPECIAL TAHSILDAR (L.A.)
POWER GRID CORPORATION OF INDIA, CHEVARAMBALAM,
KOZHIKODE, NOW NEAR CIVIL STATION, KAKKANAD,
ERNAKULAM DISTRICT, PIN 682 030
OTHER PRESENT:
GP SYLAJA S.L.
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY
HEARD ON 20.12.2023, ALONG WITH CRP.166/2022, THE COURT
ON 16.02.2024 DELIVERED THE FOLLOWING:
CRP Nos.370/21 & 166/22
-2-
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
FRIDAY, THE 16TH DAY OF FEBRUARY 2024 / 27TH MAGHA, 1945
CRP NO. 166 OF 2022
AGAINST THE ORDER/JUDGMENT OPELE 623/2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
POWER GRID CORPORATION OF INDIA
POWER GRID CORPORATION OF INDIA LTD.,
CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
KAKKANAD, COCHIN - 682 030, PRESENTLY AT
CONSTRUCTION AREA OFFICE, 400/220, KV SUB
STATION, KUMARAPURAM P.O, PALLIKKARA, ERNAKULAM
- 683 565, REPRESENTED BY ITS SENIOR GENERAL
MANAGER, PIN - 683565
BY ADV MILLU DANDAPANI
RESPONDENT/S:
1 SUNI BABU
W/O BABU, AGED 43 YEARS, EETTUNGAPADI,
CHERANELLOR, KOOVAPPADY VILLAGE, KUNNATHUNAD
TALUK, PIN - 683544
2 THE SPECIAL TAHSILDAR (LA)
POWER GRID CORPORATION OF INDIA LTD.
CHEVARAMBALAM, KOZHIKODE - 673 017, PIN - 673017
BY ADV P.T.JOSE
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
20.12.2023, ALONG WITH CRP.370/2021, THE COURT ON 16.02.2024
DELIVERED THE FOLLOWING:
CRP Nos.370/21 & 166/22
-3-
ORDER
Dated this the 16th day of February, 2024
These revision petitions are filed
challenging the common order passed by the
Additional District Judge-VI, Ernakulam in O.P.
(Electricity) No.623 of 2013. The original
petition was filed by the revision petitioner in
CRP No.370 of 2021 (hereinafter called 'the
claimant'), being dissatisfied with the
compensation awarded towards the damage and loss
sustained due to the drawing of 400 KV lines
across his property by the Power Grid Corporation
of India Ltd (hereinafter called 'the
Corporation'). The essential facts are as under;
The claimant is in ownership and possession
of landed property having an extent of 46 Ares in
Sy.No.40/3 of Koovappady Village in Kunnathunadu
Taluk. The land was cultivated with various
yielding and non-yielding trees. According to
the claimant, to facilitate drawing of the lines CRP Nos.370/21 & 166/22
and smooth transmission of power, large number of
trees were cut from his property. The drawing of
high tension lines rendered the land underneath
and adjacent to the lines useless, resulting in
diminution of the value of the property. In
spite of the huge loss suffered by the claimant,
only an amount of Rs.7,715/- was paid as
compensation towards the value of yielding and
non-yielding trees cut. Surprisingly, no
compensation was granted for diminution in land
value. Hence, the original petition was filed,
seeking enhanced compensation towards the value
of trees cut and diminution in land value.
2. The court below rejected the claim for
enhanced compensation for the value of trees cut
since no evidence in support of the claim was
produced. As far as the claim for enhanced
compensation towards diminution in land value is
concerned, the court below relied on Ext.A7
document as well as Exts.C16 and C16(a)
commission report and sketch. Relying on CRP Nos.370/21 & 166/22
Ext.C16(a) sketch, it was found that no electric
line was drawn over the claimant's property and
only the outer corridor passes through 2.200
cents of claimant's property. For outer corridor,
20% of the land value was granted as
compensation. Accordingly, the claimant was
found entitled to compensation of Rs.74,773/-.
Dissatisfied with the quantum of enhancement, the
claimant has filed CRP No.370 of 2021, whereas
the Corporation has filed CRP No.166 of 2022
contending that the enhancement ordered is far in
excess of the actual damage sustained.
3. Heard Adv.P.T.Jose for the claimant and
Adv.Millu Dandapani for the Corporation.
4. Learned Counsel for the claimant
contended that the court below committed gross
illegality in refusing to grant enhanced
compensation for the loss sustained due to the
cutting of valuable trees, in spite of the
Advocate Commissioner assessing and reporting the
loss. The findings in the Commissioner's report CRP Nos.370/21 & 166/22
were not relied on by the court below for the
reason that the property was inspected much after
the trees were cut. The said reasoning is flawed
since the trees were cut much after issuance of
notification by the Corporation and the cause of
action for filing the original petition arose
only on payment of the initial compensation,
even later.
5. It is submitted that the court below
grossly erred in granting only 20% for the outer
corridor. Considering the extent of damage
sustained and the diminution in land value
consequent to the drawing of lines, the court
below ought to have granted compensation as
claimed.
6. Learned Counsel for the Corporation
contended that, compensation towards diminution
in land value granted is exorbitant and there is
no rationale in granting 9% interest on that
amount. The court below also erred in relying on
Ext.A7 for fixing the land value of the CRP Nos.370/21 & 166/22
claimant's property. As the drawing of electric
lines does not prohibit the landowner from
conducting agricultural activities and putting up
small structures, 20% for the outer corridor is
exorbitant.
7. A careful scrutiny of the impugned order
reveals that the claim for enhancement of
compensation towards the value of trees cut was
rightly rejected since no supporting material,
other than the findings in the Advocate
Commissioner's report, was made available. As
found by the court below, apart from the
interested testimony of a solitary witness, who
is the claimant in some of the connected cases,
no other independent witness was examined to
prove the claim. It is also not in dispute that
the trees were cut in the year 2011 and the
commissioner inspected the property after a long
period and had assessed the value of the trees on
a comparison with the trees standing in the
remaining property and nearby properties. Such CRP Nos.370/21 & 166/22
comparison, having no scientific basis, is not
sufficient to discard the contemporaneous
valuation statement prepared by the Corporation.
8. As far as the diminution in land value
is concerned, the factors to be taken into
consideration, as laid down in KSEB v. Livisha
[(2007) 6 SCC 792] are as under;
"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."
On careful scrutiny of the impugned order, it is
seen that the compensation was enhanced after
taking all the above factors into consideration.
The nature of the land, the cultivation therein, CRP Nos.370/21 & 166/22
and the manner in which the land was affected by
drawing of the lines have all been considered
fixing the land value as well as the percentage
of diminution. For the outer corridor, 20% is
granted, which I find to be just and proper. As
such, there is no illegality or material
irregularity in the impugned order, warranting
intervention by this Court in exercise of the
revisional power under Section 115 of the Code of
Civil Procedure.
For the aforementioned reasons, the civil
revision petitions filed by the claimant as well
as the Corporation are dismissed. The Power Grid
Corporation shall pay the enhanced compensation
fixed by the court below within three months of
receipt of a copy of this order.
Sd/-
V.G.ARUN JUDGE Scl/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!