Citation : 2024 Latest Caselaw 5040 Ker
Judgement Date : 15 February, 2024
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE DEVAN RAMACHANDRAN
THURSDAY, THE 15TH DAY OF FEBRUARY 2024 / 26TH MAGHA, 1945
WP(C) NO. 11793 OF 2022
PETITIONER:
RADHAKRISHNAN O., AGED 71 YEARS, S/O.OMMINI,
KRISHNAVILASAM, CHOOLATHEERUVU, MUTHUKULAM
NORTH, ALAPPUZHA DISTRICT.
BY ADVS.
K.S.HARIHARAPUTHRAN
BHANU THILAK
RESPONDENTS:
1 STATE OF KERALA, REP. BY THE SECRETARY TO WATER
RESOURCES, GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM - 695 001.
2 SUPERINTENDING ENGINEER, KUTTANAD DEVELOPMENT
CIRCLE, CHENGANNUR - 689 121.
3 THE EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION,
DEPARTMENT OF IRRIGATION, CHENGANNUR, ALAPPUZHA
DISTRICT - 689 121.
4 BRANCH MANAGER, KERALA FINANCIAL CORPORATION,
BRANCH OFFICE, ALAPPUZHA - 688 001.
BY ADVS.
ADV. VENUGOPAL.M.R
DHANYA P.ASHOKAN(K/001671/2000)
S. MUHAMMAD ALIKHAN(K/000644/2020)
SRI. SUJITH MATHEW JOSE
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
15.02.2024, ALONG WITH WP(C)NO.30034/2019, THE COURT ON THE SAME
DAY DELIVERED THE FOLLOWING:
WPC 11793/22 & 30034/19
2
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE DEVAN RAMACHANDRAN
THURSDAY, THE 15TH DAY OF FEBRUARY 2024 / 26TH MAGHA, 1945
WP(C) NO. 30034 OF 2019
PETITIONER:
S. PRIYA, AGED 48 YEARS, PROPRIETRESS,
M/S. DEEVIKA CONSTRUCTIONS, 10 B, SREE
DHANYA HEAVENS, AMALAMUKKU, PERROORKADA P O,
THIRUVANANTHAPURAM-695001.
BY ADVS.
K.S.HARIHARAPUTHRAN
SMT.BHANU THILAK
RESPONDENTS:
1 STATE OF KERALA, REPRESENTED BY THE SECRETARY FOR
WATER RECOURSES, GOVERNMENT SECRETARIAT-695001.
2 THE CHIEF ENGINEER, INLAND WATER WAYS AND KUTTANAD
PACKAGE, ALAPPUZHA-688011.
3 THE SUPERINTENDENT ENGINEER, KUTTANAD DEVELOPMENT
CIRCLE, CHENGANNUR, ALAPPUZHA-689121.
4 THE EXECUTIVE ENGINEER, MINOR IRRIGATION DIVISION,
CHENGANNUR, ALAPPUZHA-689121.
5 THE ASSISTANT EXECUTIVE ENGINEER, KUTTANAD
DEVELOPMENT SUB-DIVISION, CHARUMMOOD,MAVELIKKARA,
ALAPPUZHA-690505.
6 THE ASSISTANT EXECUTIVE ENGINEER, KUTTANAD
DEVELOPMENT SUB-DIVISION, HARIPAD, ALAPPUZHA-690514.
7 THE ASSISTANT ENGINEER, KUTTANAD DEVELOPMENT
SECTION, KATTANAM, CHARUMMODU, ALAPPUZHA-689121.
8 THE ASSISTANT ENGINEER, MINOR IRRIGATION SECTION,
HARIPAD, ALAPPUZHA-690514.
WPC 11793/22 & 30034/19
3
BY ADV.
SRI.SUJITH MATHEW JOSE - SPL GP
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION
ON 15.02.2024, ALONG WITH WP(C)NO.11793/2022, THE COURT ON THE
SAME DAY DELIVERED THE FOLLOWING:
WPC 11793/22 & 30034/19
4
JUDGMENT
[WP(C) Nos.11793/2022, 30034/2019]
I am considering these Writ Petitions together because, the first
among them has been filed by Smt.Priya; while, the second by her
power-of-attorney; wherein, she asserts that she is the Contractor of
a work entrusted to her by the Irrigation Department of the
Government of Kerala, under the 'Kuttanad Package'; and assails
Exts.P10 in WP(C)No.30034/2019 as being illegal and unlawful, since
it terminates the contract at her risk and cost, on the allegation that
she did not complete the work, even after having been given
sufficient time.
2. That said, WP(C)No.11793/2022 has been filed by the
petitioner, seeking directions to the respondents therein to effect
payment of amounts under the 7 th part-bill as per Ext.P1, which has
been denied, which, according to her, is without any tangible
reason. She thus prays that both Writ Petitions be allowed in terms
of the prayers made therein.
3. Sri.K.S.Hariharaputhran - learned counsel for the
petitioner, explained that, even though his client was awarded the WPC 11793/22 & 30034/19
contract under the 'Kuttanad Package, it became subsequently clear
that it would be impossible to complete the same on account of
various factors, including the impediments of natural causes, as also
the variation in climate and weather. He added that, this is evident
from the fact that, in Ext.P5 - which is the Minutes of the meeting
to review the work progress, held as early as in the year 2017 - it
was recorded that no new work can be completed under the
'Package' and that no administrative sanction for works will be
further issued. He pointed out that, as per the third decision therein,
works which were found not capable of being completed in the near
future, were recommended to be dropped. He submitted that the
factum of his client rendered incapacitated to complete the work -
it being impossible, particularly on account of the ravaging floods of
the years 2018 and 2019 - is evident from Exts.P7 and P8
recommendations made by the Superintending Engineer himself, but
that it was without even adverting to the same that Ext.P10 in
WP(C)No.30034/2019 has been issued, terminating her contract. He
thus prayed that the said order be set aside; consequentially, praying
that the respondents be directed to honour the part-bill with respect WPC 11793/22 & 30034/19
to the work in question, which is the subject matter in
WP(C)No.11793/2022, pointing out that it has been now held up
solely because of the aforementioned order of termination still
remaining in force, though stayed by this Court. He concluded,
pointing out that, in Ext.P2 in WP(C)No.30034/2019, all the
assertions of his client has been admitted and her part-bills ordered
to be disbursed.
4. Sri.Sujith Mathew Jose - learned Special Government
Pleader, responded to the afore submissions of
Sri.K.S.Hariharaputhran, saying that the petitioner cannot shy away
from her obligations under the contract awarded to her, which is
the subject matter in WP(C)No.30034/2019. He invited my attention
to Ext.P10, to argue that, as stated therein, even though petitioner's
original contract period was to expire on 06.03.2016, it was
extended multiple times, namely, on 06.09.2016, 31.12.2016,
31.03.2017, 31.03.2018, 29.06.2018, 27.09.2018, 26.12.2018,
31.03.2019 and 29.06.2019; and that this was done so as to provide
the petitioner enough time to complete the work. He submitted that,
however, even after the lapse of more than 53 months since the WPC 11793/22 & 30034/19
commencement of work, the progress was found to be only 11.14%,
and therefore, that this is a case where even a hearing to the
petitioner was not necessary, to conclude that she has acted in
violation of her contractual obligations. He submitted that, therefore,
Ext.P10 in WP(C)No.30034/2019 is irreproachable; and
consequently, that, as per the applicable Rules, Regulations and
Circulars holding the field, the petitioner's further bills under the
contract cannot be favoured to her and therefore, the reliefs sought
in WP(C)No.11793/2022 being untenable.
5. Smt.Dhanya Ashokan - learned Standing Counsel for the
Kerala Financial Corportaion (KFC) - 4 th respondent in
WP(C)No.11793/2022 - at this time, intervened to say that the
petitioner had availed of certain financial facilities from her client,
on the strength of a power-of-attorney, to the effect that any
payment by the official respondents will be credited to the loan
account only. She submitted that, therefore, if any relief is to be
granted by this Court in these Writ Petitions, then it may be
clarified that the official respondents will credit the eligible amounts
into the loan account in question and not to the petitioner directly. WPC 11793/22 & 30034/19
She added that, this is more so because, the account has now
become a Non Performing Asset and her client has already initiated
recovery action against the petitioner.
6. I have examined the afore rival positions of the parties
very carefully, with specific reference to the documents produced by
them in the two Writ Petitions.
7. The initial sets of facts are without dispute, namely that
the petitioner was contracted with the work under the 'Flood
Management Programme', which is a centrally sponsored scheme;
and that the site was handed over to her on 13.03.2015, with the
time of completion being 06.03.2016.
8. Interestingly, Ext.P10 thereupon says that the time frame
for completion of work was extended at least nine times from 2016
to 2019; and what is crucially relevant in this regard is that many
of those were granted without imposition of fine. Obviously, the
respondents were also aware that the extensions granted without fine
were on account of the fact that the petitioner was incapacitated
from completing the work within the time schedules; and there is
some reflection on this in Ext.P5 - which is the Minutes of a High WPC 11793/22 & 30034/19
Level Committee of all officers concerned, held as early as on April
2017. Perhaps, this Court could have disregarded Ext.P5, it being
the Minutes of the meeting conducted much earlier than the period
extended to the petitioner, but what then becomes relevant are
Exts.P7 and P8 recommendations, made by the Superintending
Engineer dated 12.02.2019 and 15.05.2019 respectively.
9. As is ex facie evident from the said proceedings, the
explanation of the petitioner - that though she was trying to
complete the work within the time frame stipulated, she was forced
with natural disasters including floods, thus being unable to
complete it under the contract - was taken into account and
virtually conceded to. It is also recorded in both the proceedings
that a revised estimate for the work will have to be done; and more
crucially, in Ext.P8, the Superintending Engineer then goes on to say
that the completed works of the petitioner were found to be
satisfactory by the farmers; and further that, though she was
originally granted 365 days for completion, only 75 days could have
been used on account of the natural conditions available.
10. To fortify this, the Superintending Engineer thereafter WPC 11793/22 & 30034/19
says that all these factors were intimated to the other Authorities
and that since the petitioner was unable to complete the work for
various reasons which are not attributable to her, a revised estimate
was required to be settled, to provide most essential benefits to the
farmers of the area in question. In fact, the said Engineer concludes
Ext.P8 in an accusatory tone, saying that none of the other
Authorities took any action in this regard until then.
11. Pertinently, as argued by Sri.Hariharaputhran, in Ext.P1
produced along with WP(C)No.30034/2019, the afore is virtually
conceded and a recommendation made to honour the part-bills of
the petitioner.
12. One, therefore, fails to understand how, in the matrix of
the afore factual situation, the same Authority who issued Exts.P7
and P8 could have then issued Ext.P10, merely saying that since the
petitioner could not complete the work within the time frame
stipulated, her contract is liable to be cancelled. It is also difficult to
fathom how the Superintending Engineer could have entered into a
conclusion that the petitioner had ' committed breach of contract
repeatedly and has no interest to complete the work ' (sic), when he WPC 11793/22 & 30034/19
himself has made some recommendations as mentioned above.
13. I do not propose to speak any further on this issue
because, it would amount to pre-judging the matter, since am of the
view that the entire scenario will have to re-adjudicated and re-
evaluated by the Superintending Engineer, or such other competent
Authority. I am persuaded to this view because Ext.P10 does not
show any participation of the petitioner during the proceedings when
it was issued, though it refers to the notice dated 22.07.2019, which
is stated to be the final notice notifying her of the termination of
contract. However, since Ext.P10 does not reflect any hearing having
been given to the petitioner, or consideration of the
recommendations in Exts.P1, P7 and P8, as also her explanation;
and am hence certain that the entire matter will require to be
reconsidered without any avoidable delay.
14. The afore being so concluded, as regards
WP(C)No.30034/2019, the corollary question is whether the
petitioner's bills ought to be paid with respect to the same work in
WP(C)No.11793/2022. In this regard, the petitioner asserts that she
has completed more than 50% of the works and was entitled to WPC 11793/22 & 30034/19
more than Rs.11 Crores, but that she was paid only about Rs.2.5
Crores. It is her specific contention that, since she has been pushed
to financial crisis on account of such refusal, she is left without any
other option, but to approach this Court.
15. It is, therefore, limpid that the reliefs sought for in
WP(C)No.11793/2022 has a direct bearing on the action this Court
proposes to order in WP(C)No.30034/2019 because, the work is same
and the disbursement of amounts sought for in the former is part of
the work, which is the subject matter of the latter.
In the afore circumstances, these Writ Petitions are ordered in
the following manner:
a) WP(C)No.30034/2019 is allowed and Ext.P10 set aside;
with a consequential direction to the 3 rd respondent, or any other
competent Authority, to re-evaluate the claims of the petitioner,
after affording her an opportunity of being heard and of filing
objections, adverting specifically to Exts.P1, P5, P7 and P8 therein;
thus culminating in an appropriate order/necessary action thereon, as
expeditiously as is possible, but not later than two months from the
date of receipt of a copy of this judgment.
WPC 11793/22 & 30034/19
b) WP(C)No.11793/2022 is allowed to the limited extent of
directing the official respondents therein to disburse the amounts
eligible to the petitioner, as may be found due to her, after
direction in (a) above is completed, which shall be done not later
than one month thereafter.
c) Needless to say, while disbursing eligible amounts, the
authorities will also hear the KFC and take a call whether such
payments are to be made directly to the loan account or to the
petitioner.
Sd/-
RR DEVAN RAMACHANDRAN
JUDGE
WPC 11793/22 & 30034/19
APPENDIX OF WP(C) 30034/2019
RESPONDENT EXHIBITS
Exhibit EXHIBIT R1(a); TRUE COPY AGREEMENT
DATED,23.03.2015
Exhibit EXHIBIT R1(b):TRUE COPY OF THE REVELANT
PAGE OF THE TENDER DOCUMENT
Exhibit EXHIBIT R1(c): TRUE COPY OF THE
MEASUREMENT AND PART BILL DATED 14-09--
Exhibit EXHIT R1(d): TRUE COPY OF THE MEASUREMENT,
BILL AND PASS ORDER
Exhibit EXHIBIT R1(b):TRUE COPY OF THE REVELANT
PAGE OF THE TENDER DOCUMENT
Exhibit EXHIT R1(d): TRUE COPY OF THE MEASUREMENT,
BILL AND PASS ORDER
Exhibit EXHIBIT R1(c): TRUE COPY OF THE
MEASUREMENT AND PART BILL DATED 14-09--
Exhibit EXHIBIT R1(b):TRUE COPY OF THE REVELANT
PAGE OF THE TENDER DOCUMENT
Exhibit EXHIBIT R1(a); TRUE COPY AGREEMENT
DATED,23.03.2015
Exhibit EXHIT R1(d): TRUE COPY OF THE MEASUREMENT,
BILL AND PASS ORDER
Exhibit EXHIBIT R1(a); TRUE COPY AGREEMENT
DATED,23.03.2015
Exhibit EXHIBIT R1(c): TRUE COPY OF THE
MEASUREMENT AND PART BILL DATED 14-09--
Exhibit EXHIBIT R1(b):TRUE COPY OF THE REVELANT
PAGE OF THE TENDER DOCUMENT
Exhibit EXHIBIT R1(c): TRUE COPY OF THE
MEASUREMENT AND PART BILL DATED 14-09--
Exhibit EXHIT R1(d): TRUE COPY OF THE MEASUREMENT,
BILL AND PASS ORDER
Exhibit EXHIBIT R1(a); TRUE COPY AGREEMENT
DATED,23.03.2015
PETITIONER EXHIBITS
EXHIBIT P9 TRUE COPY OF THE 7TH PART BILL DATED
30.07.2019.
EXHIBIT P8 TRUE COPY OF THE LETTER DATED 15.05.2019
IS PRODUCED.
EXHIBIT P7 TRUE COPY OF THE MINUTES OF THE MEETING
WPC 11793/22 & 30034/19
DATED 12.02.2019 CONVENED BY 3RD
RESPONDENT.
EXHIBIT P6 TRUE COPY OF THE NOTICE DATED 26.11.2018
ISSUED BY THE 4TH RESPONDENT TO THE 3RD
RESPONDENT RECOMMENDING FOR EXTENSION OF THE PERIOD OF THE SUBJECT WORK UP TO 31.03.2019 WITH FINE.
EXHIBIT P5 TRUE COPY OF THE MINUTE OF THE MEETING CONVENED BY THE ADDITIONAL CHIEF SECRETARY(FINANCE) HELD ON 26.04.2017.
EXHIBIT P4 TRUE COPY OF THE INTIMATION DATED 14.01.2016 BY THE 4TH RESPONDENT TO THE 3RD RESPONDENT.
EXHIBIT P2 TRUE COPY OF THE PROCEEDINGS OF THE 3RD RESPONDENT DATED 12.12.2018.
EXHIBIT P1 TRUE COPY OF THE AGREEMENT DATED 06.03.2015 ALONG WITH FORWARDING LETTER.
EXHIBIT P3 TRUE COPY OF THE 4TH RESPONDENTS LETTER DATED 01.09.2016.
EXHIBIT P12 TRUE COPY OF THE FORWARDING LETTER DATED 06.09.2019.
EXHIBIT P11 TRUE COPY OF THE EXPLANATION DATED 26.08.2019.
EXHIBIT P10 TRUE COPY OF THE 3RD RESPONDENTS NOTICE OF TERMINATION DATED 05.09.2019.
WPC 11793/22 & 30034/19
APPENDIX OF WP(C) 11793/2022
PETITIONER EXHIBITS Exhibit P1 TRUE COPY OF THE INTIMATION NO.A1-385/2017 DATED 4/5/2021, ISSUED BY THE 3RD RESPONDENT.
Exhibit P2 TRUE COPY OF THE NOTICE NO.KFC/ALP/612/21- 22 DATED 9/3/2022 ISSUED BY THE 4TH RESPONDENT, TO THE PETITIONER.
RESPONDENT EXHIBITS Exhibit R1(d) A True copy of the relevant pages of Kerala PWD manual ,Clause 2116.2.1.
Exhibit R1(a) True copy of the Power of Attorney documents.
Exhibit R1(b) A True copy of the relevant page of Kerala PWD Manual ,Clause 2008 Exhibit R1(c) A true copy of the letter dated 30.09.2021 from the Law Officer , Irrigation and Administration Thiruvananthapuram PETITIONER EXHIBITS Exhibit P3 TRUE COPY OF THE REVENUE RECOVERY NOTICE DATED 09-11-2023 ISSUED BY THE 3RD RESPONDENT
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!