Monday, 11, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Vadavucode - Puthencruz Grama ... vs Deputy Tahsildar, Revenue Recovery
2024 Latest Caselaw 5011 Ker

Citation : 2024 Latest Caselaw 5011 Ker
Judgement Date : 15 February, 2024

Kerala High Court

Vadavucode - Puthencruz Grama ... vs Deputy Tahsildar, Revenue Recovery on 15 February, 2024

Author: P Gopinath

Bench: P Gopinath

                IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                PRESENT
                 THE HONOURABLE MR. JUSTICE GOPINATH P.
    THURSDAY, THE 15TH DAY OF FEBRUARY 2024 / 26TH MAGHA, 1945
                         WP(C) NO. 3702 OF 2015
PETITIONER/S:

          VADAVUCODE - PUTHENCRUZ GRAMA PANCHAYAT
          PUTHENCRUZ P.O., ERNAKULAM DISTRICT, REP. BY ITS
          SECRETARY.

          BY ADV K.S.ARUN KUMAR



RESPONDENT/S:

    1     DEPUTY TAHSILDAR, REVENUE RECOVERY
          TALUK OFFICE, KUNNATHUNADU, AT PERUMBAVOOR, PIN-683
          542.

    2     GREATER COCHIN DEVELOPMENT AUTHORITY
          KADAVANTHRA, COCHIN-682020, REP. BY ITS SECRETARY.

          BY ADVS.
          SRI.M.K.THANKAPPAN, SC, GCDA
          SRI. VENUGOPAL V., GOVT. PLEADER



     THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
15.02.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 W.P (C) No.3702/2015                 -2-

                              JUDGMENT

This writ petition has been filed challenging revenue recovery

proceedings initiated against the petitioner for recovery of an amount of

Rs.1,94,939/- together with interest @ 12.5% from 04-04-2012 upon a

requisition initiated by the 2nd respondent namely the Greater Cochin

Development Authority (GCDA).

2. The brief facts are that the petitioner, a Grama Panchayat had

entered into Ext.P2 agreement with the 2 nd respondent for construction of a

Mini Civil Station. Allegedly owing to delay in payment of amounts due, the

2nd respondent was required to make payments out of its own fund to

contractors etc. According to the 2 nd respondent any loss caused to the 2 nd

respondent owing to default by the petitioner is recoverable from the

petitioner. The amount demanded is stated to be interest calculated on

amounts paid belatedly.

3. The learned counsel appearing for the petitioner would submit

that there is no clause in Ext.P2 agreement for the levy of interest. It is

submitted that in the absence of any such clause in Ext.P2 agreement and

since parties were in a contractual relationship, the 2 nd respondent cannot

unilaterally determine for itself that certain amounts are payable by the

petitioner towards interest and to seek to recover the same by resorting to

revenue recovery proceedings. Reliance is placed in this regard on a Division

Bench decision of this court in Sriram Engineering Construction Co.

Ltd. v. Kerala State Industrial Development Corporation; (2007

(2) KLT 388).

4. The learned counsel for the 2nd respondent would vehementally

contend that the petitioner cannot dispute the liability to pay the amount

demanded as there was a clear breach of obligations of the petitioner. It is

submitted that Ext.P2 agreement clearly stipulates that all loss suffered by the

2nd respondent owing to any breach by the petitioner can be recovered from

the petitioner. It is submitted that since the amounts now demanded cannot

be disputed, the ratio of the decision in Sriram Engineering

Construction Co. Ltd. (supra) may not apply to the facts and

circumstances of the case.

5. The learned Government Pleader points out that even while there

is a challenge in the writ petition to the revenue recovery proceedings, there is

no challenge in the writ petition to Ext.P5 which is the demand raised by the

2nd respondent for payment of the amount. Learned Government Pleader also

points out that the judgment of Sriram Engineering Construction Co.

Ltd. (supra) has been declared per incuriam in the judgment of this court in

Premanandan K. v. State of Kerala and others; [2020 (3) KHC 719].

6. Having heard the learned counsel for the petitioner, learned

Government Pleader and the learned standing counsel appearing for the 2 nd

respondent, I am of view that the petitioner is entitled to succeed. The issue

appears to be covered in favour of the petitioner by virtue of the Division

Bench judgment of this court in Sriram Engineering Construction Co.

Ltd. (supra). The petitioner and the 2nd respondent were in a contractual

relationship. While it is the case of the petitioner that no amount of interest

was payable by the petitioner, the 2nd respondent asserts that since the

petitioner is liable to make good any loss suffered by the 2 nd respondent, the

petitioner is liable to pay interest on belated payments. An identical issue

appears to have gained the attention of Division Bench of this court in

Sriram Engineering Construction Co. Ltd. (supra), it was held;

"Disputed amounts not settled or adjudicated cannot be recovered by the proceedings under Revenue Recovery Act. Ext.P2 is not a statutory contract. Respondents can realise disputed amount only by adjudication and in the absence of clause for arbitration the only remedy available is to file a suit or file a counter claim in the pending suit. In this case, the Managing Director did not decide the question of damages payable from KSIDC as mentioned under Clause 34 after notice and adjudication. Ext.P12 is a decision from Chief Engineer. Clause 34 cannot be treated as an arbitration clause. When petitioner's claim for damages to the tune of Rs.43 lakhs was rejected under Clause 34, petitioner, treating it as arbitration award, filed petition to set aside the award and KSIDC itself contended that Clause 34 cannot be equated to arbitration and Ext.P11 decision of Managing Director is not amounting to arbitration award. Here, breach of contract is not admitted and petitioner contended that termination of contract by KSIDC is illegal and suit for recovering damages is pending."

In the light of the law laid down by a Division Bench of this court, this writ

petition is liable to be allowed. Contention taken by the learned Government

Pleader that Ext.P5 order has not been challenged need not detain this court

as Ext.P5 is only a demand following which revenue recovery proceedings

were initiated against the petitioner. The petitioner is only challenging the

initiation of revenue recovery proceedings and therefore even if the demand is

not challenged, in the light of law laid down by this court in Sriram

Engineering Construction Co. Ltd. (supra)., the revenue recovery

proceedings can be quashed. This court in Premanandan (supra) has held

that the decision in Sriram Engineering Construction Co. Ltd. is not

applicable as the facts are completely different. Though there is also an

observation that the said judgment is per incuriam, there is no finding

contrary to the law laid down in Sriram Engineering Construction Co.

Ltd. Accordingly this writ petition is allowed. Ext.P1 will stand quashed. If

the 2nd respondent wishes to claim the amount by filing a suit, the period

during which this writ petition was pending before this court along with the

stay against recovery proceedings [i.e., from 04-02-2015 till 15-02-2024] will

stand excluded, for the purposes of determining any period of limitation for

filing such suit.

Sd/-

GOPINATH P. JUDGE

AMG

APPENDIX OF WP(C) 3702/2015

PETITIONER EXHIBITS

P1 : TRUE COPY OF THE REVENUE RECOVERY NOTICE BEARING NO.B6- 2012/91039/7 DATED 01-12-2014 ISSUED BY THE 1ST RESPONDENT.

P2 : TRUE COPY OF THE AGREEMENT DATED 31-12-2007 EXECUTED BY G.C.D.A.

P3 : TRUE COPY OF THE REPORT OF THE ASST. ENGINEER OF THE PANCHAYAT.

P4 : TRUE COPY OF THE LETTER DATED 06-02-2012 BY THE PETITIONER'S SECRETARY TO 2ND RESPONDENT'S SECRETARY.

P5 : TRUE COPY OF THE LETTER DATED 19-04-2012 BY THE 2ND RESPONDENT'S SECRETARY TO THE PETITONER'S SECRETARY.

P6 : TRUE COPY OF THE DECISION NO.III/(25) DATED 23-04-2012 OF THE PETITIONER PANCHAYAT.

P7 : TRUE COPY OF THE OBJECTION SUBMITTED BY THE PETITIONER'S SECRETARY AGAINST THE DEMAND NOTICE DATED 14-01-2015.

RESPONDENT EXHIBITS

Exhibit R 2(a) TRUE COPY OF THE LETTER NO. 6164/I.A3/13/LSGD DATED 26-05-2015

Exhibit R2(b) TRUE COPY OF THE LETTER NO. 5814/E2/2006/GCDA DATED 3-06-2015 TO THE DISTRICT COLLECTOR, ERNAKULAM

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter