Citation : 2024 Latest Caselaw 23013 Ker
Judgement Date : 1 August, 2024
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE P.M.MANOJ
THURSDAY, THE 1ST DAY OF AUGUST 2024 / 10TH SRAVANA, 1946
WP(C) NO. 33709 OF 2014
PETITIONER:
PRECIOUS INFRAPROJECTS PVT.LTD.
AGED 40 YEARS
10/815/16, ST.LOUIS COMMERCIAL COMPLEX,
CHURCHCIRCLE, THRISSUR, PINCODE - 680001.
REPRESENTEDBY ITS MANAGING DIRECTOR, LEO LOUIS.
BY ADV SRI.RAJIT
RESPONDENTS:
1 THE BANKING OMBUDSMAN
O/O.THE BANKING OMBUDSMAN (KERALA, UNION
TERRITORYOF LAKSHADWEEP AND MAHI), RESERVE BANK OF
INDIA,BAKERY JUNCTION, TRIVANDRUM - 695 033.
2 BANK OF INDIA
ERNAKULAM MID-CORPORATE BRANCH, MANAVALAN
BUILDING,SUBHASH CHANDRA BOSE ROAD, VYTTILA,
COCHIN -682 019, REPRESENTED BY GENERAL MANAGER.
BY ADV SRI.ABRAHAM P.GEORGE, SC, BANK OF INDIA
THIS WRIT PETITION (CIVIL) HAVING BEEN FINALLY
HEARD ON 01.08.2024, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
2
W.P.(C) No.33709 of 2014
JUDGMENT
Dated this the 01st day of August, 2024
The petitioner has availed a loan of Rs.10 crores for the completion
of a construction project. As per Ext.P2, there are terms of agreement
with respect to the loan. Accordingly, the rate of interest was fixed at the
rate of 16.5% per annum. The term for repayment of loan was decided as
102 equal monthly instalments at the rate of 0.18 Crores. The repayment
commences from October 2013 onwards. This was on the basis of
moratorium agreed by the bank for a period of six months after the
completion of project in March 2013. It is stated, there was no condition
that the bank will levy any charge for pre-closure of loan. According to the
petitioner, the bank assured that rate of interest would be lowered on
progress of the project and the petitioner insisted for an option of pre-
closure without levying any charge, in case the bank refuses to lower the
interest rate as agreed. As per Ext.P2 agreement, it is stated that the
petitioner is not liable to pay the pre-closure charges in the event the
petitioner finds the bank is going back on agreed understanding of
lowering the rate of interest.
2. After the sanctioning of loan of Rs.10 crores, the petitioner
proceeded with the project and they were able to find tenants, who are
willing to pay monthly rent for Rs.30 lakhs for the building. Therefore, the
petitioner requested to change the credit facility to rent discounting
scheme for an amount of Rs.15 crores and also requested to lower the rate
of interest as agreed in between the petitioner and the respondent bank
while availing the loan. It is also pointed out by the petitioner that they
already obtained offers from other banks for taking over the loan at the
interest rate of 11.25%. In contrary to the terms agreed as per Ext.P2, the
2nd respondent refused to lower the interest rate and demanded an amount
of Rs.42,50,000/- towards the prepayment charges, which was calculated
at the rate of 0.50% of the entire loan amount. The same has been
communicated as per Ext.P4.
3. Since the 2nd respondent bank stepped away from the agreed
terms, finding no other way, petitioner has shifted the loan account from
the 2nd respondent bank to other banks, wherein the petitioner offered
better rate of interest at 11.25%. Thereafter, the petitioner informed the
2nd respondent bank that they are not liable and willing to pay the pre-
closure charge of Rs.42,50,000/-. This was refuted by the bank and
informed that the closure of the loan and the release of the documents,
which are mortgaged to the bank can be done only when the petitioner is
remitting the amount as claimed in Ext.P4. It is also stated that any
further action would be taken only after getting sanction from the higher
authorities for waiver of the pre-closure charges. Accordingly, the petitioner
deposited the entire amount of Rs.11,50,41,547/- as demanded in Ext.P4.
This is only with an intention to avail the documents mortgaged by the
petitioner before the 2nd respondent, at the time of availing the term loan.
4. However, contrary to the understanding, an amount of
Rs.42,50,000/-, which is charged as pre-closure charges and which was
kept in suspense account, has been utilised by the bank without giving any
intimation to the petitioner on 13.11.2013. Under such circumstances, the
petitioner has preferred Ext.P5 representation and it is rejected as per
Ext.P6. Being aggrieved by that, the petitioner has preferred Ext.P7 before
the 1st respondent Ombudsman.
5. On receipt of Ext.P7, the 1st respondent issued notice to the 2nd
respondent only to answer the allegation raised in Ext.P7. Accordingly, the
2nd respondent has offered their explanation. However, without evaluating
the circumstances and the facts involved in this case, the 1 st respondent
has closed the complaint by pointing out that as per Clause 13(1)(a) of the
Banking Ombudsman Scheme, 2006, the 1 st respondent is unable to
intervene in the matter.
6. In response, the 2nd respondent bank has preferred a counter
affidavit, wherein it is reiterated that the loan was availed by the petitioner
for an amount of Rs.10 crores, with a repayment tenure of 102 monthly
instalments. The repayment of instalments at the rate of 0.18 crores,
which starts from October, 2013. The interest rate is fixed at 16.25% per
annum. It is also stated that the petitioner is well aware of the pre-closure
charges at the rate of 0.50% per annum on Rs.10 crores for the remaining
102 months on simple interest basis, which would amounts to
Rs.42,50,000/-. The petitioner took the decision to pre-close the loan while
the bank was in the process of reviewing the account of the petitioner with
better terms as requested by them.
7. I have heard Sri.Rajit, the learned counsel appearing for the
petitioner, Sri.Abraham P.George, the Standing Counsel appearing for the
2nd respondent.
8. On evaluating the contentions raised in the writ petition it appears
that Ext.P2 agreement does not provide any specific right with respect to
the pre-closure of the charges. In fact, the column pertains to pre-closure
was left blank. It is also discernible from pleadings that while availing the
loan itself, there was an agreed terms with respect to pre-closure of the
loan, if the bank is not ready and willing to grant a reduced rate of interest.
The repayment was not started as the bank has fixed a moratorium for a
period of six months after the completion of the project. The period of
repayment starts from October 2010. Even by that time, there is no
positive response from the 2nd respondent bank with respect to reduced
rate of interest. At that point of time, the petitioner obtained many offers
from other banks with reduced interest rate and this was intimated to the
2nd respondent bank.
9. However, there was no positive response from the 2 nd respondent-
bank. In order to avoid payment of interest, the petitioner accepted the
offers extended by the other bank and repaid the entire amount demanded
in Ext.P2 on 12.10.2013. At that point of time, the pre-closure charges,
which amounts at the rate of 0.50% per annum on Rs.10 crores, which
comes to Rs.42,50,000/- was kept in a suspense account. Later, without
notice to the petitioner, the amount was credited by the bank and utilised
towards the pre-closure charges. This is the circumstances in which the
petitioner preferred Ext.P7 complaint before the Ombudsman. On receipt
of Ext.P7 the Ombudsman sought explanation from the 2 nd respondent
Bank. On receipt of the reply from the part of the 2 nd respondent bank,
without assessing and ascertaining the dispute between the petitioner and
the bank, the Ombudsman has decided the matter through a cryptic order,
which is stated to be on the ground of Clause 13 (a) of the Banking
Ombudsman Scheme, 2006.
10. Clause 13(1)(a) of the Banking Ombudsman Scheme, 2006 reads
thus:
13. Rejection of the complaint.
(1) The Banking Ombudsman may reject a complaint at any
stage if it appears to him that the complaint made is;
(b) frivolous, vexatious, malafide or
(b) without any sufficient cause; or
xxxxx xxxxx xxxxxx
11. On a perusal of Ext.P9, it does not appear the Banking
Ombudsman has evaluated the complaint as frivolous, vexatious or
malafide and does not offer any specific reason for rejection except saying
that they are unable to proceed with the complaint in the light of clause
13(1)(a) of the scheme, 2006. Even then there was no opportunity of
hearing was offered to the petitioner. That itself shows that there is non
application of mind as well as violation of principles of natural justice. The
1st respondent, being an entity which is vested with the powers to decide
the dispute with the bank and its customer, without proper application of
mind and considering the real facts involved, has closed the complaint by
pointing out some frivolous reason. Hence, I am of the considered opinion
that Ext.P9 cannot stand the test of law.
12. Accordingly, Ext.P9 stands set aside. The 1 st respondent is
directed to reconsider the issue in the light of Ext.P2 agreement and
following the Banking Ombudsman Scheme, 2006, within a period of three
months from the date of receipt of a certified copy of this judgment.
Needless to say, while reconsidering the matter as directed above, an
opportunity shall be afforded to both sides.
The writ petition is disposed of as above.
sd/-
P.M.MANOJ JUDGE das
APPENDIX OF WP(C) 33709/2014
PETITIONER EXHIBITS EXT.P-1: A TRUE COPY OF THE SANCTION LETTER BEARING NO.EMCB/VVS/12-13/25 DTD 4.7.2012 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER EXT.P-2: A TRUE COPY OF THE HYPOTHECATION CUM LOAN AGREEMENT EXECUTED BETWEEN THE PETITIONER AND THE 2ND RESPONDENT EXT.P-3: A TRUE COPY OF LETTER DTD 21.9.2013 SUBMITTED BY THE PETITIONER BEFORE THE 2ND RESPONDENT EXT.P-4: A TRUE COPY OF THE EMAIL SENT BY THE 2ND RESPONDENT TO THE PETITIONER EXT.P-5: A TRUE COPY OF THE LETTER DTD 29.1.2014 SEND BY THE PETITIONER TO THE 2ND RESPONDENT EXT.P-6: A TRUE COPY OF THE LETTER BEARING NO.ERNMCV/VVS/2014-15/33 DTD 6.2.2014 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER EXT.P-7: A TRUE COPY OF THE COMPLAINT FILED BY THE PETITIONER BEFORE THE IST RESPONDENT EXT.P-8: A TRUE COPY OF THE REPLY FILED BY THE 2ND RESPONDENT BEFORE THE IST RESPONDENT EXT.P-9: A TRUE COPY OF THE LETTER BEARING NO.OBO(T)1212/CTS/000104/2014-15 DTD 27.8.2014
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!