P. Muraleedharan vs The Kerala State Co-Operative Bank
2024 Latest Caselaw 9910 Ker

Citation : 2024 Latest Caselaw 9910 Ker
Judgement Date : 5 April, 2024

Kerala High Court

P. Muraleedharan vs The Kerala State Co-Operative Bank on 5 April, 2024

Author: N.Nagaresh

Bench: N.Nagaresh

                 IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                  PRESENT
                   THE HONOURABLE MR.JUSTICE N.NAGARESH
         FRIDAY, THE 5TH DAY OF APRIL 2024 / 16TH CHAITHRA, 1946
                          WP(C) NO. 8800 OF 2024
PETITIONER:

              P. MURALEEDHARAN
              AGED 52 YEARS
              S/O. DIVAKARA MENON, ADVOCATE,
              PARANGODATH HOUSE, ARIMPUR P.O.,
              KAIPPILLY DESOM, VELUTHOOR VILLAGE,
              THRISSUR TALUK, THRISSUR DISTRICT.,
              PIN - 680620

              BY ADVS.
              K.A.MOHAMED HARIS
              ANEESA NAZAR
              K.M.SALIM


RESPONDENTS:

     1        THE KERALA STATE CO-OPERATIVE BANK,
              SAHAKARANA SADABDTHI MANDIRAM, KOVILAKATHUMPADAM,
              THIRUVAMBADY P.O., THRISSUR DISTRICT
              REPRESENTED BY ITS AUTHORISED OFFICER, PIN - 68002
     2        THE AUTHORISED OFFICER
              KERALA STATE CO-OPERATIVE BANK,
              SAHAKARANA SADABDTHI MANDIRAM, KOVILAKATHUMPADAM,
              THIRUVAMBADY P.O., THRISSUR DISTRICT.,
              PIN - 680022

              SRI.P.C.SASINDHARAN (STANDING COUNSEL)


     THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
05.04.2024, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C) No.8800 Of 2024
                               2


                         JUDGMENT

Dated this the 5th day of April, 2024

The petitioner has approached this Court aggrieved by

the coercive proceedings for recovery of financial advance

made by the Kerala State Co-operative Bank Limited to the

petitioner, invoking the provisions of the Securitisation and

Reconstruction of Financial Assets and Enforcement of

Security Interest Act, 2002.

2. The Bank paid ₹26.5 lakhs to the petitioner as

Simple Loan in the year 2017. The petitioner states that

though the petitioner made remittances promptly during the

initial repayment period of the financial advance, he could not

pay the repayment installments promptly later due to Covid-19

pandemic. The repayment of loan fell into arrears. It

happened due to reasons beyond the control of the petitioner. WP(C) No.8800 Of 2024

3. Though the petitioner requested the Bank to permit

the petitioner to repay the overdue amounts in easy monthly

installments, the Bank authorities were not yielding. The

authorities, instead started coercive proceedings invoking the

provisions of the Securitisation and Reconstruction of

Financial Assets and Enforcement of Security Interest Act,

2002 and the Security Interest (Enforcement) Rules, 2002 and

issued Ext.P8 notice.

4. The petitioner states that he is still in a position to

clear the overdue amounts towards the loan, if sufficient time

is given to clear the dues in easy monthly installments. If the

respondents are permitted to continue with the coercive

proceedings and auction the secured assets provided by the

petitioner, he will be put to untold hardship and loss.

5. Standing Counsel entered appearance on behalf of

the Bank and denied all the statements made by the

petitioner. On behalf of the respondents, it is submitted that

the loan was given to the petitioner in the year 2017. The WP(C) No.8800 Of 2024

petitioner committed default in repaying the loan.

6. The Bank repeatedly reminded the petitioner and

required him to clear the dues. The petitioner deliberately

omitted to do so. In the circumstances, the Bank had no other

go than to proceed against the petitioner invoking the

provisions of the Securitisation and Reconstruction of

Financial Assets and Enforcement of Security Interest Act,

2002. The impugned Ext.P8 notice was issued in these

circumstances. The petitioner has not advanced any legal

reasons to thwart the coercive proceedings initiated by the

Bank.

7. The Standing Counsel, however, submitted that if

the petitioner is ready and willing to make a substantial

payment soon and remit the balance overdue amount

immediately thereafter, a short breathing time can be granted

to the petitioner to clear the dues. The Standing Counsel

submitted that the outstanding amount due to the Bank from

the petitioner as on 05.04.2024 is ₹40,08,367/- and the WP(C) No.8800 Of 2024

overdue amount as on 05.04.2024 is ₹22,03,822/-.

8. I have heard the counsel for the petitioner and the

Standing Counsel representing the Bank.

9. The specific case of the petitioner is that the

petitioner has been making the repayment and maintaining

the loan account initially. The default in repayment of the loan

occurred lately due to reasons beyond the control of the

petitioner. The petitioner has provided substantial security

which will safeguard the interest of the Bank.

10. In the facts and circumstances of the case, I am

inclined to dispose of the writ petition giving a short and

reasonable time to the petitioner to clear off the liability.

11. The writ petition is therefore disposed of with the

following directions:

(i) The petitioner shall remit the overdue

amount of ₹22,03,822/- in 12 consecutive

and equal monthly installments along with

accruing interest and other Bank charges, if WP(C) No.8800 Of 2024

any. First of such installments shall be paid

on or before 06.05.2024.

(ii) If the petitioner commits default in

making payments as directed above, the

respondent will be at liberty to continue with

the coercive proceedings against the

petitioner in accordance with law.

(iii) The petitioner shall also pay current

EMIs along with the aforesaid payments.

(iv) If the petitioner makes payments as

directed above, coercive proceedings, if any,

against the petitioner shall stand deferred.

Sd/-

N.NAGARESH JUDGE hmh WP(C) No.8800 Of 2024

APPENDIX OF WP(C) 8800/2024

PETITIONER EXHIBITS

Exhibit P1 TRUE COPY OF THE RELEVANT PAGES OF THE LOAN ACCOUNT PASS BOOK AND THE REPAYMENT STATEMENT OF THE PETITIONER Exhibit P2 TRUE COPY OF THE CIRCULAR DATED 27TH MARCH 2020, TAKEN FROM WEBSITE OF RBI Exhibit P3 TRUE COPY OF THE CIRCULAR DATED 23RD MAY 2020, TAKEN FROM WEBSITE OF RBI Exhibit P4 TRUE COPY OF THE RESOLUTION FRAME WORK 1.0 -DATED 6THAUGUST 2020, TAKEN FROM WEBSITE OF RBI Exhibit P5 TRUE COPY OF THE RESOLUTION FRAME WORK 2.0 -DATED 5TH MAY 2021, TAKEN FROM WEBSITE OF RBI.

Exhibit P6 TRUE COPY OF THE DEMAND NOTICE ISSUED BY THE BANK DATED 27.11.2018 (RECEIVED DURING DECEMBER 2018) Exhibit P7 TRUE COPY OF THE 13(4) NOTICE ISSUED BY THE 1ST RESPONDENT BANK DATED 04.03.2020 (SERVED DURING APRIL 2020) Exhibit P8 . TRUE COPY OF THE NOTICE ISSUED TO THE PETITIONER BY THE ADVOCATE COMMISSIONER DATED 10.12.2023 IN CRL. M.P. NO.5905 OF 2023

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter