Sunday, 19, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Avarachan M.P vs Power Grid Corporation Of India Ltd
2024 Latest Caselaw 11408 Ker

Citation : 2024 Latest Caselaw 11408 Ker
Judgement Date : 23 April, 2024

Kerala High Court

Avarachan M.P vs Power Grid Corporation Of India Ltd on 23 April, 2024

Author: V.G.Arun

Bench: V.G.Arun

             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                              PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
   TUESDAY, THE 23RD DAY OF APRIL 2024 / 3RD VAISAKHA, 1946
                        CRP NO. 358 OF 2021
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.904 OF 2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

            AVARACHAN M.P.
            AGED 58 YEARS
            S/O. PAILY PILLA, MAMBAKKATTU HOUSE, KAMMANODE,
            PATTIMATTOM VILLAGE, KUNNATHUNADU TALUK, ERNAKULAM
            DISTRICT
            BY ADVS.
            P.T.JOSE
            S.ASHITHA


RESPONDENT/S:

    1       POWER GRID CORPORATION OF INDIA LTD.
            CONSTRUCTION AREA OFFICE, KAKKANAD, NOW IN
            PAO/400,220 KV SUB STATION, KUMANRAPURAM P.O.,
            PALLIKARA, KOCHI-682 303, REP BY DEPUTY MANAGER
    2       THE SPECIAL TAHSILDAR (LA),
            POWER GRID CORPORATION OF INDIA LTD, CHEVARAMBALAM,
            KOZHIKODE, NOW IN KAKKANAD P.O-682 030
    3       STATE OF KERALA,
            REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI-
            682 021
    4       KERALA STATION ELECTRICITY BOARD,
            REPRESENTED BY CHAIRMAN AND MANAGING DIRECTOR, KSEB
            LTD, THIRUVANANTHAPURAM-695 001
            BY ADV ROJO JOSEPH


OTHER PRESENT:

            GP JIBU T.S.SC FOR KSEB B.PREMOD; ADV.PRAVEEN K.JOY
            FOR POWERGRID


        THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
19.01.2024, ALONG WITH CRP.238/2021, THE COURT ON 23.04.2024
DELIVERED THE FOLLOWING:
 CRP Nos.358 of 2021 and 238 of 2021

                                 -2-



              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
    TUESDAY, THE 23RD DAY OF APRIL 2024 / 3RD VAISAKHA, 1946
                         CRP NO. 238 OF 2021
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.904 OF 2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

             POWER GRID CORPORATION OF INDIA LTD.,
             CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
             PALLIKKARA, COCHIN 682 030.
             BY ADV ROJO J.THURUTHIPARA


RESPONDENT/S:

     1       AVARACHAN M.P.,
             AGED 58 YEARS
             S/O. PAILY PILLA, MAMBAKKATTU HOUSE, KUMMANODE,
             PATTIMATTOM VILLAGE, KUNNATHUNADU TALUK, ERNAKULAM
             DT. 683 562.
     2       THE SPECIAL TAHSILDAR (LA),
             POWER GRID CORPORATION OF INDIA LTD., CHEVARAMBALAM,
             KOZHIKODE 673 017.
     3       THE STATE OF KERALA,
             REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI
             682 030.
     4       THE KERALA STATE ELECTRICITY BOARD
             REPRESENTED BY ITS CHAIRMAN AND MANAGING DIRECTOR,
             KSEB, THIRUVANANTHAPURAM-695 001
             BY ADVS.
             P.T.JOSE
             S.ASHITHA


         THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
19.01.2024, ALONG WITH CRP.358/2021, THE COURT ON 23.04.2024
DELIVERED THE FOLLOWING:
 CRP Nos.358 of 2021 and 238 of 2021

                                 -3-



                              ORDER

Dated this the 23rd day of April, 2024

These revision petitions are filed

challenging the order passed by the Additional

District Judge-VI, Ernakulam in O.P.(Electricity)

No.904 of 2013. The original petition was filed

by the revision petitioner in CRP No.358 of 2021

(hereinafter called 'the claimant'), being

dissatisfied with the compensation awarded

towards the damage and loss sustained due to the

drawing of 400 KV lines across his property by

the Power Grid Corporation of India Ltd

(hereinafter called 'the Corporation'). The

essential facts are as under;

The claimant is in ownership and possession

of landed property having an extent of 25.91 Ares

in Resurvey No.514/10/3 of Pattimattam Village in

Kunnathunadu Taluk. The land was cultivated with

various yielding and non-yielding trees.

According to the claimant, to facilitate drawing CRP Nos.358 of 2021 and 238 of 2021

of the lines and smooth transmission of power,

large number of trees were cut from his property.

The drawing of high tension lines rendered the

land underneath and adjacent to the lines

useless, resulting in diminution of the value of

the property. In spite of the huge loss suffered

by the claimant, only an amount of Rs.2,10,540/-

was paid as compensation towards the value of

yielding and non-yielding trees cut.

Surprisingly, no compensation was granted for

diminution in land value. Hence, the original

petition was filed, seeking enhanced compensation

towards the value of trees cut and diminution in

land value.

2. The court below allowed the claim for

enhanced compensation for the value of trees cut

by awarding 50% of the compensation already

granted by the Corporation. Thus, the claimant

was found entitled for Rs.1,05,270/- towards the

value of trees cut. As far as the claim for

enhanced compensation towards diminution in land CRP Nos.358 of 2021 and 238 of 2021

value is concerned, the court below relied on

Ext.A5 document as well as Exts.C1 and C1(a)

commission report and sketch. The court below has

took note of the fact that the petition schedule

property is situated at a distance of 200 metres

from Perumbavoor-Puthencruz road and 150 metres

from Periyar Valley road. Moreover, LP School,

Anganavadi and Temple are situated on the

northern side of the petition schedule property.

It is also reported by the Commissioner that a

road that starts from the canal bund road passes

through the northern side of the petition

schedule property and a lot of reputed

institutions are situated within a radius of a

150 metres. Based on the said factors and also

considering the fact that there is no direct

public road access to the petition schedule

property, the court below fixed the land value of

the claimant's property at Rs.1,89,695/- per

cent, by deducting 10% of the land value of the

property involved in Ext.A5 document. Relying on CRP Nos.358 of 2021 and 238 of 2021

Ext.C1(a) sketch, the extent of central corridor

was held to be 17.960 cents and that of the outer

corridor, 37.410 cents. For the central corridor,

40% of the land value was granted as compensation

and for the outer corridor, 20% of the land

value. Accordingly, the claimant was found

entitled to compensation of Rs.27,82,065/-

towards diminution in land value. Dissatisfied

with the quantum of enhancement, the claimant has

filed CRP No.358 of 2021, whereas the Corporation

has filed CRP No.238 of 2021 contending that the

enhancement ordered is far in excess of the

actual damage sustained.

3. Heard Adv.P.T.Jose for the claimant and

Adv.Rojo Joseph for the Corporation.

4. Learned Counsel for the claimant

contended that the court below committed gross

illegality in granting only 50% of the amount

already paid as enhanced compensation for the

loss sustained due to the cutting of valuable

trees, in spite of the Advocate Commissioner CRP Nos.358 of 2021 and 238 of 2021

assessing and reporting the loss. It is submitted

that the petition schedule property is situated

at a distance of 200 metres from Perumbavoor-

Puthencruz road and 150 metres from Periyar

Valley road. Moreover, LP School, Anganavadi and

Temple are situated on the northern side of the

petition schedule property. It is also reported

by the Commissioner that a road that starts from

the canal bund road passes through the northern

side of the petition schedule property and a lot

of reputed institutions are situated within a

radius of a 150 metres. Without properly

considering these crucial factors, 10% deduction

was made from the value of the property involved

in Ext.A5 document.

5. It is submitted that the court below

grossly erred in granting only 40% of the land

value fixed for the central corridor and 20% for

the outer corridor. It is further submitted that

the court below is not justified in refusing to

grant anything towards the remaining property, CRP Nos.358 of 2021 and 238 of 2021

which is also affected due to the drawing of

electric lines. Considering the extent of damage

sustained and the diminution in land value

consequent to the drawing of lines, the court

below ought to have granted compensation as

claimed.

6. Learned Counsel for the Corporation

contended that, compensation towards the value of

trees cut and diminution in land value granted is

exorbitant and there is no rationale in granting

9% interest on that amount. The court below also

erred in relying on Ext.A5 for fixing the land

value of the claimant's property. As the drawing

of electric lines does not prohibit the landowner

from conducting agricultural activities and

putting up small structures, 40% of the land

value granted for the central corridor and 20%

for the outer corridor are exorbitant.

7. The court below had awarded 50% of the

compensation already granted as additional

compensation, based on the Commission report as CRP Nos.358 of 2021 and 238 of 2021

well as the Detailed Valuation Statement. A

careful scrutiny of the impugned order reveals

that the claim for enhancement of compensation

towards the value of trees cut was rightly

considered on the basis of available evidence

produced.

8. As far as the diminution in land value

is concerned, the factors to be taken into

consideration, as laid down in KSEB v. Livisha

[(2007) 6 SCC 792] are as under;

"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."

On careful scrutiny of the impugned order, it is CRP Nos.358 of 2021 and 238 of 2021

seen that the compensation was enhanced after

taking all the above factors into consideration.

The nature of the land, the cultivation therein,

and the manner in which the land was affected by

drawing of the lines are all seen considered for

fixing the land value as well as the percentage

of diminution. Based on the above factors and a

comparison of the petition schedule property with

the property involved in Ext.A5, the court below

has fixed the land value at Rs.1,89,695/- per

cent, viz, 10% less than the value shown in

Ext.A5 document, which according to me, is

reasonable. Similarly, discretion was properly

exercised by the court below in granting 40% of

the land value as compensation for the central

corridor and 20% for the outer corridor. The

court below has also rightly rejected the claim

towards the diminution of land value for the

remaining property, on finding that the electric

lines were drawn across the extreme southern side

of the property without affecting the remaining CRP Nos.358 of 2021 and 238 of 2021

portion of the petition schedule property.

9. The contention of the Corporation that

the Government having fixed the land value, the

court below could not have fixed a higher value

is liable to be rejected since, while assessing

the damage sustained and fixing the compensation,

the court is not bound by the guidelines/orders

issued by the Government. The contention that the

court below committed an illegality in awarding

9% interest cannot also be sustained in the light

of the decision of this Court in V.V. Jayaram v

Kerala State Electricity Board [2015 (3) KHC

453]. As such, there is no illegality or material

irregularity in the impugned order, warranting

intervention by this Court in exercise of the

revisional power under Section 115 of the Code of

Civil Procedure.

For the aforementioned reasons, the civil

revision petitions filed by the claimant as well

as the Corporation are dismissed. The enhanced CRP Nos.358 of 2021 and 238 of 2021

compensation fixed by the court below shall be

paid within three months of receipt of a copy of

this order. If any amount is deposited pursuant

to the order of this Court or otherwise, the same

shall forthwith be released to the claimant on

his filing appropriate application.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter