Sunday, 19, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

N.K.Madhavan Nair vs Power Grid Corporation Of India
2024 Latest Caselaw 11406 Ker

Citation : 2024 Latest Caselaw 11406 Ker
Judgement Date : 23 April, 2024

Kerala High Court

N.K.Madhavan Nair vs Power Grid Corporation Of India on 23 April, 2024

Author: V.G.Arun

Bench: V.G.Arun

             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                              PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
   TUESDAY, THE 23RD DAY OF APRIL 2024 / 3RD VAISAKHA, 1946
                        CRP NO. 387 OF 2021
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.64 OF 2015 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

            N.K.MADHAVAN NAIR
            AGED 63 YEARS
            S/O.PADMANABHAN NAIR, NEDUMPURATHU HOUSE,
            ELAMBAKAPILLY P.O., KOOVAPPADY, PERUMBAVOOR.
            BY ADV P.T.JOSE


RESPONDENT/S:

    1       POWER GRID CORPORATION OF INDIA
            CONSTRUCTION AREA OFFICE, KAKKANAD,NOW IN PAO/400,
            220KV SUBSTATION, KUMARAPURAM P.O., PALLIKARA, KOCHI
            - 682 303 REP. BY DEPUTY MANAGER.
    2       THE SPECIAL TAHSILDAR (L.A.)
            POWERGRID CORPORATION OF INDIA LTD., CHEVARAMBALAM,
            KOZHIKODE, NOW IN KAKKANAD P.O. - 682 030 NEAR CIVIL
            STATION.
    3       STATE OF KERALA
            REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI
            - 682 030.
    4       KERALA STATE ELECTRICITY BOARD
            REPRESENTED BY CHAIRMAN AND MANAGING DIRECTOR, KSEB
            LTD., THIRUVANANTHAPURAM - 695 001.
            BY ADV R.HARISHANKAR


OTHER PRESENT:

            sr.gp.v.tekchand; GP B.S.SYAMANTHAK sc for kseb
            a.arunkumar


        THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD
ON09.04.2024, ALONG WITH CRP.47/2022, THE COURT ON 23.04.2024
DELIVERED THE FOLLOWING:
 CRP Nos.387 of 2021 and 47 of 2022

                                 -2-




            IN THE HIGH COURT OF KERALA AT ERNAKULAM
                              PRESENT
                THE HONOURABLE MR.JUSTICE V.G.ARUN
    TUESDAY, THE 23RD DAY OF APRIL 2024 / 3RD VAISAKHA, 1946
                         CRP NO. 47 OF 2022
AGAINST THE ORDER/JUDGMENT DATED 12.02.2021 IN OPELE NO.64 OF
2015 OF VI ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

           POWER GRID CORPORATION OF INDIA
           CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
           KAKKANAD, COCHIN 682 030 PRESENTLY AT CONSTRUCTION
           AREA OFFICE, 400/220, KV SUB STATION, KUMARAPURAM
           P.O, PALLIKKARA, ERNAKULAM 683565 REPRESENTED BY ITS
           SENIOR GENERAL MANAGER
           BY ADV MILLU DANDAPANI


RESPONDENT/S:

     1     N.K.MADHAVAN NAIR
           AGED 70 YEARS
           S/O. PADMANABHAN NAIR, NEDUMPURATH HOUSE,
           ELAMBAKAPILLY P.O, KOOVAPPADY, PERUMBAVOOR 683544
     2     THE SPECIAL TAHSILDAR (LA),
           POWER GRID CORPORATION OF INDIA LTD, CHEVARAMBALAM
           PO, KOZHIKODE-673 017.
     3     STATE OF KERALA, REPRESNTED BY DISTRICT COLLECTOR
           STATE OF KERALA, REPRESENTED BY DISTRICT COLLECTOR,
           CIVIL STATION, KAKKANAD, ERNAKULAM, KOCHI-682 030.
     4     KERALA STATE ELECTRICITY BOARD, REPRESENTED BY
           CHAIRMAN & MANAGING DIRECTOR,
           KSEB LTD., VAIDYUTHI BHAVAN, PATTOM PO,
           THIRUVANANTHAPURAM-695 004.
     5     THE SPECIAL TAHSILDAR (LA)
           POWER GRID CORPORATION OF INDIA LTD, CHEVERAMBALAM
           P.O, KOZHIKODE 673 017
     6     STATE OF KERALA
           REPRESENTED BY DISTRICT COLLECTOR, CIVIL STATION,
           KAKKANAD ERNAKULAM KOCHI 682 030
     7     KERALA STATE ELECTRICITY BOARD - KSEB
 CRP Nos.387 of 2021 and 47 of 2022

                                 -3-


           REPRENTED BY CHAIRMAN AND MANAGING DIRECTOR, KSEB
           LTD, VAIDYUTHI BHAWAN, PATTOM P.O,
           THIRUVANANTHAPURAM 695 004
           BY ADVS.
           P.T.JOSE
           R.HARISHANKAR


      THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD
ON09.04.2024, ALONG WITH CRP.47/2022, THE COURT ON 23.04.2024
DELIVERED THE FOLLOWING:
 CRP Nos.387 of 2021 and 47 of 2022

                                 -4-



                              ORDER

Dated this the 23rd day of April, 2024

These revision petitions are filed

challenging the order passed by the Additional

District Judge-VI, Ernakulam in O.P.(Electricity)

No.64 of 2015. The original petition was filed by

the revision petitioner in CRP No.387 of 2021

(hereinafter called 'the claimant'), being

dissatisfied with the compensation awarded

towards the damage and loss sustained due to the

drawing of 400 KV lines across his property by

the Power Grid Corporation of India Ltd

(hereinafter called 'the Corporation'). The

essential facts are as under;

The claimant is in ownership and possession

of landed property having an extent of 40.4 Ares

in Resurvey No.379/3/1 of Koovappady Village in

Kunnathunadu Taluk. The land was cultivated with

various yielding and non-yielding trees. CRP Nos.387 of 2021 and 47 of 2022

According to the claimant, to facilitate drawing

of the lines and smooth transmission of power,

large number of trees were cut from his property.

The drawing of high tension lines rendered the

land underneath and adjacent to the lines

useless, resulting in diminution of the value of

the property. In spite of the huge loss suffered

by the claimant, only an amount of Rs.1,47,760/-

was paid as compensation towards the value of

yielding and non-yielding trees cut.

Surprisingly, no compensation was granted for

diminution in land value. Hence, the original

petition was filed, seeking enhanced compensation

towards the value of trees cut and diminution in

land value.

2. The court below allowed the claim for

enhanced compensation for the value of trees cut

by awarding 50% of the compensation already

granted by the Corporation. Thus, the claimant

was found entitled for Rs.73,380/- towards the

value of trees cut. As far as the claim for CRP Nos.387 of 2021 and 47 of 2022

enhanced compensation towards diminution in land

value is concerned, the court below relied on

Ext.A4 document as well as Exts.C3 and C3(a)

commission report and plan. The Advocate

Commissioner reported that the petition schedule

property is situated on the southern side of the

Korumbaserry road. The court below took note of

the fact that Ext.A4 document was executed one

year after the trees were cut and removed from

the claimant's property. Based on the said

factors, the court below fixed the land value of

the claimant's property at Rs.1,53,000/- per

cent, by deducting 10% of the land value of the

property involved in Ext.A4 document. Relying on

Ext.C3(a) plan, the court below found that no

electric lines were drawn across the claimant's

property and only the outer corridor admeasuring

9.983 cents passes through the side of the

property. For the outer corridor, 20% of the

land value was granted as compensation. The court

below also took note of the fact that, the outer CRP Nos.387 of 2021 and 47 of 2022

corridor passes through the side of the property

without affecting the remaining petition schedule

property. Accordingly, the claimant was found

entitled to compensation of Rs.3,05,479/- towards

diminution in land value. Dissatisfied with the

quantum of enhancement, the claimant has filed

CRP No.387 of 2021, whereas the Corporation has

filed CRP No.47 of 2022 contending that the

enhancement ordered is far in excess of the

actual damage sustained.

3. Heard Adv.P.T.Jose for the claimant and

Adv.Millu Dandapani for the Corporation.

4. Learned Counsel for the claimant

contended that the court below committed gross

illegality in granting only 50% of the amount

already paid as enhanced compensation for the

loss sustained due to the cutting of valuable

trees, in spite of the Advocate Commissioner

assessing and reporting the loss. It is submitted

that the claimant's property is situated on the

southern side of the Korumbassery road. Without CRP Nos.387 of 2021 and 47 of 2022

properly considering this crucial factor, the

land value of the property is fixed as only

Rs.1,53,000/- per cent.

5. It is further submitted that the court

below grossly erred in granting only 20% of the

land value for the outer corridor and refusing to

grant anything towards the remaining property.

Considering the extent of damage sustained and

the diminution in land value consequent to the

drawing of lines, the court below ought to have

granted compensation as claimed.

6. Learned Counsel for the Corporation

contended that, compensation towards the value of

trees cut and diminution in land value granted is

exorbitant and there is no rationale in granting

9% interest on that amount. The court below also

erred in relying on Ext.A4 for fixing the land

value of the claimant's property. As no electric

lines were drawn across the petition schedule

property and there is no prohibition on the

landowner from conducting agricultural activities CRP Nos.387 of 2021 and 47 of 2022

and putting up small structures, 20% of land

value granted for the outer corridor is

exorbitant.

7. The court below had awarded 50% of the

compensation already granted as additional

compensation, based on the commission report as

well as the detailed valuation statement. A

careful scrutiny of the impugned order reveals

that the claim for enhancement of compensation

towards the value of trees cut was rightly

considered on the basis of available evidence

produced.

8. As far as the diminution in land value

is concerned, the factors to be taken into

consideration, as laid down in KSEB v. Livisha

[(2007) 6 SCC 792] are as under;

"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other CRP Nos.387 of 2021 and 47 of 2022

similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."

On careful scrutiny of the impugned order, it is

seen that the compensation was enhanced after

taking all the above factors into consideration.

The nature of the land, the cultivation therein,

and the manner in which the land was affected by

drawing of the lines are all seen considered for

fixing the land value as well as the percentage

of diminution. The court below has fixed the land

value at Rs.1,53,000/-, taking into account the

fact that Ext.A4 document was executed one year

after the trees were cut and removed from the

claimant's property, which according to me, is

reasonable. The discretion was properly exercised

in granting 20% of the land value as compensation

for the outer corridor. The claim for

compensation towards remaining property was also CRP Nos.387 of 2021 and 47 of 2022

rightly rejected, on finding that the outer

corridor passes through a side of the property

without affecting the remaining portion.

9. The contention of the Corporation that

the Government having fixed the fair value, the

court below could not have fixed a higher value

is liable to be rejected since, while assessing

the damage sustained and fixing the compensation,

the court is not bound by the guidelines/orders

issued by the Government. The contention that the

court below committed an illegality in awarding

9% interest cannot also be sustained in the light

of the decision of this Court in V.V. Jayaram v

Kerala State Electricity Board [2015 (3) KHC

453]. As such, there is no illegality or material

irregularity in the impugned order, warranting

intervention by this Court in exercise of the

revisional power under Section 115 of the Code of

Civil Procedure.

For the aforementioned reasons, the civil CRP Nos.387 of 2021 and 47 of 2022

revision petitions filed by the claimant as well

as the Corporation are dismissed. The enhanced

compensation fixed by the court below shall be

paid within three months of receipt of a copy of

this order. If any amount is deposited pursuant

to the order of this Court or otherwise, the same

shall forthwith be released to the claimant on

his filing appropriate application.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter