Sunday, 19, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

T.T.Xavier vs Power Grid Corporation Of India Ltd
2024 Latest Caselaw 11404 Ker

Citation : 2024 Latest Caselaw 11404 Ker
Judgement Date : 23 April, 2024

Kerala High Court

T.T.Xavier vs Power Grid Corporation Of India Ltd on 23 April, 2024

Author: V.G.Arun

Bench: V.G.Arun

             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                              PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
   TUESDAY, THE 23RD DAY OF APRIL 2024 / 3RD VAISAKHA, 1946
                        CRP NO. 399 OF 2021
AGAINST THE ORDER/JUDGMENT DATED 31.03.2021 IN OPELE NO.621 OF
2013 OF VI ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

            T.T.XAVIER
            AGED 64 YEARS
            S/O.THOMA, THELAKKATTU HOUSE, CHERANALLOOR,
            KOOVAPPADY VILLAGE, KUNNATHUNAD TALUK, ERNAKULAM
            DISTRICT - 683 544.
            BY ADV P.T.JOSE


RESPONDENT/S:

    1       POWER GRID CORPORATION OF INDIA LTD.
            CONSTRUCTION AREA OFFICE, KAKKANAD,NOW IN PAO/400,
            220KV SUBSTATION, KUMARAPURAM P.O., PALLIKKARA,
            KOCHI - 682 303 REP. BY DEPUTY MANAGER.
    2       THE SPECIAL TAHSILDAR (L.A.)
            POWERGRID CORPORATION OF INDIA LTD., CHEVARAMBALAM,
            KOZHIKKODE - 673 017 NOW IN THRIKKAKARA VILLAGE,
            KANAYANNOOR TALUK, KAKKANAD P.O. - 682 030.
    3       STATE OF KERALA
            REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI
            - 682 030.
    4       KERALA STATE ELECTRICITY BOARD
            REPRESENTED BY CHAIRMAN AND MANAGING DIRECTOR, KSEB
            LTD., THIRUVANANTHAPURAM - 695 001.
            BY ADV R.HARISHANKAR


OTHER PRESENT:

            GP B.S.SYAMANTHAK;GP JIBU T.S. SC FOR KSEB
            A.ARUNKUMAR


        THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
19.01.2024, ALONG WITH CRP.177/2022, THE COURT ON 23.04.2024
DELIVERED THE FOLLOWING:
 CRP Nos.399 of 2021 and 177 of 2022

                                 -2-




              IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
                 THE HONOURABLE MR.JUSTICE V.G.ARUN
    TUESDAY, THE 23RD DAY OF APRIL 2024 / 3RD VAISAKHA, 1946
                         CRP NO. 177 OF 2022
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.621 OF 2013 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:

             POWER GRID CORPORATION OF INDIA
             CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
             KAKKANAD, COCHIN - 682 030, PRESENTLY AT
             CONSTRUCTION AREA OFFICE, 400/220, KV SUB STATION,
             KUMARAPURAM P.O, PALLIKKARA, ERNAKULAM , REPRESENTED
             BY ITS SENIOR GENERAL MANAGER, PIN - 683565
             BY ADV MILLU DANDAPANI


RESPONDENT/S:

     1       T T XAVIER
             S/O. THOMA, AGED 57 YEARS, THELAKKATTU HOUSE,
             CHERANALLOOR, KOOVAPPADY VILLAGE, KUNNATHUNAD
             TALUK., PIN - 683544
     2       THE SPECIAL TAHSILDAR (LA)
             POWER GRID CORPORATION OF INDIA LTD. CHEVARAMBALAM,
             KOZHIKODE - 673 017, PIN - 673017
     3       STATE OF KERALA
             REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI
             - 682 030, PIN - 682030
     4       KERALA STATE ELECTRICITY BOARD - KSEB
             REPRESENTED BY CHAIRMAN & MANAGING DIRECTOR KSEB
             LTD., THIRUVANANTHAPURAM - 695 001, PIN - 695001
             BY ADV P.T.JOSE


         THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
19.01.2024, ALONG WITH CRP.399/2021 THE COURT ON 23.04.2024
DELIVERED THE FOLLOWING:
 CRP Nos.399 of 2021 and 177 of 2022

                                 -3-



                              ORDER

Dated this the 23rd day of April, 2024

These revision petitions are filed

challenging the order passed by the Additional

District Judge-VI, Ernakulam in O.P.(Electricity)

No.621 of 2013. The original petition was filed

by the revision petitioner in CRP No.399 of 2021

(hereinafter called 'the claimant'), being

dissatisfied with the compensation awarded

towards the damage and loss sustained due to the

drawing of 400 KV lines across his property by

the Power Grid Corporation of India Ltd

(hereinafter called 'the Corporation'). The

essential facts are as under;

The claimant is in ownership and possession

of landed property having total extent of 6.93

Ares in Sy.Nos.64/10, 64/7 and 40/6 of Koovappady

Village in Kunnathunadu Taluk. The land was

cultivated with various yielding and non-yielding CRP Nos.399 of 2021 and 177 of 2022

trees. According to the claimant, to facilitate

drawing of the lines and smooth transmission of

power, large number of trees were cut from his

property. The drawing of high tension lines

rendered the land underneath and adjacent to the

lines useless, resulting in diminution of the

value of the property. In spite of the huge loss

suffered by the claimant, only an amount of

Rs.20,261/- was paid as compensation towards the

value of yielding and non-yielding trees cut.

Surprisingly, no compensation was granted for

diminution in land value. Hence, the original

petition was filed, seeking enhanced compensation

towards the value of trees cut and diminution in

land value.

2. The court below rejected the claim for

enhanced compensation for the value of trees cut

since no evidence in support of the claim was

produced. As far as the claim for enhanced

compensation towards diminution in land value is CRP Nos.399 of 2021 and 177 of 2022

concerned, the court below relied on Ext.A7

document as well as Exts.C14 and C14(a)

commission report and sketch. The court below has

adopted the land value of the property involved

in Ext.A7 document. Relying on Ext.C14(a) plan,

the extent of central corridor was held to be

0.570 cents and that of the outer corridor, 4.940

cents. The court below also took note of the fact

that a small portion of the house is situated

within the extent covered by the outer corridor.

For the central corridor, 40% of the land value

was granted as compensation and for the outer

corridor, 20% of the land value. The court below

also granted Rs.25,000/- as compensation towards

injurious affection on the house. Accordingly,

the claimant was found entitled to compensation

of Rs.2,31,646/-. Dissatisfied with the quantum

of enhancement, the claimant has filed CRP No.399

of 2021, whereas the Corporation has filed CRP

No.177 of 2022 contending that the enhancement CRP Nos.399 of 2021 and 177 of 2022

ordered is far in excess of the actual damage

sustained.

3. Heard Adv.P.T.Jose for the claimant and

Adv.Millu Dandapani for the Corporation.

4. Learned Counsel for the claimant

contended that the court below committed gross

illegality in refusing to grant enhanced

compensation for the loss sustained due to the

cutting of valuable trees, in spite of the

Advocate Commissioner assessing and reporting the

loss. The findings in the Commissioner's report

were not relied on by the court below for the

reason that the property was inspected much after

the trees were cut. The said reasoning is flawed

since the trees were cut much after issuance of

notification by the Corporation and the cause of

action for filing the original petition arose

only on payment of the initial compensation, even

later.

5. It is submitted that the court below

grossly erred in granting only 40% of the land CRP Nos.399 of 2021 and 177 of 2022

value for the central corridor and only 20% for

the outer corridor. It is further submitted that

the court below is not justified in granting only

Rs.25,000/- as compensation even after finding

the house is situated within the extent covered

by the outer corridor. Considering the extent of

damage sustained and the diminution in land value

consequent to the drawing of lines, the court

below ought to have granted compensation as

claimed.

6. Learned Counsel for the Corporation

contended that, compensation towards diminution

in land value granted is exorbitant and there is

no rationale in granting 9% interest on that

amount. The court below also erred in relying on

Ext.A7 for fixing the land value of the

claimant's property. As the drawing of electric

lines does not prohibit the landowner from

conducting agricultural activities and putting up

small structures, 40% of the land value granted CRP Nos.399 of 2021 and 177 of 2022

for the central corridor and 20% for the outer

corridor are exorbitant. The court below grossly

erred in granting Rs.25,000/- towards injurious

affection on the house, which is in no way

affected.

7. A careful scrutiny of the impugned order

reveals that the claim for enhancement of

compensation towards the value of trees cut was

rightly rejected since no supporting material,

other than the findings in the Advocate

Commissioner's report, was made available. As

found by the court below, apart from the

interested testimony of a witness, who is the

claimant in some of the connected cases, no other

independent witnesses were examined. The court

below also took note of the fact that the trees

were cut and removed in the year 2011 and the

Commissioner inspected the property after a long

period. Therefore, the court below rightly

refused to accept the assessment made by the CRP Nos.399 of 2021 and 177 of 2022

Commissioner, which was based on an overview of

the trees standing in the remaining petition

schedule property and neighbouring property. On

the other hand, the court below found the

Corporation to have assessed the yield on the

basis of local inspection, enquiry and data

furnished by the Government departments. It was

therefore held that the evidence let in by the

claimant was not sufficient to discard the

contemporaneous valuation statement prepared by

the Corporation.

8. As far as the diminution in land value

is concerned, the factors to be taken into

consideration, as laid down in KSEB v. Livisha

[(2007) 6 SCC 792] are as under;

"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion CRP Nos.399 of 2021 and 177 of 2022

would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."

On careful scrutiny of the impugned order, it is

seen that the compensation was enhanced after

taking all the above factors into consideration.

The nature of the land, the cultivation therein,

the commercial importance of the area and the

manner in which the land was affected by drawing

of the lines are all seen considered for fixing

the land value as well as the percentage of

diminution. After considering the similarities of

the properties involved, the court below has

adopted the land value in Ext.A7 document, which

according to me, is reasonable. For the central

corridor, 40% of the land value is granted as

compensation and for outer corridor, 20% is

granted, which also I find to be just and proper. CRP Nos.399 of 2021 and 177 of 2022

Similarly, discretion was properly exercised by

the court below in granting Rs.25,000/-, towards

injurious affection on the house situated in the

outer corridor.

9. The contention of the Corporation that

the Government having fixed the fair value, the

court below could not have fixed a higher value

is liable to be rejected since, while assessing

the damage sustained and fixing the compensation,

the court is not bound by the guidelines/orders

issued by the Government. The contention that

the court below committed an illegality in

awarding 9% interest cannot also be sustained in

the light of the decision of this Court in V.V.

Jayaram v Kerala State Electricity Board [2015

(3) KHC 453]. As such, there is no illegality or

material irregularity in the impugned order,

warranting intervention by this Court in exercise

of the revisional power under Section 115 of the

Code of Civil Procedure.

CRP Nos.399 of 2021 and 177 of 2022

For the aforementioned reasons, the civil

revision petitions filed by the claimant as well

as the Corporation are dismissed.

If any amount is deposited pursuant to the

order of this Court or otherwise, the same shall

forthwith be released to the claimant on his

filing appropriate application. The entire

enhanced compensation shall be paid to the

claimant within three months of receipt of a copy

of this order.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter