Citation : 2024 Latest Caselaw 10707 Ker
Judgement Date : 12 April, 2024
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
FRIDAY, THE 12TH DAY OF APRIL 2024 / 23RD CHAITHRA, 1946
CRP NO. 386 OF 2021
AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.682 OF 2014 OF VI
ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
POWER GRID CORPORATION OF INDIA LTD.
CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
KAKKANAD, COCHIN 682 030, PRESENTLY AT CONSTRUCTION
AREA OFFICE, 400/220 KV SUB STATION, KUMARAPURAM
P.O., PALLIKKARA, ERNAKULAM-683 565, REP.BY ITS
SENIOR GENERAL MANAGER
BY ADV MILLU DANDAPANI
RESPONDENT/S:
1 JACOB
AGED 64 YEARS
S/O.POULO, RESIDING AT MADAN HOUSE, MANJAPRA
VILLAGE, ALUVA TALUK, ERNAKULAM, KERALA 683 581
2 THE SPECIAL TAHASILDAR (LA)
POWER GRID CORPORATION OF INDIA LTD., CHEVARAMBALAM,
KOZHIKODE 673 017
3 STATE OF KERALA
REP.BY DISTRICT COLLECTOR, CIVIL STATION, KAKKANAD,
ERNAKULAM, KOCHI 682 030
4 KERALA STATE ELECTRICITY BOARD
REP.BY IT'S CHAIRMAN AND MANAGING DIRECTOR, KSEB
LTD, VYDYUDHI BHAVAN, PATTOM (P.O.),
THIRUVANANTHAPURAM 695 001
BY ADVS.
P.T.JOSE
R.HARISHANKAR
OTHER PRESENT:
SC FOR KSEB A. ARUNKUMAR;GP B.S.SYAMANTHAK
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
18.01.2024, ALONG WITH CRP.20/2022, THE COURT ON 12.04.2024
DELIVERED THE FOLLOWING:
CRP Nos.386/21 & 20/22
-2-
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE V.G.ARUN
FRIDAY, THE 12TH DAY OF APRIL 2024 / 23RD CHAITHRA, 1946
CRP NO. 20 OF 2022
AGAINST THE ORDER/JUDGMENT DATED 20.03.2021 IN OPELE NO.682 OF
2014 OF VI ADDITIONAL DISTRICT COURT, ERNAKULAM
REVISION PETITIONER/S:
JACOB
AGED 72 YEARS
S/O.POULO, MADAN HOUSE, MANJAPRA, ANGAMALY - 683
581.
BY ADV P.T.JOSE
RESPONDENT/S:
1 POWER GRID CORPORATION OF INDIA
CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
KAKKANAD, COCHIN 682 030. NOW IN PAO/400, 220KV
SUBSTATION, KUMARAPURAM P.O.,PALLIKKARA, COCHI - 682
030, REP. BY DEPUTY MANAGER.
2 THE SPECIAL TAHSILDAR (L.A.)
POWERGRID CORPORATION OF INDIA
LTD.,CHEVARAMBALAM,KOZHIKKODE - 673 017, NOW IN
THRIKKAKARA VILLAGE, KANAYANNOOR TALUK, KAKKANAD
P.O. - 682 030.
3 STATE OF KERALA
REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI
- 682 030.
4 KERALA STATE ELECTRICITY BOARD
REPRESENTED BY CHAIRMAN AND MANAGING DIRECTOR, KSEB
LTD., THIRUVANANTHAPURAM - 695 001.
BY ADV R.HARISHANKAR
THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON
18.01.2024, ALONG WITH CRP.386/21, THE COURT ON 12.04.2024
DELIVERED THE FOLLOWING:
CRP Nos.386/21 & 20/22
-3-
ORDER
Dated this the 12th day of April, 2024
These revision petitions are filed
challenging the order passed by the Additional
District Judge-VI, Ernakulam in O.P.(Electricity)
No.682 of 2014. The original petition was filed
by the revision petitioner in CRP No.20 of 2022
(hereinafter called 'the claimant'), being
dissatisfied with the compensation awarded
towards the damage and loss sustained due to the
drawing of 400 KV lines across his property by
the Power Grid Corporation of India Ltd
(hereinafter called 'the Corporation'). The
essential facts are as under;
The claimant is in ownership and possession
of landed property having an extent of 12.55
Ares comprised in Sy.No.289/6 of Manjapra Village
in Aluva Taluk. The land was cultivated with
various yielding and non-yielding trees. CRP Nos.386/21 & 20/22
According to the claimant, to facilitate drawing
of the lines and smooth transmission of power,
large number of trees were cut from his property.
The drawing of high tension lines rendered the
land underneath and adjacent to the lines
useless, resulting in diminution of the value of
the property. In spite of the huge loss suffered
by the claimant, only an amount of Rs.1,93,603/-
was paid as compensation towards the value of
yielding and non-yielding trees cut.
Surprisingly, no compensation was granted for
diminution in land value. Hence, the original
petition was filed, seeking enhanced compensation
towards the value of trees cut and diminution in
land value.
2. The court below rejected the claim for
enhanced compensation for the value of trees cut
since no evidence in support of the claim was
produced. As far as the claim for enhanced
compensation towards diminution in land value is
concerned, the court below relied on Ext.A7 CRP Nos.386/21 & 20/22
document as well as Exts.C7 and C7(a) commission
report and sketch. The Advocate Commissioner
reported that the claimant's property is situated
at a distance of 250 metres from Manjapra-Chully
Road, which is a bus route and also abuts the
Idamalayar Canal Road and Panchayat Anganavadi
Road. Moreover, St. Sebastian Church, Homoeo
Clinic and LP School are situated within close
proximity to the petition schedule property.
Based on these factors, the court below adopted
the land value shown in Ext.A7 document. Relying
on Ext.C7(a) sketch, the extent of central
corridor was held to be 12.230 cents and that of
the outer corridor, 15.440 cents. For the central
corridor, 40% of the land value was granted as
compensation and for outer corridor, 20% of the
land value. Accordingly, the claimant was found
entitled to compensation of Rs.17,96,121/-.
Dissatisfied with the quantum of enhancement, the
claimant has filed CRP No.20 of 2022, whereas the CRP Nos.386/21 & 20/22
Corporation has filed CRP No.386 of 2021
contending that the enhancement ordered is far in
excess of the actual damage sustained.
3. Heard Adv.P.T.Jose for the claimant and
Adv.Millu Dandapani for the Corporation.
4. Learned Counsel for the claimant
contended that the court below committed gross
illegality in refusing to grant enhanced
compensation for the loss sustained due to the
cutting of valuable trees, in spite of the
Advocate Commissioner assessing and reporting the
loss. The findings in the Commissioner's report
were not relied on by the court below for the
reason that the property was inspected much after
the trees were cut. The said reasoning is flawed
since the trees were cut much after issuance of
notification by the Corporation and the cause of
action for filing the original petition arose
only on payment of the initial compensation, even
later.
5. It is further submitted that the court CRP Nos.386/21 & 20/22
below grossly erred in granting only 40% of the
land value for the central corridor and only 20%
for outer corridor. Considering the extent of
damage sustained and the diminution in land value
consequent to the drawing of lines, the court
below ought to have granted compensation as
claimed.
6. Learned Counsel for the Corporation
contended that, compensation towards diminution
in land value granted is exorbitant and there is
no rationale in granting 9% interest on that
amount. The court below also erred in relying on
Ext.A7 for fixing the land value of the
claimant's property. As the drawing of electric
lines does not prohibit the landowner from
conducting agricultural activities and putting up
small structures, 40% of land value granted for
central corridor and 20% for the outer corridor
are exorbitant.
7. A careful scrutiny of the impugned order CRP Nos.386/21 & 20/22
reveals that the claim for enhancement of
compensation towards the value of trees cut was
rightly rejected since no supporting material,
other than the findings in the Advocate
Commissioner's report, was made available. As
found by the court below, apart from the
interested testimony of a witness, who is the
claimant in one of the connected cases, no other
witnesses were examined. The court below also
took note of the fact that the Commissioner's
assessment was based on the Mahazar, whereas the
Corporation has assessed the compensation on the
basis of details furnished by the Government
departments. It was therefore held that the
evidence let in by the claimant was not
sufficient to discard the contemporaneous
valuation statement prepared by the Corporation.
8. As far as the diminution in land value
is concerned, the factors to be taken into
consideration, as laid down in KSEB v. Livisha CRP Nos.386/21 & 20/22
[(2007) 6 SCC 792] are as under;
"10. The situs of the land, the distance between the high voltage electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."
On careful scrutiny of the impugned order, it is
seen that the compensation was enhanced after
taking all the above factors into consideration.
The nature of the land, the commercial importance
of the area and the manner in which the land was
affected by drawing of the lines are all seen
considered for fixing the land value as well as
the percentage of diminution. The court below has
adopted the land value in Ext.A7 document, which CRP Nos.386/21 & 20/22
according to me, is reasonable. The discretion
was properly exercised in granting 40% of the
land value as compensation for the central
corridor and 20% for the outer corridor.
9. The contention of the Corporation that
the Government having fixed the land value, the
court below could not have fixed a higher value
is liable to be rejected since, while assessing
the damage sustained and fixing the compensation,
the court is not bound by the guidelines/orders
issued by the Government. The contention that
the court below committed an illegality in
awarding 9% interest cannot also be sustained in
the light of the decision of this Court in V.V.
Jayaram v Kerala State Electricity Board [2015
(3) KHC 453]. As such, there is no illegality or
material irregularity in the impugned order,
warranting intervention by this Court in exercise
of the revisional power under Section 115 of the
Code of Civil Procedure.
CRP Nos.386/21 & 20/22
For the aforementioned reasons, the civil
revision petitions filed by the claimant as well
as the Corporation are dismissed. The enhanced
compensation fixed by the court below shall be
paid within three months of receipt of a copy of
this order. If any amount is deposited pursuant
to the order of this Court or otherwise, the same
shall forthwith be released to the claimant on
his filing appropriate application.
Sd/-
V.G.ARUN JUDGE Scl/
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!