Citation : 2024 Latest Caselaw 10683 Ker
Judgement Date : 12 April, 2024
"C.R."
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE EASWARAN S.
FRIDAY, THE 12TH DAY OF APRIL 2024 / 23RD CHAITHRA, 1946
WP(C) NO. 8789 OF 2018
PETITIONER/S:
1 T.P. PAULOSE "DIED, LRS IMPLEADED"
AGED 72 YEARS
THELAPPILLY HOUSE, PULIYANAM P.O, ANGAMALY,
ERNAKULAM DISTRICT - 683 572.
2 ADDL.P2. ANIAMMA PAULOSE
AGED 56 YEARS, WIFE OF DECEASED T.P.PAULOSE,
RESIDING AT THELAPPILLY HOUSE, PULIYANAM P.O.,
ANGAMALY, ERNAKULAM DISTRICT - 683 572.
3 ADDL.P3. ELDHO PAUL
AGED 44 YEARS, SON OF DECEASED T.P.PAULOSE,
RESIDING AT THELAPPILLY HOUSE, PULIYANAM P.O.,
ANGAMALY, ERNAKULAM DISTRICT - 683 572.
4 ADDL.P4. SUNI JAMES
AGED 50 YEARS, DAUGHTER OF DECEASED T.P.PAULOSE,
RESIDING AT MARACHERY PUTHENPURA, MARAMANGALAM,
KUTHUKUZHY P.O., KUTHUKUZHY, ERNAKULAM DISTRICT -
686 691.
[ADDITIONAL PETITIONER NOS.P2 TO P4 ARE IMPLEADED AS PER
ORDER DATED 11.07.2022 IN I.A.1/2022 IN WP(C)8789/2018]
BY ADVS.
SRI.JACOB P.ALEX
SRI.RANJITH VARGHESE
SRI.RAHUL VARGHESE
SANTHA VARGHESE
RESPONDENT/S:
1 THE STATE OF KERALA
REPRESENTED BY THE SECRETARY TO GOVERNMENT, PWD
(IRRIGATION DEPARTMENT), GOVERNMENT SECRETARIAT,
THIRUVANANTHAPURAM.
WP(C) 8789/2018
2
2 THE EXECUTIVE ENGINEER
PWD BUILDINGS DIVISION, ERNAKULAM, EDAPPALLY,
KOCHI - 682 024.
3 THE ASSISTANT EXECUTIVE ENGINEER
BUILDINGS SUB DIVISION, MUVATTUPUZHA - 686 673.
4 THE DISTRICT COLLECTOR
COLLECTORATE, KAKKANAD, ERNAKULAM - 682 030.
BY ADV GOVERNMENT PLEADER
OTHER PRESENT:
SRI.BIMAL.K.NATH,,SR.G.P.
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR
ADMISSION ON 11.04.2024, THE COURT ON 12.04.2024 DELIVERED
THE FOLLOWING
WP(C) 8789/2018
3
"C.R"
J U D G M E N T
Two intriguing questions arise for
consideration in this writ petition. Can the
respondents initiate revenue recovery measures for
alleged damages caused on account of re-tendering
of the work awarded to one Late T.P Paulose?
Secondly, even if it is held so, can the legal
heirs of the Late T.P.Paulose be held liable to
the alleged damages caused to State exchequer.
2. Sri.T.P.Paulose, a contractor, was the
successful tenderer in terms of Ext.P1 notice
inviting tenders for providing rain shade to the court complex at Muvattupuzha. Ext.P1 is dated
7.10.2016. Sri.T.P.Paulose on 20.10.2016 addressed
to the 2nd respondent requesting to relieve him
from the obligation to complete the work, which
was awarded to him. Despite this notice, the 2 nd
respondent proceeded to select late
Sri.T.P.Poulose as lowest tenderer pursuant to
Ext.P1 notice on 28.10.2016. As per Ext.P4 dated WP(C) 8789/2018
14.12.2016, late Sri.T.P.Paulose was put on notice
that his failure to execute agreement will entail
further consequences and proceedings against him.
Thereafter, on 30.1.2017, the attempt of the 2nd
respondent to persuade the second lowest bidder to
complete the work failed, and therefore,
proceedings for recovery against Sri.T.P.Paulose
was recommended. It is pursuant to this order
that Ext.P6 was issued to late Sri.T.P.Paulose
stating that an amount of Rs.6,01,929.74 was the
loss caused to the Department consequent to the
re-tendering of the work. In response to Ext.P6,
late Sri.T.P.Paulose addressed to the 2nd
respondent on 29.7.2017 vide Ext.P7 stating that he is not liable under any circumstances for the
loss that was caused. It is pertinent to note
that Ext.P6 was dated 8.6.2017 and by Ext.P8, the
said request was turned down and the 2nd respondent
decided to proceed with recovery measures against
late Sri.T.P.Paulose. By order dated 11.7.2022 in
I.A.No.1/2022, his legal heirs were impleaded as WP(C) 8789/2018
additional petitioners 2 to 4, who are prosecuting
the present writ petition.
3. A counter affidavit has been filed on
behalf of the 2nd respondent in which it is
contended that as per notice inviting tender for
the works, every bidder is expected before quoting
his rate to inspect the site of the proposed
works. It is also stated that the rates quoted
shall be inclusive ones, covering all the
operations contemplated in the specifications and
tender schedules and all incidental works
necessary for such operations such as shoring
bailing out work, scaffolding etc. Therefore, it
is contended that since late T.P.Paulose carried out joint inspection with officers of the
respondent and found that various items involved
in the work were not provided in the price
schedule and that the petitioner had not inspected
the site before quoting the tender. It is further
averred that if the contractor does not come
forward to execute the original agreement after
the work is awarded, the selection notice issued WP(C) 8789/2018
in his favour gets cancelled and, hence, a breach
is committed by him.
4. Controverting to the averments contained
in the counter affidavit, late Sri.T.P.Paulose had
filed a reply affidavit, in which it is stated
that re-tendering of the work at his risk and cost
was belatedly issued on 12.10.2017 as per
Ext.R2(a). It is also pointed out that under
Ext.R2(a) report, the 3rd respondent has submitted
to the 2nd respondent that the agreement to re-cast
the estimate with all required items was done
since the drawings were not provided with the
tender. The assertion that the cement concrete
works under Ext.P1 price schedule needs to be carried out in case rain water falls on the
varanda floor etc. is denied. The re-tendering
work, according to Sri.T.P.Paulose, has been done
without following the procedure laid down under
Ext.P10 Government Order.
5. I have heard Sri.Ranjith Varghese,
learned counsel appearing for the petitioner and WP(C) 8789/2018
the learned Senior Government Pleader on behalf of
the respondents.
6. Learned counsel for the petitioner
submits that damages for breach of contract with
the Government could be recovered only after
assessing the damages arising out of the breach.
He further contends that unless the said damages
are liquidated and found in an appropriate civil
proceeding, there cannot be any attempt to recover
the alleged loss caused due to re-tendering of the
work. He relies on the decision of this Court in
Build Tech. India v. State of Kerala and Others
[2000 (2) KLJ 142]. He further relies on the
decisions of the Hon'ble Supreme Court in Tulsi Narayan Garg v. M.P.Road Development Authority
[2019 SCC OnLine SC 1158]; State of Karnataka v.
Shree Rameshwara Rice Mills [(1987) 2 SCC 160] and
J.G.Engineers Pvt. Ltd. v. Union of India and
Another [(2011) 5 SCC 758].
7. On the other hand, learned Senior
Government Pleader takes me to Ext.R2(a) letter in
which it is specifically stated by the Assistant WP(C) 8789/2018
Executive Engineer that it is because of the
refusal of late Sri.T.P.Paulose that the work had
to be re-tendered. He also refers to the
averments in paragraph Nos.4 and 6 of the counter
affidavit to assert that the proceedings initiated
for recovery of damages on account of re-tendering
of the work was proper. Therefore, he prays for
the dismissal of the writ petition.
8. I have considered the rival submissions
raised across the bar.
9. Insofar as the first question is concerned,
it is explicitly clear that there was no agreement
executed between late Sri.T.P.Paulose and the
respondents. It is also evident from the records that at the first possible instance,
Sri.T.P.Paulose had intimated to the tendering
authority his inability to execute the agreement
for various reasons. This apparently was ignored
while the selection order was issued on
28.10.2016. Thus, there is a unilateral decision
on the part of the respondents to award the work WP(C) 8789/2018
to late Sri.T.P.Paulose, despite his reluctance to
proceed further in this matter.
10. The issue as to whether a claim for
either liquidated damages or unliquidated damages
could be raised in terms of the provisions
contained under the Kerala Revenue Recovery Act,
1963, came up for consideration before this court
in Ponnappan K.A. Vs D.F.O., Chalakudy and others
[1984 KHC 442] and in Govindankutty v. State of
Kerala [2016 (4) KLT 929]. It was held that
unless the damages are quantified in a civil
proceedings, the provisions of Kerala Revenue
Recovery Act cannot be invoked. In the light of
the aforesaid principles, I am inclined to take a view that the additional petitioners are justified
in contending that the attempt made by the 2 nd
respondent to recover the differential amount
between the lowest tenderer - the amount quoted by
late Sri.T.P.Paulose and the amount for which the
retender was made - cannot be sustained.
11. Insofar as the second question raised in
the present writ petition is concerned, WP(C) 8789/2018
admittedly, there was no agreement between late
Sri.T.P.Paulose and the respondents by which the
terms and conditions were settled between the
parties. Even one was to assume that there was
such contract and the mere application for the bid
and its consequential acceptance would result into
a contract between the parties, still the question
would be whether the legal heirs are liable for
the loss allegedly caused due to the respondents.
Therefore, while answering the second question,
this Court would have to decide whether there is a
concluded contract or not, and even if there is
none, whether the additional petitioners are
liable to the claim for damages.
12. It is pertinent to note that the parties
are at variance as to whether there was concluded
contract or not between late Sri.T.P.Paulose and
the respondents. The argument of the State is that
the mere fact that Late T.P Poulose had applied
for tender pursuant to the notice inviting e-
tender and further that he was selected as lowest WP(C) 8789/2018
tenderer itself is sufficient to conclude that
there is a concluded contract.
13. Before answering the question on the
liability of the legal heirs for damages claimed
by the State, the question as to whether there is
a concluded contract or not is required to be
decided. It is not possible to assume or conclude
that due to mere fact that an application was
filed/submitted by Sri.T.P.Paulose pursuant to
Ext.P1 notice and the consequential acceptance and
selection of Sri.T.P.Paulose as the lowest
tenderer will not ipso facto lead to a conclusion
that there was a concluded contract between the
parties. This is especially so, when late Sri.T.P.Paulose had given a request to withdraw
from the tender immediately on coming to know that
he will not be able to perform his part of the
contract. Despite this letter, it appears that
the 2nd respondent had proceeded to select late
Sri.T.P.Paulose as the lowest tenderer. Can such
a unilateral decision on the part of the 2nd
respondent be sufficient to fasten the liabilities WP(C) 8789/2018
on late Sri.T.P.Paulose, so as to make his legal
heirs liable?.
14. The learned counsel for the petitioner
Sri.Ranjith Varghese further submitted that there
is no concluded contract between late
Sri.T.P.Paulose and the respondents. The learned
counsel for the petitioner, further submits that
the stand of the respondents as reflected from the
counter affidavit, especially paragraph 8, that
the moment late T.P.Paulose submitted his
application pursuant to the tender notice, that
itself is sufficient to warrant initiation of
further steps by the respondents to recover the
loss, if any, caused by recovering the same as arrears of land revenue, cannot for a moment be
sustained. He further relies on a Constitution
Bench decision of the Hon'ble Supreme Court in
K.P.Chaudhari v. State of Madhyapradesh & Others
[1966 SCC Online 21] to drive home his point. On
a close reading of the aforesaid judgment,
especially paragraph No.10, shows that the Hon'ble
Apex Court had occasion to consider the issue as WP(C) 8789/2018
to whether in the absence of a concluded contract
between the contractor and the Government in terms
of Article 299(1) of the Constitution of India,
whether there can be any liability cast upon the
contractor?. The question as to whether there
could be an implied contract between the parties
based on the application submitted for
participation in tender process, was also
considered. Ultimately, the Hon'ble Apex Court
went on to hold that "in view of the mandatory
terms of Article 299(1) of the Constitution of India, no implied contract could be spelled out between the Government and the appellant at the stage of bidding, for, Article 299 in effect rules out all implied contracts between the Government and another person."
15. In view of the categoric finding, this
Court finds that on facts of the present case,
there was no concluded contract and therefore,
this Court has no hesitation in its mind to reject
the contention of the respondents that there was a
contract between late T.P.Paulose enabling them to WP(C) 8789/2018
proceed against his legal heirs. It may be noticed
that these incidental issues came up for
consideration before this Court only because of
the death of Sri.T.P.Paulose during the pendency
of the present writ petition and the legal heirs
were permitted to implead as additional
petitioners and prosecute this writ petition.
Hence precisely, the second issue was framed and
decided by this court.
16. Another argument raised by the learned
Senior Government pleader appearing for the State
is that the fact that late T.P Paulose applied for
tender and that he was selected itself is
sufficient to make him liable for the damages and
hence the State is entitled to recover it from the
legal heirs. This issue regarding the enforcement
of contract on legal representatives becomes
rather incidental since this court has already
found that there is no concluded contract between
the parties. However, since the State insists that
it is entitled to recover the damages on account
of re-tendering of work from the legal WP(C) 8789/2018
representatives of the deceased Late T.P. Paulose,
this issue also requires to be considered.
17. Law relating to performance of a contract
and the liabilities of legal heirs is stated under
Section 37 of the Indian Contract Act, 1872. The
effect of death of a person and his liabilities is
governed by Section 306 of the Indian Succession
Act, 1925.
18. Section 306 of the Indian Succession Act,
1925 reads as under
"All demands whatsoever and all rights to prosecute or defend any action or special proceeding existing in favour of or against a person at the time of his decease survive and against his executors or administrators, except causes of action for defamation, assault, as defined in the Indian Penal Code or other personal injuries not causing the death of the party: and except also cases where, after the death of the party, the relief sought could not be enjoyed or granting it would be nugatory."
19. Though the aforesaid provision speaks
only of executors and administrators, the same WP(C) 8789/2018
principles must necessarily prevail in the case of
other legal representatives also. This proposition
is affirmed by the Hon'ble Supreme Court in M.
Veerappa Vs Evelyn Sequeria [AIR 1988 SC 506].
Therefore, the section applies to devolution of
rights and liabilities in contract and proceedings
relating to contact.
20. A further question would also have to be
necessarily answered by this Court. If the law is
as aforesaid, then the question to be considered
is whether there is a vested right of action for
the breach of contract. If the answer is in
affirmative, then the death of either party has no
effect upon it, whether or not it arose from a contract of personal nature (see Halsbury's Law of
England, fourth Edn, Vol.9 Page 615).
21. On a further analysis of facts at hand,
it is seen that parties did not choose their
bargain to be reduced in writing. Although the law
relating to enforcement of contracts on legal
representative being succinctly stated above, the
prime consideration should be that the obligation WP(C) 8789/2018
arises only on execution of a contract. In Pollock
and Mulla On Indian Contract Twelfth Edition Page
947, the learned Author has opined, that there can
be no obligation without a contract. More or less
similar issue came up for consideration before the
Apex Court in Bombay HSG Board V Karbhase Nairk
and Co [AIR 1975 SC 763], wherein the Apex Court
was called upon to decide on a certificate for
appeal on a decision of Division Bench of Bombay
High Court, whether without a concluded contract,
a contractor was bound to be paid at the rates
quoted by him in notice for damages. Answering the
question, the Apex Court held that mere fact that
Engineer-in-charge did not exercise his power to cancel the order would not mean a contract is
concluded on contractor's term. The Apex Court
went on to negative the claim of the contractor.
22. Be that as it may, it will also be
appropriate to consider whether under a contract
which basically involves personal skills of the
contractor, whether the legal representatives
would be liable to perform the contract?. WP(C) 8789/2018
Governing provision under the Indian Contract Act
is Section 40 of the Indian Contract Act, 1872
which reads as under:
"40. If it appears from the nature of the case that it was the intention of the parties to any contract that any promise in it should be performed by the promisor himself, such promise must be performed by the promisor. In other cases, the promisor or his representatives may employ a competent person to perform it".
Reading of the aforesaid Section gives answer to
the question posed before this court in the
following manner:
A) Necessarily there should be a contract between the parties;
B) Liability of the representative should be
provided in the contract itself.
23. It may be apposite to note that a
contract for designing a building by an architect
is held to be a personal contract and which could
not be enforceable against his legal
representative. {See Morsel Cleaners Ltd Vs Hicks
[(1966) 2 Lloyd's Rep 338]}. Based on the above, WP(C) 8789/2018
this Court is inclined to take a view that in the
present case, no liability could be fastened on
the legal heirs.
24. In Vinayak Purshottam Dube (D) v.
Jayashree Padamkar Bhat & Others [2024 SCC Online
212], the Hon'ble Supreme Court was called upon to
decide whether a contract executed in a personal
capacity would bind the legal heirs or not? While
answering the question in affirmative, the Apex
Court held as under:
"21. Thus, a contract can be performed vicariously by the legal representatives of the promisor depending upon the subject matter of the contract and the nature of performance that was stipulated thereto. But a contract involving exercise of individual's skills or expertise of the promisor or which depends upon his/her personal qualification or competency, the promisor has to perform the contract by himself and not by his/her representatives. A contract of service is also personal to the promisor. This is because when a person contracts with another to work or to perform service, it is on the basis of the individual's skills, competency or other qualifications of the promisor and in WP(C) 8789/2018
circumstances such as the death of the promisor he is discharged from the contract."
25. In the aforesaid decision also the
principles as expounded by this Court is affirmed
by the Hon'ble Supreme Court of India. Added to
the above, the Apex Court went on to hold, even in
a case of concluded contract which involving
personal skill, the legal representatives are not
liable. Therefore, it must be necessarily held
that the legal representatives are not liable to
the claim for damages by the State.
26. In the result, this Court finds that the
additional petitioners 2 to 4 are entitled to succeed. It is declared that they are not liable
to answer the claim for damages raised by the
State against Late T.P. Paulose.
Hence the Writ petition is allowed. Exts.P6
and P8 are set aside. No order as to costs.
Sd/-
EASWARAN S. JUDGE jg WP(C) 8789/2018
APPENDIX OF WP(C) 8789/2018
PETITIONER EXHIBITS
EXHIBIT P1 TRUE COPY OF THE PRICE SCHEDULE.
EXHIBIT P2 TRUE COPY OF LETTER DT. 20.10.2016 ISSUED BY THE PETITIONER TO THE 2ND RESPONDENT.
EXHIBIT P3 TRUE COPY OF SELECTION NOTICE
DT.28.10.2016 ISSUED BY THE 2ND
RESPONDENT TO THE PETITIONER.
EXHIBIT P4 TRUE COPY OF LETTER DT. 14.12.2016 ISSUED
BY THE 2ND RESPONDENT TO THE PETITIONER.
EXHIBIT P5 TRUE COPY OF LETTER DT. 30.01.2017 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER.
EXHIBIT P6 TRUE COPY OF LETTER DT. 08.06.2017 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER.
EXHIBIT P7 TRUE COPY OF LETTER DT. 29.07.2017 ISSUED BY THE PETITIONER TO THE 2ND RESPONDENT.
EXHIBIT P7(A) TRUE COPY OF ACKNOWLEDGMENT RECEIPT EVIDENCING RECEIPT OF EXHIBIT P7 LETTER.
EXHIBIT P8 TRUE COPY OF LETTER DT. 16.01.2018 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER.
EXHIBIT P9 TRUE COPY OF LETTER DT. 02.03.2018 ISSUED BY THE PETITIONER TO THE 2ND RESPONDENT.
ADDL.EXHIBIT P10 TRUE COPY OF THE GOVERNMENT ORDER DATED 30.07.2015
ADDL.EXHIBIT P11 TRUE COPY OF LETTER DATED 29.5.2018 ISSUED BY THE PUBLIC INFORMATION OFFICER OF THE RESPONDENT.
WP(C) 8789/2018
ADDL.EXHIBIT P12 TRUE COPY OF LETTER DATED 12.6.2018 ISSUED BY THE 3RD RESPONDENT UNDER THE RIGHT TO INFORMATION ACT.
ADDL.EXHIBIT P13 TRUE COPY OF THE CIRCULAR DATED 10.5.2005 OF GOVERNMENT OF KERALA.
ADDL.EXHIBIT P14 DEATH CERTIFICATE ISSUED BY THE KOCHI MUNICIPAL CORPORATION.
ADDL.EXHIBIT P15 TRUE COPY OF THE LEGAL HEIRSHIP CERTIFICATE ISSUED BY THE TAHSILDAR, ALUVA
RESPONDENT'S EXHIBITS
EXHIBIT R2(a) TRUE COPY OF THE LETTER DATED 1.12.2016
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!