Monday, 20, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Joju Peter vs Power Grid Corporation Of India Ltd
2024 Latest Caselaw 10398 Ker

Citation : 2024 Latest Caselaw 10398 Ker
Judgement Date : 11 April, 2024

Kerala High Court

Joju Peter vs Power Grid Corporation Of India Ltd on 11 April, 2024

Author: V.G.Arun

Bench: V.G.Arun

              IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                PRESENT

                 THE HONOURABLE MR.JUSTICE V.G.ARUN

   THURSDAY, THE 11TH DAY OF APRIL 2024 / 22ND CHAITHRA, 1946

                         CRP NO. 373 OF 2021

 AGAINST THE ORDER/JUDGMENT DATED IN OPELE NO.624 OF 2013 OF VI

                 ADDITIONAL DISTRICT COURT, ERNAKULAM

REVISION PETITIONER/S:

            JOJU PETER
            AGED 52 YEARS
            MONIKKATH HOUSE, CHERANELLUR, KOOVAPPADY VILLAGE,
            KUNNATHUNAD TALUK 683 544
            BY ADV P.T.JOSE


RESPONDENT/S:

    1       POWER GRID CORPORATION OF INDIA LTD.
            CONSTRUCTION AREA OFFICE, KAKKANAD, NOW IN PAO/400,
            220KV SUBSTATION, KUMARAPURAM P.O., PALLIKARA, KOCHI
            682 303, REP.BY DEPUTY MANAGER
    2       THE SPECIAL TAHSILDAR (L.A.)
            POWER GRID CORPORATION OF INDIA, CHEVARAMBALAM,
            KOZHIKODE, NOW NEAR CIVIL STATION, KAKKANAD, ERNAKULAM
            DISTRICT, PIN 682 030
    3       STATE OF KERALA
            REP.BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI 682 030
    4       KERALA STATE ELECTRICITY BOARD,
            REP.BY CHAIRMAN AND MANAGING DIRECTOR, KSEB LTD.,
            THIRUVANANTHAPURAM 695 004
            BY ADV R.HARISHANKAR


OTHER PRESENT:

            SC FOR KSEB A.ARUNKUMAR;GP B.S.SYAMANTHAK


        THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON

18.01.2024,   ALONG   WITH   CRP.182/2022,   THE   COURT   ON   11.04.2024

DELIVERED THE FOLLOWING:
 CRP Nos.373/21 & 182/22

                                  -2-




               IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                PRESENT

                  THE HONOURABLE MR.JUSTICE V.G.ARUN

    THURSDAY, THE 11TH DAY OF APRIL 2024 / 22ND CHAITHRA, 1946

                          CRP NO. 182 OF 2022

AGAINST THE ORDER/JUDGMENT DATED 31.03.2021 IN OPELE NO.624 OF

2013 OF VI ADDITIONAL DISTRICT COURT, ERNAKULAM

REVISION PETITIONER/S:

             POWER GRID CORPORATION OF INDIA
             CONSTRUCTION AREA OFFICE, MAVELIPURAM COLONY,
             KAKKANAD, COCHIN - 682 030, PRESENTLY AT CONSTRUCTION
             AREA OFFICE, 400/220, KV SUB STATION, KUMARAPURAM P.O,
             PALLIKKARA, ERNAKULAM REPRESENTED BY ITS SENIOR
             GENERAL MANAGER, PIN - 683565
             BY ADV MILLU DANDAPANI


RESPONDENT/S:

     1       JOJU PETER
             AGED 53 YEARS
             S/O. PATHROSE ,MONIKKATH HOUSE, CHERANELLUR PO,
             KOOVAPADI VILLAGE , KUNNATHUNADU TALUK, REPRESENTED BY
             POWER OF ATTORNEY HOLDER, HIS FATHER PATHROSE.
             ERNAKULAM DISTRICT, PIN - 683544
     2       THE SPECIAL TAHSILDAR (LA)
             POWER GRID CORPORATION OF INDIA LTD. CHEVARAMBALAM,
             KOZHIKODE, PIN - 673017
     3       STATE OF KERALA
             REPRESENTED BY DISTRICT COLLECTOR, ERNAKULAM, KOCHI,
             PIN - 682030
     4       KERALA STATE ELECTRICITY BOARD - KSEB
             REPRESENTED BY CHAIRMAN & MANAGING DIRECTOR KSEB LTD.,
             THIRUVANANTHAPURAM, PIN - 695001
             BY ADV P.T.JOSE

         THIS CIVIL REVISION PETITION HAVING BEEN FINALLY HEARD ON

18.01.2024, ALONG WITH CRP.373/212022, THE COURT ON 11.04.2024

DELIVERED THE FOLLOWING:
 CRP Nos.373/21 & 182/22

                                -3-



                             ORDER

Dated this the 11th day of April 2024

These revision petitions are filed

challenging the order passed by the Additional

District Judge-VI, Ernakulam in O.P.(Electricity)

No.624 of 2013. The original petition was filed

by the revision petitioner in CRP No.373 of 2021

(hereinafter called 'the claimant'), being

dissatisfied with the compensation awarded

towards the damage and loss sustained due to the

drawing of 400 KV lines across his property by

the Power Grid Corporation of India Ltd

(hereinafter called 'the Corporation'). The

essential facts are as under;

The claimant is in ownership and possession

of landed property having total extent of 35.60

Ares in Sy.Nos.41/6 and 41/7 of Koovappady

Village in Kunnathunadu Taluk. The land was

cultivated with various yielding and non-yielding CRP Nos.373/21 & 182/22

trees. According to the claimant, to facilitate

drawing of the lines and smooth transmission of

power, large number of trees were cut from his

property. The drawing of high tension lines

rendered the land underneath and adjacent to the

lines useless, resulting in diminution of the

value of the property. In spite of the huge loss

suffered by the claimant, only an amount of

Rs.1,21,216/- was paid as compensation towards

the value of yielding and non-yielding trees cut.

Surprisingly, no compensation was granted for

diminution in land value. Hence, the original

petition was filed, seeking enhanced compensation

towards the value of trees cut and diminution in

land value.

2. The court below rejected the claim for

enhanced compensation for the value of trees cut

since no evidence in support of the claim was

produced. As far as the claim for enhanced

compensation towards diminution in land value is CRP Nos.373/21 & 182/22

concerned, the court below relied on Ext.A7

document as well as Exts.C17 and C17(a)

commission report and plan. Relying on Ext.C17(a)

plan, the court below found that a tower was

erected in the claimant's property and the extent

of property covered by the tower was held to be

8.895 cents. Similarly, the extent of central

corridor was held to be 37.41 cents (46.305-

8.895) and that of the outer corridors, 32.367

cents. The court below also took note of the fact

that the remaining property admeasuring 8.895

cents is also affected due to the drawing of

electric lines. For the extent covered by the

tower, 100% of the land value was granted as

compensation. For the central corridor, 40% of

the land value was granted as compensation and

for the outer corridors, 20% of the land value.

Since the entire property was found to be

affected by the drawing of electric lines,

Rs.1,00,000/- was also awarded as compensation to CRP Nos.373/21 & 182/22

the claimant. Accordingly, the claimant was

found entitled to compensation of Rs.52,54,687/-.

Dissatisfied with the quantum of enhancement, the

claimant has filed CRP No.373 of 2021, whereas

the Corporation has filed CRP No.182 of 2022

contending that the enhancement ordered is far in

excess of the actual damage sustained.

3. Heard Adv.P.T.Jose for the claimant and

Adv.Millu Dandapani for the Corporation.

4. Learned Counsel for the claimant

contended that the court below committed gross

illegality in refusing to grant enhanced

compensation for the loss sustained due to the

cutting of valuable trees, in spite of the

Advocate Commissioner assessing and reporting the

loss. The findings in the Commissioner's report

were not relied on by the court below for the

reason that the property was inspected much after

the trees were cut. The said reasoning is flawed

since the trees were cut much after issuance of CRP Nos.373/21 & 182/22

notification by the Corporation and the cause of

action for filing the original petition arose

only on payment of the initial compensation, even

later.

5. It is submitted that the court below

grossly erred in granting only 40% of the land

value for the central corridor and only 20% for

the outer corridors. It is further submitted that

the court below is not justified in granting only

Rs.1,00,000/- as compensation even after finding

the entire property is affected due to the

drawing of electric lines. Considering the extent

of damage sustained and the diminution in land

value consequent to the drawing of lines, the

court below ought to have granted compensation as

claimed.

6. Learned Counsel for the Corporation

contended that, compensation towards diminution

in land value granted is exorbitant and there is

no rationale in granting 9% interest on that CRP Nos.373/21 & 182/22

amount. The court below also erred in relying on

Ext.A7 for fixing the land value of the

claimant's property. As the drawing of electric

lines does not prohibit the landowner from

conducting agricultural activities and putting up

small structures, 40% of the land value granted

for the central corridor and 20% for the outer

corridors are exorbitant. The court below grossly

erred in granting Rs.1,00,000/- for the property,

which is in no way affected.

7. A careful scrutiny of the impugned order

reveals that the claim for enhancement of

compensation towards the value of trees cut was

rightly rejected since no supporting material,

other than the findings in the Advocate

Commissioner's report, was made available. As

found by the court below, apart from the

interested testimony of a witness, who is the

claimant in some of the connected cases, no other

witnesses were examined. The court below also CRP Nos.373/21 & 182/22

took note of the fact that the trees were cut and

removed in the year 2011 and the Commissioner

inspected the property after a long period.

Therefore, the court below rightly refused to

accept the assessment made by the Commissioner,

which was based on the trees standing in the

remaining petition schedule property and

neighbouring property. On the other hand, the

court below found the Corporation to have

assessed the yield on the basis of local

inspection, enquiry and data furnished by the

Government departments. It was therefore held

that the evidence let in by the claimant was not

sufficient to discard the contemporaneous

valuation statement prepared by the Corporation.

8. As far as the diminution in land value

is concerned, the factors to be taken into

consideration, as laid down in KSEB v. Livisha

[(2007) 6 SCC 792] are as under;

"10. The situs of the land, the distance between the high voltage CRP Nos.373/21 & 182/22

electricity line laid thereover, the extent of the line thereon as also the fact as to whether the high voltage line passes over a small tract of land or through the middle of the land and other similar relevant factors in our opinion would be determinative. The value of the land would also be a relevant factor. The owner of the land furthermore, in a given situation may lose his substantive right to use the property for the purpose for which the same was meant to be used."

On careful scrutiny of the impugned order, it is

seen that the compensation was enhanced after

taking all the above factors into consideration.

The nature of the land, the cultivation therein,

the commercial importance of the area and the

manner in which the land was affected by drawing

of the lines are all seen considered for fixing

the land value as well as the percentage of

diminution. After considering the similarities of

the properties involved, the court below has

adopted the land value in Ext.A7 document, which

according to me, is reasonable. For the land CRP Nos.373/21 & 182/22

covered by the tower, 100% of the land value is

granted as compensation and the central and outer

corridors are granted 40% and 20% respectively,

which also I find to be just and proper. The

discretion was properly exercised in granting

Rs.1,00,000/-, finding the entire property is

affected due to the drawing of electric lines.

9. The contention of the Corporation that

the Government having fixed the fair value, the

court below could not have fixed a higher value

is liable to be rejected since, while assessing

the damage sustained and fixing the compensation,

the court is not bound by the guidelines/orders

issued by the Government. The contention that

the court below committed an illegality in

awarding 9% interest cannot also be sustained in

the light of the decision of this Court in V.V.

Jayaram v Kerala State Electricity Board [2015

(3) KHC 453].

10. Having held as above, I find a patent CRP Nos.373/21 & 182/22

mistake in the order, which is liable to be

corrected in exercise of this Court's revisional

jurisdiction. After granting 100% of the land

value as compensation towards the tower foot

area, the court has mistakenly directed to deduct

the compensation paid towards the tower foot area

from the enhanced compensation awarded. It is

also clear from the impugned order that, while

computing the compensation for the central

corridor, the area covered by the tower was

deducted. Therefore, the impugned order, to that

extent, needs to be corrected.

For the aforementioned reasons, the civil

revision petition filed by the claimant is

allowed in part. The direction in the impugned

order, to deduct the compensation paid towards

the tower foot area from the enhanced

compensation is deleted. The enhanced

compensation awarded by the court below shall be

paid within three months, without any deduction. CRP Nos.373/21 & 182/22

If any amount is deposited pursuant to the order

of this Court or otherwise, the same shall

forthwith be released to the claimant on his

filing appropriate application.

The civil revision petition filed by the

Corporation is dismissed.

Sd/-

V.G.ARUN JUDGE Scl/

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter