Tuesday, 12, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S. Nath Infrastructures vs State Of Kerala
2023 Latest Caselaw 3574 Ker

Citation : 2023 Latest Caselaw 3574 Ker
Judgement Date : 29 March, 2023

Kerala High Court
M/S. Nath Infrastructures vs State Of Kerala on 29 March, 2023
W.P.(C) No. 16643/2022 & batch
                                  :1:



                IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                PRESENT

                THE HONOURABLE MR. JUSTICE SHAJI P.CHALY

     WEDNESDAY, THE 29TH DAY OF MARCH 2023 / 8TH CHAITHRA, 1945

                         WP(C) NO. 16643 OF 2022

PETITIONER/S:

           M/S. NATH INFRASTRUCTURES
           28/309 A1, THONDAYAD, KOTTOOLY ROAD, CHERVARAMBALAM P.O
           KOZHIKODE-673 017, REPRESENTED BY ITS MANAGING PARTNER,
           V RAJEENDRANATH.
           BY ADVS.
           SANTHOSH MATHEW
           ARUN THOMAS
           KARTHIKA MARIA
           ANIL SEBASTIAN PULICKEL
           ABI BENNY AREECKAL
           MATHEW NEVIN THOMAS


RESPONDENT/S:

     1     STATE OF KERALA
           REPRESENTED BY THE SECRETARY TO THE GOVERNMENT, PUBLIC
           WORKS DEPARTMENT, GOVERNMENT SECRETARIAT,
           THIRUVANANTHAPURAM, KERALA - 695 001.
     2     PROJECT DIRECTOR,
           KERALA ROAD FUND BOARD-PROJECT MANAGEMENT UNIT,
           GROUND FLOOR, BSNL OFFICE BUILDING, CGM(O) DOORSANCHAR
           BHAVAN, PMG JUNCTION, THIRUVANANTHAPURAM,
           KERALA - 695 033.
     3     THE CHIEF EXECUTIVE OFFICER,
           KERALA INFRASTRUCTURE INVESTMENT FUND BOARD 2ND FLOOR,
           FELICITY SQUARE, MG ROAD, STATUE, THIRUVANANTHAPURAM,
           KERALA - 695 001.
     4     THE TEAM LEADER,
           PMU-KRFB, GROUND FLOOR, BSNL OFFICE BUILDING, CGM(O)
           DOORSANCHAR BHAVAN, PMG JUNCTION, THIRUVANANTHAPURAM,
           KERALA - 695 033.
     5     EXECUTIVE ENGINEER,
           KERALA ROAD FUND BOARD-PROJECT MANAGEMENT UNIT,
           KOZHIKODE / WAYANAD, A-16, VRINDAVAN COLONY, CHEVAYUR,
           KERALA - 673 017.
     6     ADDL. R6 IMPLEADED:

           THE AUTHORIZED OFFICER.
 W.P.(C) No. 16643/2022 & batch
                                  :2:


             THE FEDERAL BANK LTD., L.C.R.D KOZHIKODE DIVISION, IST
             FLOOR, FEDERAL TOWERS, ARAIYIDATHUPALAM, KOZHIKODE,
             KERALA - 673 016.

             (ADDL. R6 IS IMPLEADED AS PER ORDER DATED 21.12.2022 IN IA-
             4/2022 IN WP(C) NO. 16643/2022.)
             BY ADVS.
             Mohan Jacob George
             P.V.PARVATHY (P-41)(K/000036/1991)
             REENA THOMAS(R-364)
             NIGI GEORGE(K/1169/2012)
             R3 BY SRI. CHANDRASEKHARAN NAIR
             R1 BY SRI. K.V. MANOJ KUMAR, SPL. GOVERNMENT PLEADER



THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 16.03.2023,

ALONG WITH WP(C).16798/2022, THE COURT ON 29.03.2023 DELIVERED THE

FOLLOWING:
 W.P.(C) No. 16643/2022 & batch
                                  :3:




                IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                PRESENT

                THE HONOURABLE MR. JUSTICE SHAJI P.CHALY

     WEDNESDAY, THE 29TH DAY OF MARCH 2023 / 8TH CHAITHRA, 1945

                         WP(C) NO. 16798 OF 2022

PETITIONER/S:

           M/S. NATH INFRASTRUCTURES,
           28/309 A1, THONDAYAD, KOTTOOLY ROAD, CHERVARAMBALAM
           (PO), KOZHIKODE - 673 017 REPRESENTED BY ITS MANAGING
           PARTNER.
           BY ADVS.
           SANTHOSH MATHEW
           ARUN THOMAS
           KARTHIKA MARIA
           ANIL SEBASTIAN PULICKEL
           ABI BENNY AREECKAL
           MATHEW NEVIN THOMAS
           KARTHIK RAJAGOPAL


RESPONDENT/S:

     1     STATE OF KERALA,
           REPRESENTED BY THE SECRETARY TO THE GOVERNMENT, PUBLIC
           WORKS DEPARTMENT, GOVERNMENT SECRETARIAT,
           THIRUVANANTHAPURAM, KERALA - 695 001.
     2     PROJECT DIRECTOR,
           KERALA ROAD FUND BOARD-PROJECT MANAGEMENT UNIT,
           GROUND FLOOR, BSNL OFFICE BUILDING, CGM(O) DOORSANCHAR
           BHAVAN, PMG JUNCTION, THIRUVANANTHAPURAM,
           KERALA - 695 033.
     3     THE CHIEF EXECUTIVE OFFICER,
           KERALA INFRASTRUCTURE INVESTMENT FUND BOARD , 2ND
           FLOOR, FELICITY SQUARE, MG ROAD, STATUE,
           THIRUVANANTHAPURAM, KERALA - 695 001.
     4     THE TEAM LEADER, PMU-KRFB,
           GROUND FLOOR, BSNL OFFICE BUILDING, CGM(O) DOORSANCHAR
           BHAVAN, PMG JUNCTION, THIRUVANANTHAPURAM,
           KERALA - 695 033.
     5     EXECUTIVE ENGINEER,
           KERALA ROAD FUND BOARD-PROJECT MANAGEMENT UNIT,
           KOZHIKODE / WAYANAD, A-16, VRINDAVAN COLONY, CHEVAYUR,
           KERALA - 673 017.
     6     ADDL.R6 IMPLEADED:
 W.P.(C) No. 16643/2022 & batch
                                  :4:


             THE AUTHORIZED OFFICER
             THE FEDERAL BANK LTD., LCRD KOZHIKODE DIVISION, 1ST
             FLOOR, FEDERAL TOWERS, ARAIYIDATHUPALAM, KOZHIKODE,
             KERALA 673 016

             [ADDL. R6 IMPLEADED AS PER ORDER DATED 21.12.2022 IN
             I.A.4/2022 IN WP(C)16798/2022.]
             BY ADVS.
             MOHAN JACOB GEORGE
             P.V.PARVATHY (P-41)
             REENA THOMAS
             NIGI GEORGE
             SRI. K.V. MANOJ KUMAR



THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 16.03.2023,

ALONG WITH WP(C).16643/2022, THE COURT ON 29.03.2023 DELIVERED THE

FOLLOWING:
 W.P.(C) No. 16643/2022 & batch
                                       :5:



                          SHAJI P. CHALY, J.
         ---------------------------------------------------------
                  W.P.(C). Nos.16643 & 16798 of 2022
         ---------------------------------------------------------
                  Dated this the 29th day of March, 2023.

                             JUDGMENT

The captioned writ petitions are filed by one and the same

petitioner, who is a contractor engaged by the Kerala Road Fund

Board, respondent No.2, to carry out the works "KIIFB-

Improvements to Thamarassery-Varattiakkal road in Kozhikode

District", and "KIIFB-2016-17 Improvement of Kaithapoyil-

Kodenchery-Agastianmuzhi Road Km 0/000 to 21/200 in Kozhikode

District" respectively. Accordingly, Exhibit P3 agreements were

executed on 03.02.2018 and 13.09.2018 respectively, and the work

was to be completed within 18 months from the date of execution of

the agreement.

2. In W.P.(C) No. 16643 of 2022, the petitioner challenges

Exhibit P18 order dated 08.04.2022 issued by the Project Director,

Kerala Road Fund Board-- respondent No.2, terminating the work at

the risk and cost of the petitioner. It is stated therein that the site

was handed over to the contractor on 12.02.2018 with a period of

completion of 18 months. It is also stated that the fourth extension

of time of completion of the work was granted upto 31.12.2021. W.P.(C) No. 16643/2022 & batch

But, supplementary agreement was not executed as the validity of

the bank guarantee was not extended. It is further stated that the

extension of time of completion was requested upto 31.03.2022.

However, the Team Leader, as per letter dated 01.02.2022,

reported that there are many concrete works still pending and BC

works in the first reach of 14.10 Km and second stretch of 2.75 km.

are also not arranged by the petitioner contractor.

3. That apart, it is stated that as per a letter dated

05.03.2022, the Executive Engineer reported that repeated

instructions were given to the contractor to carry out the BC works

and balance side protection work; but the contractor did not start

the balance work at the site to date. It is further stated that two

notices were issued from the office of the second respondent dated

01.12.2021 and 10.01.2022 on the slow progress of the work and

directed to complete the work at an early date benefiting the

climatic condition; but the contractor did not show the proportionate

progress during the extended period of time of completion and

therefore, the undue delay in executing the work could not be

accepted further.

4. Insofar as W.P.(C) No. 16798 of 2022 is concerned, the

petitioner challenges Exhibit P19 order dated 08.04.2022 issued by

the Project Director, Kerala Road Fund Board, respondent No.2 W.P.(C) No. 16643/2022 & batch

terminating the work at the risk and cost of the petitioner

contractor. Therein also, it is stated that the site was handed over

to the contractor on 22.09.2018 with a period of completion of 18

months. It is further stated that the third extension of time of

completion for the work granted upto 31.03.2022; that the

Executive Engineer, as per letter dated 10.03.2022 reported that

even after the repeated meetings and instructions given to the

contractor, the work was progressing slowly; that the contractor has

not effectively utilized dry season from December, 2021 to March,

2022 by stating false promises and other reasons; and that the

progress achieved during the said time is not satisfactory.

5. That apart, it is specified that notices dated 20.10.2021

and 30.11.2021 were issued from the office of the Project Director

on the slow progress of the work, and final notices prior to the

termination was issued on 14.03.2022; however, no measures are

seen taken by the contractor to complete the work within the

scheduled time benefiting climatic conditions.

6. When the writ petitions came up for admission, invocation

of bank guarantee was restrained as per order dated 24.05.2022

which was being periodically extended and the same is in force now.

The paramount contention advanced by the petitioner is that there

were severe hindrances, such as electric posts, water pipeline, trees W.P.(C) No. 16643/2022 & batch

etc. along the sites, which were not shifted. That apart, it is

contended that there was delay in obtaining consent for widening

from the respective land owners.

7. The sum and substance of the contention advanced by the

petitioner is that the work was delayed not due to the laches on the

part of the petitioner, but, due to default on the part of the

respondents in timely removing the hindrances along the site. It is

further pointed out that even though several letters were issued by

the petitioner to the second respondent wherein the issue was

updated, no action was taken. Therefore it is the contention of the

petitioner that the work was delayed due to the Covid-19 pandemic,

and since the hindrances were removed by the respondents only

during July, 2021.

8. It is also the contention of the petitioner that he was

compelled to execute supplementary agreements to extend the time

of completion of the work on various occasions. It is further

submitted that subsequently also, the petitioner applied for

extensions after the expiry of the time of completion, and the work

was being carried on. It is also the case of the petitioner that the

request of the petitioner was endorsed and recommended by all

concerned engineers. However, none of them were approved by

the second respondent. It is the further case of the petitioner that W.P.(C) No. 16643/2022 & batch

he has completed 93% and 76% respectively of the works awarded

to him.

9. It is further contended that it is a well settled position in

law that when there is a contractual dispute, the party alleging

breach cannot also be the arbiter as to whether or not the breach

has been committed. It is further contended that when there is a

dispute as to whether or not there has been a breach in the

conditions of a contract, the party alleging breach cannot determine

whether or not a breach has actually occurred and cannot take any

penal action against the other party. However, in the instant case,

the second respondent, being a party to the agreement, cannot

unilaterally determine whether the petitioner has committed any

default or take any penal action including assigning the risk and

cost of re-tendering to the petitioner and invoking the performance

securities provided by the petitioner. It is also contended that as

per clause 24 of the agreement, all disputes arising during the

implementation have to be settled through civil courts of applicable

jurisdiction.

10. In sum and substance, the contention advanced by the

petitioner is that it must be proved before a civil court of applicable

jurisdiction that there are sufficient grounds to assign the risk and

cost to the petitioner before the same can be done. It is also W.P.(C) No. 16643/2022 & batch

contended that the second respondent has failed to meet its

obligations under the agreements and the site was not handed over

free of hindrances which contributed heavily to the delay in the

work. Other contentions are also raised.

11. KIIFB, respondent No.3, has contended that it is only a

funding agency and it is the prerogative of the special purpose

vehicle, respondent No.2, to regulate the work in terms of the

agreement. Additional documents are also produced along with I.A.

No. 3 of 2022.

12. I have heard Sri. Santhosh Mathew for the petitioners,

Sri. K. V. Manoj Kumar, learned Special Government Pleader, and

Sri. S. Chandrasekharan Nair for KIIFB, and perused the pleadings

and material on record.

13. The sum and substance of the contention advanced by the

petitioner is that the Project Director, being a party to the contract,

is not vested with any powers to terminate the contract at the risk

and cost of the contractor. The Project Director is shown as the

employer in the agreement and the engineer is the team leader;

Executive Engineer, PWD Roads Division, Kozhikode is the

authorised representative. The General Conditions of Contract

shows that the employer is the party who will employ the contractor

to carry out the works. The Engineer is the person named in the W.P.(C) No. 16643/2022 & batch

Contract Data (Or any other competent person appointed and

notified to the contractor to act in replacement of the Engineer) who

is responsible for supervising the contractor, administering the

contract, certifying payments due to the contractor, issuing and

valuing variations to the contract, awarding extensions of time and

valuing the compensation events.

14. Clause 17 of the General Conditions of Contract deals with

'the works to be completed by the Intended Completion date' and

sub-clause 17.1 makes it clear that the contractor may commence

execution of the works on the start date and shall carry out the

works in accordance with the programmes submitted by the

contractor, as updated with the approval of the Engineer, and

complete them by the Intended Completion Date.

15. As per clause 36, the contractor is bound to carry out the

items in the Bill of Quantities item wise variation upto 25 percent

excess provided that the change does not exceed 1% of initial

contract price.

16. Clause 41 deals with payments and sub-clause 41.2

enumerates that payments shall be adjusted for deductions for

advance payments retention, other recoveries in terms of the

contract and taxes at source, as applicable under the law; and that W.P.(C) No. 16643/2022 & batch

the employer shall pay the contractor the amounts certified by the

engineer within 28 days of the date of each certificate.

17. Clause 42 deals with 'compensation events' and sub-

clause 42.1 enumerates 'the compensation events unless they are

caused by the contractor', which reads as follows:

42. Compensation Bvents

42.1. The following are compensation events unless they are caused by the Contractor.

(a) The Employer does not give access to a part of the sìte by the site possession date stated in the Contract Data.

(b) The Employer modified the schedule of other contractor in a way which affects the work of the contractor under the contract.

(c) The engineer orders a delay or does not issue drawings specifications or instructions required for execution of works on time.

(d) The Engineer instructs the Contractor to uncover or to carry out additional tests upon work which is then found to have no defects.

(e) The Engineer does not approve of a subcontract to be let, within 15 days.

(f) Ground conditions are substantially more adverse than could reasonably have been assumed before issuance of Letter of Acceptance from the information issued to Bidders (including the Site Investigation Reports), from information available publicly and from a visual îinspection of the site.

(g) The Engineer gives an instruction for dealing with an unforeseen condition caused by the Employer, or additional work required for safety or other reasons.

(h) Other contractors, public authorities, utilities or the Employer does not work within the dates and other constraints stated in the Contract, and they cause delay or extra cost to the Contractor.

(i) The advance payment is delayed, beyond 28 days after receipt of application and bank guarantee.

(j) The effect on the Contractor or any of the Employer's Risks.

(k) The Engineer unreasonably delays issuing a Certificate of completion.

(l) Other compensation events listed in the Contract Data or mentioned in the Contract.

18. Sub-clause 42.2 specifies that if a compensation event would

cause additional cost or would prevent the work being completed W.P.(C) No. 16643/2022 & batch

before the Intended Completion Date, the contract price shall be

increased and/or the Intended completion Date is extended, and the

engineer shall decide whether and by how much the Contract price

shall be increased and whether and by how much the Intended

completion Date shall be extended.

19. Clause 46 deals with 'liquidated damages' and clause 46.1

stipulates that the contractor shall pay liquidated damages to the

employer at the rate per day stated in the Contract Data for each

day that the Completion Date is later than the Intended Completion

Data (for the whole of the works or the milestone as stated in the

contract data); that the total amount of liquidated damages shall

not exceed the amount defined in the Contract Data; that the

employer may deduct liquidated damages from payments due to

the contractor; and that payment of liquidated damages does not

affect the contractor's other liabilities.

20. Clause 46.2 specifies that if the Intended Completion Date

is extended after liquidated damages have been paid, the Engineer

shall correct any overpayment of liquidated damages by the

Contractor by adjusting the next payment certificate, and the

contractor shall be paid interest on the over payment calculated

from the date of payment to the date of repayment at the rates W.P.(C) No. 16643/2022 & batch

specified in sub-clause 43.1

21. Sub-clause 43.3 states that if the contractor fails to

comply with the time for completion as stipulated in the tender,

then the contractor shall pay to the employer the relevant sum

stated in the Contract Data as Liquidated damages for such default

and not as penalty for every day or part of day which shall elapse

between relevant time for completion and the date stated in the

taking over certificate of the whole of the works on the relevant

section, subject to the limit stated in the Contract Data.

22. Clause 54 deals with 'termination' and sub-clause 54.1

specifically states that the employer or the contractor may

terminate the contract, if the other party causes a fundamental

breach of the contract. Clauses 54.2 deals with the fundamental

breaches of contract which shall include, but shall not be limited to,

and it reads as follows:

a) The contractor stops work for 28 days when no stoppage of work is shown on the current programme and the stoppage has not been authorized by the engineer;

b) the Engineer instructs the contractor to delay the progress of the works and the instruction is not withdrawn within 28 days;

c) the employer or the contractor is made bankrupt or goes into W.P.(C) No. 16643/2022 & batch

liquidation other than for a reconstruction or amalgamation;

d) a payment certified by the engineer is not paid by the employer to the contractor within 56 days of the date of the engineer's certificate;

e) the engineer gives notice that failure to correct a particular defect is a fundamental breach of contract and the contractor fails to correct it within a reasonable period of time determined by the engineer.

f) The contractor does not maintain a security which is required.

g) The contractor has dealyed the completion of works by the number of days for which the maximum amount of liquidated damages can be paid as defined in the contract data; and

h) if the contractor in the judgment of the employer has engaged in corrupt or fraudulent practices in completing for or in executing the contract.

23. Sub-clause 54.4 is a covenant empowering the employer to

terminate the contract for convenience notwithstanding the specific

instances pointed out in sub-clause 54.2. Sub-clause 54.5 makes it

clear that if the contract is terminated, the contractor shall stop

work immediately, make the site safe and secure and leave the site

as soon as reasonably possible.

24. Clause 55 deals with 'payment upon termination', and

sub-clause 55.1 specifies that if the contract is terminated because W.P.(C) No. 16643/2022 & batch

of a fundamental breach of contract by the contractor, the engineer

shall issue a certificate for the value of the work done less advance

payments received upto the date of issue of the certificate, less

other recoveries due in terms of the contract, less taxes due

deducted at source as per applicable law, and less the percentage to

apply to the work not completed as indicated in the Contract Data;

that additional liquidated damages shall not apply; and that if the

total amount due to the employer exceeds any payment due to the

contractor, the difference shall be a debt payable to the employer.

25. Sub-clause 55.2 makes it clear that if the contract is

terminated at the employer's convenience or because of a

fundamental breach of contract by the employer, the engineer shall

issue a certificate for the value of the work done, the cost of

balance material brought by the contractor and available at site, the

reasonable cost of removal of equipment, repatriation of the

contractor's personnel employed solely on the works, and the

contractor's costs of protecting and securing the works and less

advance payments received up to the date of the certificate, less

other recoveries due in terms of the contract and less taxes due to

be deducted at source as per applicable law.

26. Clause 57 deals with 'release from Performance' and sub- W.P.(C) No. 16643/2022 & batch

clause 57.1 states that if the contract is frustrated by the outbreak

of war or by any other event entirely outside the control of either

the employer or the contractor, the engineer shall certify that the

contract has been frustrated; that the contractor shall make the site

safe and stop work as quickly as possible after receiving the

certificate and shall be paid for all work carried out before receiving

it and for any work carried out afterwards to which the commitment

was made.

27. From the above , it is clear that the terms and conditions

of the agreement executed by and between the employer and the

contractor are definite. The petitioner did not have any complaint

with respect to the terms and conditions of the agreement executed

by and between the parties till the work was terminated by the

employer. Moreover, it is an admitted case that the period of

contract was extended by executing supplementary agreements on

various dates and even at that point of time, the petitioner did not

have a case that the terms and conditions of the contract are

unconscionable, illegal or void.

28. It is also clear that the agreement speaks about the

compensation events, if the employer commits default and also the

compensation events in the event the contractor makes default in W.P.(C) No. 16643/2022 & batch

execution of the work. The termination could be made by the

employer for his own fault and also due to the fault on the part of

the contractor. Therefore, the terms and conditions of the contract

are entered by and between the parties taking into account the

nature of the contract that had to be executed by the contractor.

29. Now, the fundamental and basic question remains to be

considered is whether as pointed out by the petitioner, the

employer has to resort to a civil remedy for the purpose of

terminating a contract. In that regard, the learned counsel for the

petitioner has advanced arguments that conditions in the PWD

Manual relied upon by the employer to terminate the contract are

merely administrative instructions and therefore, the said provisions

cannot overlook the law in respect of the termination of contract.

30. In support of the said contention, the learned counsel has

placed reliance on a Division Bench judgment of this Court in State

of Kerala v. Aboobacker Kutty [1992 (2) KLT 939], wherein

following the judgment of the Apex Court in Fernandez v. State of

Mysore (AIR 1967 SC 1753), it is held that the instructions

contained in the PWD Manual are merely administrative instructions

and not statutory rules.

31. In my considered opinion, the issue to be decided in this W.P.(C) No. 16643/2022 & batch

writ petition is entirely different. This is a case where the parties

have entered into an agreement which are having specific terms

and conditions with respect to each and every aspect, including the

termination of contract. Therefore, the provisions of the PWD

Manual would have to be read along with the terms and conditions

agreed by and between the parties.

32. Clause 2116.1 deals with 'termination due to default by

contractor', which states that as per General Conditions of Contract,

the agreement authority has the power to cancel the contract and

arrange the work otherwise in the event of default by the

contractor; that the agreement authority, in exercising the power

vested with him, shall follow the procedure outlined in the General

Conditions of the Contract; and that the damages and penalties

provided therein and applicable to the particular contract shall also

be realised in accordance with the General Conditions of Contract.

33. Clause 2116.2 dealing with 'termination of contract',

enumerates the circumstances under which the Department can

terminate the contract at the risk and cost of the contractor that: --

(i) if the contractor does not turn up for starting the work within the

specified period to take charge of the site after executing the

agreement; (ii) if the contractor does not show the proportionate W.P.(C) No. 16643/2022 & batch

progress during the extended period of time of completion; (iii) if

the contractor abandons the work after executing a portion without

genuine reason and does not resume or complete it even after

specific direction from the Department; (iv) fails to make

application for extension of time of completion in time; (v) the

licence of the contractor whose work has been terminated shall be

cancelled with immediate effect and shall be barred from quoting for

another work for a minimum period of five years. Contract licence

shall not be renewed in his name or different name of a binamy;

and (vi) a company or person or firm once terminated shall be

disqualified from participating in any tender in his name or by using

a different name or binamy. There shall also be a fine and forfeiture

of deposits.

34. Clause 2116.2.1 of the PWD Manual Revised Edition, 2012

deal with 'realisation of loss on account of termination', which

clearly specifies that an amount equal to 30% of the cost of the

remaining works at agreed rates of the terminated contract shall be

recovered from the defaulted contractor towards the risk and cost;

that the contractor shall be directed to remit the risk and cost

amount within three months; that there is no need to wait till the

work is arranged alternatively through another contractor and the

total loss sustainable due to the default of the original contractor is W.P.(C) No. 16643/2022 & batch

assessed; that such loss, if any, shall be realised after completion of

the work; and that if he fails to remit the amount within the period,

the steps enumerated thereunder can be adopted for realisation of

loss. It also specified that the amount can be realised from the

EMD/security; Bill amount/ retention if any due to the contract;

any dues from department to the contract; and Bank Guarantee/

Performance Guarantee or by filling civil suit against the contractor.

35. That apart, clause 2116.2.2 deals with 'revoking of

termination', which specifies that the contract for a work on

terminated by the agreement authority can be revoked by the

immediate superior officer, if the contractor expresses his

willingness at later date to complete the balance work; but

performance guarantee of 30% of the balance work to be completed

shall be deposited; and the said performance guarantee shall be

released only on completion of the work. In such a case, the

contractor is bound to do the work at the originally agreed rates for

which agreement authority shall execute a supplemental agreement

with balance schedule and fresh time of completion.

36. Therefore, on a conjoint reading of the agreement and the

provisions of the PWD Manual specified above, it is clear that power

is vested with the employer to terminate the contract. It is not by W.P.(C) No. 16643/2022 & batch

invocation of the provisions of the PWD Manual alone, the

termination was effected by the employer. But, it was also taking

into account the terms and conditions of the agreement mutually

agreed upon by and between the parties.

37. Therefore, it is not a case where the petitioner is not

without a remedy, if an action of termination is employed by the

employer. It is also clear from clause 2118 of the PWD Manual

dealing with the 'settlement of disputes and differences' that the

agreement authority as well as the contractor shall follow the

procedure contained in the relevant clauses in the General

Conditions of Contract for settling the disputes arising out of the

execution of the contract.

38. The issue of the legal effect of the Public Works

Department Code was considered by the Apex Court in Fernandez

(supra), wherein the question considered was whether the

instructions in the Code have any statutory force, and if they have

no statutory force, whether they confer any right on anybody; and if

so, whether a tenderer can claim any rights on the basis of the

administrative instructions; and finally it was held that the State

Government can take executive action in all matters in which the

Legislature of the State can pass laws; but Article 162 by itself does W.P.(C) No. 16643/2022 & batch

not confer any rule making power on the State Government in that

behalf; and therefore, it was held that the instructions contained in

the Code are mere administrative instructions and are not statutory

rules.

39. But, this is a case where the action was initiated on the

basis of the terms and conditions of contract entered into by and

between the parties. Therefore, that can only be treated as a

contract executed by and between the parties in terms of the

provisions of the Indian Contract Act, 1872. Viewed so, once an

offer was made by the employer and accepted by the contractor

and an agreement was executed by and between the parties, one of

the parties cannot turn around and attack some of the terms and

conditions of the agreement, but for the agreement vitiated by

undue influence, fraud, misrepresentation, without free consent,

mistake of fact or it is void consequent to any terms and conditions

forbidden by law.

40. Further, the petitioner does not have a case that any of

the agreement conditions executed by and between the parties is

void in nature. The issue with respect to the binding nature of the

terms and conditions of an agreement executed by and between the

State or other authority with private persons was considered by the W.P.(C) No. 16643/2022 & batch

Apex Court in Bareilly Development Authority and Ors. v. Ajay

Pal Singh and Ors. [(1989) 2 SCC 116], Radhakrishna Agarwal

and Ors. Vs. State of Bihar and Ors. [(1977) 3 SCC 457],

Premji Bhai Parmar and Ors. Vs. Delhi Development

Authority and Ors. [1980(2) SCC 129] and Divisional Forest

Officer v. Biswanath Tea Co. Ltd. [(1981) 3 SCC 238] and it is

held that the contract entered into by and between the State and

the persons aggrieved is non statutory and purely contractual and

the rights are governed only by the terms of the contract and no

writ or order can be issued under Article 226 of the Constitution of

India, so as to compel the authorities to permit a breach of

contract, pure and simple.

41. However, conducting an elaborate survey of the earlier

Supreme Court judgments on the issue relating to a non statutory

contract, the Apex Court had rendered a judgment in M.P. Power

Management Company Limited, Jabalpur v. Sky Power

Southeast Solar India Private Limited and others [2023) 2

SCC 703] holding that the principle laid down in Bareilly

Development Authority (supra) that in the case of a non-

statutory contract, the rights are governed only by the terms of the

contract and the decisions, which are purported to be followed, may

not continue to hold good, in the light of what has been laid down in W.P.(C) No. 16643/2022 & batch

ABL International Limited and another v. Export Credit

Guarantee Corporation of India [(2004) 3 SCC 553] (supra),

and as followed in the recent judgment in State of U.P. v. Sudhir

Kumar Singh and Ors.[2020 SCC Online SC 847]. After finding

so, it was held thus:

82.1. It is, undoubtedly, true that the writ jurisdiction is a public law remedy. A matter, which lies entirely within a private realm of affairs of public body, may not lend itself for being dealt with under the writ jurisdiction of the Court.

...

82.12. In a case the State is a party to the contract and a breach of a contract is alleged against the State, a civil action in the appropriate forum is, undoubtedly, maintainable. But this is not the end of the matter. Having regard to the position of the State and its duty to act fairly and to eschew arbitrariness in all its actions, resort to the constitutional remedy on the cause of action, that the action is arbitrary, is permissible (see in this regard Shrilekha Vidyarthi v. State of U.P. [Shrilekha Vidyarthi v.

State of U.P., (1991) 1 SCC 212 : 1991 SCC (L&S) 742] ). However, it must be made clear that every case involving breach of contract by the State, cannot be dressed up and disguised as a case of arbitrary State action. While the concept of an arbitrary action or inaction cannot be cribbed or confined to any immutable mantra, and must be laid bare, with reference to the facts of each case, it cannot be a mere allegation of breach of contract that would suffice. What must be involved in the case W.P.(C) No. 16643/2022 & batch

must be action/inaction, which must be palpably unreasonable or absolutely irrational and bereft of any principle. An action, which is completely mala fide, can hardly be described as a fair action and may, depending on the facts, amount to arbitrary action. The question must be posed and answered by the Court and all we intend to lay down is that there is a discretion available to the Court to grant relief in appropriate cases.

82.13. A lodestar, which may illumine the path of the Court, would be the dimension of public interest subserved by the Court interfering in the matter, rather than relegating the matter to the alternate forum."

42. Taking into account the above principles of law and

bearing in mind the terms and conditions of the agreement

executed by and between the parties, it cannot be said that the

termination of the contracts by the agreement authority is bad or

illegal. This I say because, the authority has granted sufficient

time to the petitioner, even by extending the agreement period

by executing supplementary agreements. The rest of the aspects

put forth by the petitioner in this writ petition is premature in

nature. Moreover, admittedly, consequent to the execution of the

agreement, the parties have entered into specific terms and

conditions by which the employer as well as the contractor are

given the liberty to terminate the contract in the circumstances

specified in the agreement executed by and between the parties. W.P.(C) No. 16643/2022 & batch

43. Considering the facts and figures so, I do not think, the

petitioner is entitled to get any reliefs as are sought for in the writ

petitions against Exhibits P18 and P19 termination orders made by

the Project Director--the agreement authority.

Needless to say, writ petitions fail and accordingly, they are

dismissed. However, I make it clear that all the issues with respect

to the payment due to the petitioner; the contentions raised by the

petitioner apprehending further action, and the contentions with

respect to the power of quantification of the damages by the

employer, are all left open.

sd/- SHAJI P. CHALY, JUDGE.

Rv W.P.(C) No. 16643/2022 & batch

APPENDIX OF WP(C) 16643/2022

PETITIONER'S EXHIBITS:

Exhibit P1 TRUE COPY OF NOTICE INVITING TENDER NO. PMU-

KRFB/T-07/2017-18 DATED 04.10.2017 ISSUED BY THE 2ND RESPONDENT FOR THE WORK "KIIFB IMPROVEMENTS TO THAMARASSERY-VARATTIAKKAL ROAD IN KOZHIKODE DISTRICT".

Exhibit P2 TRUE COPY OF THE LETTER OF ACCEPTANCE DATED 13.12.2017 ISSUED BY THE 2ND RESPONDENT IN FAVOUR OF THE PETITIONER.

Exhibit P3 TRUE COPY OF THE RELEVANT EXTRACTS OF THE AGREEMENT DATED 03.02.2018 ENTERED INTO BETWEEN THE PETITIONER AND RESPONDENT.

Exhibit P4 TRUE EXTRACT COPY OF THE PETITIONER FIRM'S DETAILS FROM THE REGISTRAR OF PARTNERSHIPS. Exhibit P5 TRUE COPY OF THE ORDER NO. A2/824/2018 OF THE SUPERINTENDING ENGINEER, PWD DATED 30.04.2018.

Exhibit P6 TRUE COPY OF THE PETITIONER'S LETTER TO THE 2ND RESPONDENT DATED 20.02.2018.

Exhibit P7 TRUE COPY OF THE PETITIONER'S LETTER TO THE 2ND RESPONDENT DATED 19.06.2019.

Exhibit P8 TRUE COPY OF THE PETITIONER'S LETTER TO THE 2ND RESPONDENT DATED 12.03.2021.

Exhibit P9 TRUE COPY OF SUPPLEMENTAL AGREEMENT NO. 1 DATED 24.09.2019 EXECUTED BETWEEN THE PETITIONER AND 2ND RESPONDENT.

Exhibit P10 TRUE COPY OF SUPPLEMENTAL AGREEMENT NO. 2 DATED 01.01.2020 EXECUTED BETWEEN THE PETITIONER AND 2ND RESPONDENT.

Exhibit P11 TRUE COPY OF SUPPLEMENTAL AGREEMENT NO. 4 DATED 16.09.2020 EXECUTED BETWEEN THE PETITIONER AND 2ND RESPONDENT.

Exhibit P12 TRUE COPY OF THE MOST RECENT EXTENSION REQUEST DATED 20.12.2021 SENT BY THE PETITIONER TO THE RESPONDENTS.

Exhibit P13 TRUE COPY OF THE FIRST NOTICE PRIOR TO TERMINATION ISSUED BY THE 2ND RESPONDENT DATED 01.12.2021.

Exhibit P14 TRUE COPY OF THE PETITIONER'S REPLY DATED 28.12.2021.

Exhibit P15 TRUE COPY OF THE SUPPLEMENTAL AGREEMENT NO. 3 DATED 13.03.2020 EXECUTED BETWEEN THE PETITIONER AND 2ND RESPONDENT.

Exhibit P16 TRUE COPY OF THE RELEVANT EXTRACTS OF THE W.P.(C) No. 16643/2022 & batch

ESTIMATE REPORT SUBMITTED ON REVISED 20.12.2021 BY THE 5TH RESPONDENT.

Exhibit P17 TRUE COPY OF THE FINAL NOTICE PRIOR TO TERMINATION DATED 10.01.2022 ISSUED BY THE 2ND RESPONDENT.

Exhibit P18 TRUE COPY OF THE ORDER NO.06/PWD004-18/PD/PMU-KRFB/137R/KKD/2017 DATED 08.04.2022 ISSUED BY THE 2ND RESPONDENT.

Exhibit P19 TRUE COPY OF THE REPRESENTATION DATED 21.04.2022 SUBMITTED BY THE PETITIONER BEFORE THE 1 RESPONDENT'S MINISTER FOR PUBLIC WORKS. Exhibit P20 TRUE COPY OF THE LETTER SENT BY THE 5TH RESPONDENT TO THE 4TH RESPONDENT.

Exhibit P21 TRUE COPY OF THE PETITIONER'S LETTER SUBMITTING THE 8TH AND PART BILL TO THE 5TH RESPONDENT DATED 12.05.2022.

Exhibit P22 TRUE COPY OF THE LETTER OF THE 4TH RESPONDENT ALONG WITH RELEVANT EXTRACTS OF THE CERTIFIED BILL ACCOMPANYING.

Exhibit P23 TRUE COPY OF THE NOTICE DATED 24.11.2022 ISSUED TO THE PETITIONER BY THE AUTHORIZED OFFICER, THE FEDERAL BANK LTD, LCRD, KOZHIKODE.

Exhibit P24 TRUE COPY OF THE REPLY DATED 5.12.2022 TO EXT.

P23 ISSUED BY THE PETITIONER.

Exhibit P25 TRUE COPY OF THE EMAIL REPLY OF THE BANK TO EXT.P24 DATED 06.12.2022.

RESPONDENTS' EXHIBITS: NIL

True Copy

PS To Judge.

rv W.P.(C) No. 16643/2022 & batch

APPENDIX OF WP(C) 16798/2022

PETITIONER'S EXHIBITS:

Exhibit P1 TRUE COPY OF NOTICE INVITING TENDER NO. PMU-

KRFB/T07/2017-18 FOR THE WORK "KIIFB-2016-17 IMPROVEMENT OF KAITHAPOYILKODANCHERY- AGUSTHIAMUZHI ROAD KM 0/000 TO 21/200 IN KOZHIKODE DISTRICT DATED 07.05.2018 ISSUED BY THE. 2ND RESPONDENT.

Exhibit P2 TRUE COPY OF THE LETTER OF ACCEPTANCE DATED 23.08.2018 ISSUED BY THE 2ND RESPONDENT IN FAVOUR OF THE PETITIONER.

Exhibit P3 TRUE COPY OF THE RELEVANT EXTRACTS OF THE AGREEMENT DATED 13.09.2018 ENTERED INTO BETWEEN THE PETITIONER AND RESPONDENT.

Exhibit P4 TRUE COPY OF THE PETITIONER'S LETTER TO THE 2ND RESPONDENT DATED 29.08.2019.

Exhibit P5 TRUE COPY OF THE PETITIONER'S LETTER TO THE 2ND RESPONDENT DATED 18.09.2019.

Exhibit P6 TRUE COPY OF THE PETITIONER'S LETTER TO THE 2ND RESPONDENT DATED 18.09.2019.

Exhibit P7 TRUE COPY OF THE PETITIONER'S LETTER TO THE 2ND RESPONDENT DATED 11.02.2021.

Exhibit P8 TRUE COPY OF THE SUPPLEMENTAL AGREEMENT NO. 1 DATED 08.06.2020 EXECUTED BETWEEN THE PETITIONER AND THE 2ND RESPONDENT.

Exhibit P9 TRUE COPY OF THE SUPPLEMENTAL AGREEMENT NO. 2 DATED 11.08.2021 EXECUTED BETWEEN THE PETITIONER AND THE 2ND RESPONDENT.

Exhibit P10 TRUE COPY OF THE SUPPLEMENTAL AGREEMENT NO. 3 DATED 11.10.2021 EXECUTED BETWEEN THE PETITIONER AND THE 2ND RESPONDENT.

Exhibit P11 TRUE COPY OF THE FIRST NOTICE PRIOR TO TERMINATION ISSUED BY THE 2ND RESPONDENT DATED 20.10.2021.

Exhibit P12 TRUE COPY OF THE REPLY DATED 26.10.2021 SENT BY THE PETITIONER TO THE 2ND RESPONDENT.

Exhibit P13 TRUE COPY OF THE NOTICE DATED 30.11.2021 ISSUED BY THE 2ND RESPONDENT.

Exhibit P14 TRUE COPY OF THE REPLY DATED 21.12.2021 SENT BY THE PETITIONER TO THE 2ND RESPONDENT.

Exhibit P15 TRUE COPY OF THE EMAIL OF THE 2ND RESPONDENT TO THE PETITIONER.

Exhibit P16 TRUE COPY OF THE 2ND RESPONDENT'S NOTICE DATED 14.03.2022.

EXHIBIT P17 TRUE COPY OF THE REPRESENTATION DATED W.P.(C) No. 16643/2022 & batch

15.03.2022 SUBMITTED BY THE PETITIONER BEFORE THE 2ND RESPONDENT.

EXHIBIT P18 TRUE COPY OF THE LETTER DATED 23.03.2022 SENT BY THE PETITIONER TO THE 2ND RESPONDENT.

EXHIBIT P19 TRUE COPY OF THE 2ND RESPONDENT'S ORDER NO.

38/PWD004-100/PD/PMU-KRFB/137R/KKD/2018 DATED 08.04.2022.

EXHIBIT P20 TRUE COPY OF THE REPRESENTATION DATED 21.04.2022 SUBMITTED BY THE PETITIONER BEFORE THE FIRST RESPONDENT'S MINISTER FOR PUBLIC WORKS.

EXHIBIT P21 TRUE COPY OF THE RELEVANT EXTRACTS LETTER OF THE 5TH RESPONDENT TO THE 4TH RESPONDENT DATED 17.03.2022.

EXHIBIT P22 TRUE COPY OF THE PETITIONER'S LETTER SUBMITTING THE 8TH PART BILL DATED 28.04.2022. EXHIBIT P23 TRUE COPY OF THE LETTER OF THE CONSULTANT ON THE PROJECT FORWARDING THE BILL TO THE 5TH RESPONDENT.

EXHIBIT P24 TRUE COPY OF THE PETITIONER'S LETTER DATED 19.05.2022 REQUESTING MEASUREMENT AND CERTIFICATION OF THE UNBILLED WORK.

Exhibit P25 TRUE COPY OF THE RELEVANT EXTRACTS OF THE CERTIFIED BILL FORWARDED ON 17.03.2022 ALONG WITH EXT. P21.

Exhibit P26 TRUE COPY OF THE LETTER OF THE 5TH RESPONDENT DATED 29.06.2022 ALONG WITH RELEVANT EXTRACTS OF THE CERTIFIED BILL INCLUDED THEREWITH.

Exhibit P27 TRUE COPY OF THE COMMUNICATION DATED 21.11.2022 OF THE 5TH RESPONDENT TO THE 4TH RESPONDENT ALONG WITH RELEVANT EXTRACTS OF THE CERTIFIED BILL INCLUDED THEREWITH.

Exhibit P28 TRUE COPY OF THE NOTICE DATED 24.11.2022 ISSUED TO THE PETITIONER BY THE AUTHORIZED OFFICER, THE FEDERAL BANK LTD, LCRD, KOZHIKODE.

Exhibit P29 TRUE COPY OF THE REPLY DATED 05.12.2022 TO EXT.

P 28 ISSUED BY THE PETITIONER.

Exhibit P30 TRUE COPY OF THE EMAIL REPLY OF THE BANK TO EXT.P29.

RESPONDENTS' EXHIBITS: NIL True Copy

PS To Judge.

rv

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter