Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

M/S Mecpro Infratech Pvt Ltd vs Alangad Grama Panchayath
2023 Latest Caselaw 6043 Ker

Citation : 2023 Latest Caselaw 6043 Ker
Judgement Date : 9 June, 2023

Kerala High Court
M/S Mecpro Infratech Pvt Ltd vs Alangad Grama Panchayath on 9 June, 2023
             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                              PRESENT
          THE HONOURABLE MR.JUSTICE MOHAMMED NIAS C.P.
     FRIDAY, THE 9TH DAY OF JUNE 2023 / 19TH JYAISHTA, 1945
                      WP(C) NO. 28085 OF 2013
PETITIONER:

             M/S MECPRO INFRATECH PVT LTD
             32/1487 B2, 2ND FLOOR, PALARIVATTAM P.O.,
             ERNAKULAM, COCHIN-682025, REPRESENTED BY ITS
             AUTHORISED SIGNATORY, RAJAN SKHARIYA,
             S/O.P.U,JOHN.
             BY ADV SRI.PEEYUS A.KOTTAM


RESPONDENTS:

     1       ALANGAD GRAMA PANCHAYATH
             NEERIKODE P.O., ALUVA TALUK, ERNAKULAM DISTRICT,
             PINCODE-683513, REPRESENTED BY ITS SECRETARY.
     2       THE SECRETARY
             ALANGAD GRAMA PANCHAYATH, NEERIKODE P.O., ALUVA
             TALUK, ERNAKULAM DISTRICT, PINCODE-683513.
     3       THE REVENUE DIVISIONAL OFFICER
             FORT COCHIN, PINCODE-682001.
     4       THE PRINCIPAL AGRICULTURAL OFFICER
             ERNAKULAM, PINCODE-682011.
             BY ADVS.
             SRI.DINESH MATHEW J.MURICKEN
             SR.GOVERNMENT PLEADER SMT.VINITHA.B



      THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION
ON   01.06.2023,    THE   COURT   ON    09.06.2023   DELIVERED   THE
FOLLOWING:
 WP(C)No.28085 of 2013
                                                2



                             MOHAMMED NIAS. C.P.,J
                                      ------------
                               WP(C)No.28085 of 2013
                              - - - - - - - - - - - - - - - - - - ----
                          Dated this the 9th day of June, 2023


                                        JUDGMENT

Petitioner is stated to be the owner in possession of 22.41 Ares of

the property comprised in Survey Nos.470/1A, 489/10, 490/1A1, 490/1B,

490/1A2, 480/1A, 489/10, 490/2, 490/3, 466/7, 466/8 and 466/9 purchased

as per registered Sale Deed Nos.983/2011, 982/2011, 898/2011,

4409/2011, 3538/2010, 3858/2010 of Alangad Sub Registrar Office having

purchased the same from Mathew P.Jose, Davis Jose, M.C.Thomas and

O.U.Zakir, who had submitted an application under the provisions of the

Kerala Land Utilisation Order dated 26.03.2012 before the 3rd

respondent-Revenue Divisional Office, Fort Kochi, seeking permission for

construction and developmental activities in the abovementioned

properties. By order dated 31.05.2013, the 3rd respondent-RDO passed

Ext.P1 order lifting the prohibitory order issued against conversion and

reclamation of the land in question, stating that all the reports showed that

the applied land had already been converted/reclaimed and hence no

further reclamation is necessary. It was also observed regarding the

construction and developmental activities that it was open to the applicant

to approach the local bodies concerned as per the rules. In Ext.P1, the 3rd

respondent also held that since the period when the conversion was made WP(C)No.28085 of 2013

is in dispute, the Principal Agricultural Officer, Ernakulam, will find out the

approximate period. Accordingly, the Principal Agricultural Officer,

Ernakulam, after conducting an enquiry passed an order on 3.8.2012,

Ext.P2 stating that the original conversion could have been made at least

ten years back.

2. Based on Exts.P1 and P2, the petitioner submitted an application

for a development permit before the first respondent Panchayath by

Ext.P3. However, the same was rejected by Ext P4 order, stating that the

property in question is described as 'nilam' in the revenue records, which

was challenged before this Court in WP(C)No.14919/2013, wherein this

Court, by Ext P5 judgment set aside the order impugned therein with a

direction to the Panchayath to consider the application submitted by the

petitioner afresh after conducting an inspection of the land of the

petitioner to verify whether the same continues to be a paddy land as

described in the revenue records or whether that the conversion was made

prior to the coming into force of the Kerala Conservation of Paddy Land

and Wet Land Act, 2008 and to pass appropriate orders on the application.

In spite of this judgment, by Ext.P6, the Secretary of the first respondent,

Panchayath, again rejected the request stating the same reason as in

Ext.P4 and passed Ext.P6 order. This is challenged by the petitioner

primarily contending that the petitioner's property was lying as dry land

even before the petitioner's purchase and sale deed also noticed the same.

It is also stated that Exts.P1 and P2 also reinforce the fact that the WP(C)No.28085 of 2013

petitioner's land cannot be treated as either a paddy land or a wetland,

and Ext.P6 order falls in the teeth of Ext.P5 judgment and accordingly

prays for quashing Ext.P6 order.

2. A counter affidavit has been filed on behalf of the third

respondent stating that the filling of the land in the instant case was done

unauthorizedly and disregarding the orders of prohibition issued from the

office of the third respondent. It is also stated that the reports got through

the Village Officer and the Agricultural Officer, Alangad also reported

about the illegal filling of paddy fields and water sources, and the

properties in question were included in the draft data bank prepared as

per the provisions of the Kerala Conservation of Paddy Land and Wet Land

Act, 2008.

3. The first respondent Panchayath has also filed a counter affidavit

stating that the lands in question is a paddy field as per the village

records, and it was converted in the year 2009-2010 and that on account of

this act that a stop memo has been issued in respect of the properties. It

is further stated that the property was included in the draft data bank

prepared under the provisions of the Act and thus justified Ext.P6 order. It

is also the contention of the Panchayath that going by Ext.P1 order, the

petitioner was to approach the Government for regularization of the

unauthorized conversion of the land, and since the same has not been done

so far, Ext.P6 order passed refusing permission for construction is in order. WP(C)No.28085 of 2013

4. I have heard Sri. Peeyus A. Kottam, the learned counsel for the

petitioner, learned standing counsel for respondents 1 and 2 and the

learned Government Pleader.

5. It cannot be disputed that by Ext.P1 order, the third respondent-

RDO found that the land in question had already been converted/reclaimed

and that no further reclamation is necessitated. The only observation in

Ext.P1, which calls for a factual enquiry, was the period of conversion,

which the Principal Agricultural Officer, Ernakulam, was left to decide. In

such circumstances, the third respondent held in Ext.P1 that the

petitioners are at liberty to approach the Government for regularization of

the unauthorised conversion of the reclaimed land in accordance with the

orders then in force.

6. Learned counsel for the petitioner is right in his submission that

the consideration by the first respondent ought to have been under Clause

6 of the Kerala Land Utilization Order, 1967 (for short 'the KLU Order')

and on account of his failure to pass orders strictly in accordance with the

same, the Panchayath is taking advantage and declining the permit sought

for construction by Exts.P4 and P6. It is relevant to note that In spite of

Ext.P4 order being quashed by Ext.P5 judgment of this Court, the

Panchayath has reiterated the same stand again in Ext.P6, which is clearly

an error. Since the petitioner's application for permission under Clause 6

of the KLU Order is prior to the coming into force of the Act, neither WP(C)No.28085 of 2013

Section 27A nor 27C (amended by Kerala Conservation of Paddy Land and

Wet Land (Amendment Act) i.e, Act 29 of 2018) which came into force only

on 30.12.2017, has any application in the instant case.

In the above circumstances, I quash Ext.P6 order passed by the

Panchayath. The third respondent-RDO is directed to reconsider Ext.P1

and pass orders strictly in accordance with Clause 6 of the KLU Order as

the application was made prior to coming into force of the Amended Act

29 of Act 2018. A decision in this regard will be taken with notice to the

petitioner at any rate within four months from the date of receipt of a

copy of this judgment. It is declared that the third respondent-RDO has to

reconsider Ext.P1 without referring to the provisions of the Amended Act

29 of 2018. Based on the decision to be passed by the third respondent-

RDO, the first respondent Panchayath is directed to reconsider the

application for development submitted by the petitioner within two months

from the date of receipt of the orders passed by the third respondent-RDO

as directed above.

The writ petition is disposed of as above.

Sd/- MOHAMMED NIAS. C.P.,JUDGE

dlK 3.6.2023 WP(C)No.28085 of 2013

APPENDIX OF WP(C) 28085/2013

PETITIONER'S EXHIBITS EXHIBIT P1: COPY OF PROCEEDINGS NO.K-242/10/K. DIS DATED 31.05.2012 ISSUED BY THE REVENUE DIVISIONAL OFFICER, FORT COCHIN TO THE PETITIONER.

EXHIBIT P2: COPY OF THE LETTER NO.TA(1)4568/12 DATED 03.08.2012 ISSUED BY PRINCIPAL AGRICULTURAL OFFICER, ERNAKULAM TO THE PREDECESSORS IN TITLE OF THE PETITIONER. EXHIBIT P3: COPY OF APPLICATION FOR DEVELOPMENT PERMIT DATED 31.05.2013 SUBMITTED BY PETITIONER BEFOFE THE 1ST RESPONDENT PANCHAYATH.

EXHIBIT P4: COPY OF ORDER NO.A2-4554/13 DATED 03.06.2013 ISSUED BY 1ST RESPONDENT PANCHAYATH TO THE PETITIONER. EXHIBIT P5: COPY OF JUDGMENT DATED 05.09.2013 OF THIS HONOURABLE COURT IN WPC NO.14919/2013(L).

EXHIBIT P6: COPY OF ORDER NO.A4-4554/13 DATED 28.10.2013 ISSUED BY 1ST RESPONDENT PANCHAYATH TO THE PETITIONER. EXHIBIT P7: TRUE PHOTOGRAPHS SHOWING THE LIE AND NATURE OF APPLIED LAND OF THE PETITIONER.

RESPONDENTS EXHIBITS EXHIBIT R1(a): TRUE COPY OF THE LETTER SEND BY THE 2ND RESPONDENT TO THE AGRICULTURAL OFFICER KRISHIBHAVAN, ALANGAD DATED 10.10.2013 EXHIBIT R1(b): TRUE COPY OF THE LETTER SEND BY THE AGRICULTURAL OFFICER TO THE 2ND RESPONDENT DATED 10.10.2013 EXHIBIT R1(c): TRUE COPY OF THE PROCEEDINGS OF THE LOVAL LEVEL MONITORING COMMITTEE REFERRED TO IN EXHIBIT R1(b) DATED 15.06.2010 EXHIBIT R1(d): TRUE COPY OF THE LETTER SEND BY THE VILALGE WP(C)No.28085 of 2013

OFFICER TO THE 2ND RESPONDENT DATED 28.10.2013

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter