Monday, 04, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

K.C.Antony vs State Of Kerala
2023 Latest Caselaw 2181 Ker

Citation : 2023 Latest Caselaw 2181 Ker
Judgement Date : 10 February, 2023

Kerala High Court
K.C.Antony vs State Of Kerala on 10 February, 2023
               IN THE HIGH COURT OF KERALA AT ERNAKULAM
                               PRESENT
          THE HONOURABLE MR. JUSTICE A.MUHAMED MUSTAQUE
                                  &
         THE HONOURABLE MRS. JUSTICE SHOBA ANNAMMA EAPEN
    FRIDAY, THE 10TH DAY OF FEBRUARY 2023 / 21ST MAGHA, 1944
                         WA NO. 2319 OF 2019
   AGAINST THE JUDGMENTWP(C) 4786/2019 OF HIGH COURT OF KERALA
APPELLANT/S:

          K.C.ANTONY,
          AGED 60 YEARS
          S/O.LATE CHACKO, CONTRACTOR, KAITHACKAL HOUSE,
          CHEMMALAMATTOM P.O., ERATTUPETTA - VIA, KOTTAYAM
          DISTRICT, PIN-686529.
          BY ADVS.
          JACOB P.ALEX
          SRI.JOSEPH P.ALEX
          SHRI.MANU SANKAR P.
          ANISH JOSE ANTONY


RESPONDENT/S:

    1     STATE OF KERALA,
          REPRESENTED BY ITS SECRETARY TO GOVERNMENT, PUBLIC
          WORKS DEPARTMENT, GOVERNMENT SECRETARIAT,
          THIRUVANANTHAPURAM-695001.
    2     THE CHIEF ENGINEER,
          PUBLIC WORKS DEPARTMENT, ROADS AND BRIDGES, PUBLIC
          OFFICES, MUSEUM P.O., THIRUVANANTHAPURAM-695033.
    3     THE SUPERINTENDING ENGINEER,
          PWD (ROADS AND BRIDGES), SOUTH CIRCLE,
          THIRUVANANTHAPURAM-695033.
 W.A.No.2319 of 2019

                               -:2:-


     4     THE EXECUTIVE ENGINEER,
           PWD (ROADS AND BRIDGES), KOTTAYAM, PIN-686001.
     5     KERALA STATE CONSTRUCTION CORPORATION,
           OLD PWD STORE COMPOUND, PMG, VIKAS BHAVAN P.O.,
           BEHIND BSNL OFFICE, THIRUVANANTHAPURAM-695033,
           REPRESENTED BY ITS GENERAL MANAGER .
     6     K.R.RADHAKRISHNAN,
           KIZHAKKEMURAYIL HOUSE, KADANADU PO, AMICOMPU,
           KOTTAYAM, PIN-686653.
           BY ADVS.
           GOVERNMENT PLEADER (BY ORDER)
           SRI.M.RAJAGOPALAN NAIR FOR R5
           SRI.G.BIJU
           SHRI GEORGE MATHEW FOR R6
           GOVERNMENT PLEADER SHRI K.V.MANOJ FOR R1 TO R4



      THIS WRIT APPEAL HAVING BEEN FINALLY HEARD ON 7.2.2023, THE
COURT ON 10/2/2023 DELIVERED THE FOLLOWING:
 A.MUHAMED MUSTAQUE & SHOBA ANNAMMA EAPEN, JJ.
    -----------------------------------------
                 W.A.No.2319/2019
    -----------------------------------------
    Dated this the 10th day of February, 2023

                 J U D G M E N T

A.Muhamed Mustaque, J.

The fate of this appeal, at the instance of

the writ petitioner, is based on a turn of events

subsequent to the disposal of the writ petition.

2. The appellant is a contractor for

executing the work relating to a road of a project

sponsored by NABARD. The contract was terminated

at the risk and cost of the appellant and another

contractor was engaged to complete the work. The

work was awarded to the Kerala State Construction

Corporation. The Corporation in turn awarded the

work to the appellant. The challenge regarding W.A.No.2319 of 2019

termination of the contract was unsuccessful as

well as the claim for the bills for the work

executed by the appellant including the release of

security deposit.

3. We are not detailing the facts involved in

this case obviously for the reason that we are now

deciding this appeal based on admitted facts which

are borne on the record.

4. Admittedly, as per 7th and part bill, the

appellant was entitled to Rs.58,23,726/-. As seen

from Annexure-A12, PWD already collected this

amount from NABARD. It is also admitted in the

affidavit filed along with I.A.No.2/2022 by PWD

before this Court on 3/12/2019 that a sum of

Rs.13,09,411/- is due under the 8th and final bill.

As seen from Annexure-A10 produced along with

I.A.No.1/2022 in the writ appeal, a sum of

Rs.2,42,688.77 has been quantified as damage

suffered. No other claim has been raised by PWD

from the appellant. No one has a case that the W.A.No.2319 of 2019

new contractor engaged after the termination of

the contract with the appellant has done the work

covered by the part and 7th bill and 8th and final

bill above.

5. The learned Government Pleader placed

reliance on PWD manual, revised in 2012, which

reads thus :

2116.2.1. Realisation of loss on account of termination An amount equal to 30% of the cost of the remaining works at agreed rates of the terminated contract shall be recovered from the defaulted contractor towards the risk and cost. The contractor shall be directed to remit the risk and cost amount within three months. There is no need to wait till the work is arranged alternatively through another contractor and the total loss sustainable due to the default of the original contractor is assessed. Such loss, if any, shall be realised after completion of the work. If he fails to remit the amount within this periods following steps can be adopted for realisation of loss. The amount can be realised from the following.

2. EMD/Security

3. Bill amount / retention if any due to the contract.

4. Any dues from department to the contract.

5. Bank Guarantee / Performance Guarantee or By filling civil suit against the contractor W.A.No.2319 of 2019

It was argued that the appellant is bound by a

contract and based on the clause of PWD manual as

above, the appellant can claim an amount only less

than the amount covered by the clause as above.

The learned Government Pleader also placed

reliance on the judgment of the Apex Court in

State of Gujarat Through Chief Secretary and

Another v. Amber Builders [(2020) 2 SCC 540].

6. The learned Senior Counsel appearing for

the appellant, on the other hand, placing reliance

on the judgment of the Apex Court in M.P.Power

Management Company Limited, Jabalpur v. Sky Power

Southeast Solar India Private Limited and Others

[2022 SCC Online SC 1591] submitted that the Court

is not precluded from issuing any directions in

the matter of contract, and any arbitrary action

of the State or its instrumentality can be

interfered with by invoking writ jurisdiction.

7. Placing reliance on Amber Builders case,

the learned Government Pleader rightly pointed out W.A.No.2319 of 2019

that it is not necessary for the Government to

have a recourse to adjudication, to withhold or

recover any amount based on contract. The point

in this case is in context to, not only the

authority of the Government to withhold or recover

the amount due to the contractor on a premise of

breach of contract, but also on the authority of

the Government to retain any amount in excess of

the loss already quantified by them.

8. The State and its instrumentalities are

expected to deal with the citizens in a fair

manner in all circumstances. In a normal course,

if the Government had not quantified the loss, the

Court cannot order release of the amount agreed to

be recovered, based on the contract. But that

does not mean that the Court cannot order release

of the withheld amount in excess of the loss

already quantified by the public officials. The

admitted amount in this matter cannot be withheld

except for the loss to be calculated by the W.A.No.2319 of 2019

Government. The stipulation in the PWD Manual to

recover 30% of the cost of the remaining works to

offset the possible loss likely to suffer on

breach of contract by the contractor. If the

amount has been already calculated withholding any

amount beyond the alleged loss suffered is

arbitrary and illegal.

9. We, in such circumstances, are of the view

that the admitted amount under part and 7th and 8th

and final bills, be released to the appellant,

except the amount calculated towards damages and

loss. The security deposit and any other amount

payable to the appellant towards performance

guarantee as per the contract also be released to

the appellant. We make it clear that, if the

appellant has any other claim, other than that of

the admitted amounts as above under part and 7th

and 8th and final bills including the withheld

amount, he can approach the civil court. With

liberty as above, we dispose of this appeal. W.A.No.2319 of 2019

Needful shall be done to comply with the direction

to release the amount as above to the Construction

Corporation within one month. The Construction

Corporation, on receipt of the amount, shall

release the amount to the appellant within a

further period of one month. No costs.

Sd/-

A.MUHAMED MUSTAQUE, JUDGE

Sd/-

SHOBA ANNAMMA EAPEN, JUDGE ms

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter