Muhammed Kunhi vs State Of Kerala on 9 February, 2023
W.P.(C) No. 20387 & 20699 of 2022
                                      :1:



                IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                    PRESENT

                 THE HONOURABLE MR. JUSTICE SHAJI P.CHALY

         THURSDAY, THE 9TH DAY OF FEBRUARY 2023 / 20TH MAGHA, 1944

                          WP(C) NO. 20387 OF 2022

PETITIONER/S:
           MUHAMMED KUNHI,
           AGED 47 YEARS,
           S/O. MOIDEEN KUNHI, THOTTY HOUSE, CHANGLA,
           KALLINKOOTTAM, THEKKAL FERRY P.O., KASARGOD DISTRICT -
           671 541.
           BY ADVS.
           GEORGE MATHEW
           M.D.SASIKUMARAN
           MATHEW K.T.
           SUNIL KUMAR A.G
           GEORGE K.V.
           PRAVEEN S.
           DIPU JAMES
           STEPHY K REGI

RESPONDENT/S:

     1        STATE OF KERALA
              REPRESENTED BY ITS SECRETARY, WATER RESOURCES
              DEPARTMENT, GOVERNMENT SECRETARIAT,
              THIRUVANANTHAPURAM - 695 001.
     2        KERALA WATER AUTHORITY,
              REP. BY ITS MANAGING DIRECTOR, JALA BHAVAN,
              VELLAYAMBALAM, THIRUVANANTHAPURAM - 695 033.
     3        SUPERINTENDING ENGINEER,
              KERALA WATER AUTHORITY, PUBLIC HEALTH CIRCLE,
              THIRUVANANTHAPURAM DISTRICT - 695 033.
     4        THE EXECUTIVE ENGINEER,
              SEWERAGE DIVISION, KERALA WATER AUTHORITY, PATTOOR,
              THIRUVANANTHAPURAM - 695 033.
     5        THE ASSISTANT EXECUTIVE ENGINEER,
              SEWERAGE SUB DIVISION, KERALA WATER AUTHORITY, PATTOOR,
              THIRUVANANTHAPURAM - 695 033.
              BY ADV GEORGIE JOHNY, SC
              SRI. RAJEEV JYOTHISH GEORGE, GOVERNMENT PLEADER



THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 31.01.2023,

ALONG WITH WP(C).20699/2022, THE COURT ON 09.02.2023 DELIVERED THE

FOLLOWING:
 W.P.(C) No. 20387 & 20699 of 2022
                                      :2:



                IN THE HIGH COURT OF KERALA AT ERNAKULAM

                                    PRESENT

                THE HONOURABLE MR. JUSTICE SHAJI P.CHALY

      THURSDAY, THE 9TH DAY OF FEBRUARY 2023 / 20TH MAGHA, 1944

                         WP(C) NO. 20699 OF 2022

PETITIONER/S:

             MUHAMMED KUNHI,
             AGED 47 YEARS,
             S/O. MOIDEEN KUNHI, THOTTY HOUSE,CHANGLA,
             KALLINKOOTTAM, THEKKAL FERRY P.O., KASARGOD DISTRICT -
             671 541.
             BY ADVS.
             GEORGE MATHEW
             M.D.SASIKUMARAN
             SUNIL KUMAR A.G
             MATHEW K.T.
             GEORGE K.V.
             PRAVEEN S.
             DIPU JAMES
             STEPHY K REGI
             ELSA DENNY PINDIS

RESPONDENT/S:
     1    STATE OF KERALA,
          REPRESENTED BY ITS SECRETARY, WATER RESOURCES
          DEPARTMENT, GOVERNMENT SECRETARIAT,
          THIRUVANANTHAPURAM - 695 001.
     2    KERALA WATER AUTHORITY,
          REP. BY ITS MANAGING DIRECTOR, JALA BHAVAN,
          VELLAYAMBALAM, THIRUVANANTHAPURAM - 695 033.
     3    SUPERINTENDING ENGINEER,
          KERALA WATER AUTHORITY, PUBLIC HEALTH CIRCLE,
          THIRUVANANTHAPURAM DISTRICT - 695 033.
     4    THE EXECUTIVE ENGINEER,
          SEWERAGE DIVISION, KERALA WATER AUTHORITY, PATTOOR,
          THIRUVANANTHAPURAM - 695 033.
     5    THE ASSISTANT EXECUTIVE ENGINEER,
          SEWERAGE SUB DIVISION, KERALA WATER AUTHORITY, PATTOOR,
          THIRUVANANTHAPURAM - 695 033.
          BY ADV GEORGIE JOHNY
          SRI. RAJEEV JYOTHISH GOERGE

THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 31.01.2023,

ALONG WITH WP(C).20387/2022, THE COURT ON 09.02.2023 DELIVERED THE

FOLLOWING:
 W.P.(C) No. 20387 & 20699 of 2022
                                    :3:



                          SHAJI P. CHALY, J.
         ---------------------------------------------------------
                      W.P.(C). Nos. 20387 & 20699 of 2022
         ---------------------------------------------------------
                  Dated this the 9th day of February, 2023.

                             JUDGMENT

The petitioner in the captioned writ petitions is one and the

same person, a contractor engaged by the Kerala Water Authority

to carry out its work. The works allotted to the petitioner were

terminated at the risk and cost of the petitioner and further the

petitioner was blacklisted as per Exhibits P13 and P10 orders

respectively dated 30.04.2022 for a period of five years. It is thus,

challenging the legality and correctness of the orders passed by the

statutory authority, the writ petitions are filed.

2. In W.P.(C) No. 20387 of 2022, the petitioner was awarded

the work 'AMRUT 2016-17-TSS E Block Zone II-Supplying, laying

700 mm D1-K7 sewer main from Jagathi Bund road towards

existing manhole in 1200 mm dia parallel main near Jagathi School

through Panchami Garden Ch.0.00m to 323m. The work was to be

done as per the schedule, plan, specifications and conditions of

contract. There is no dispute with respect to the tender awarded

and execution of Exhibit P1 agreement dated 28.02.2019 with the

Superintending Engineer, Kerala Water Authority, Public Health

Circle, Thiruvananthapuram, respondent No.3. According to the

petitioner, after the execution of the agreement, the site was W.P.(C) No. 20387 & 20699 of 2022

handed over to the petitioner and he started the work. However, it

is contended that handing over was done with all obstructions and

also without obtaining necessary road cutting sanction from the

authorities concerned. Various other contentions are raised by the

petitioner to demonstrate that there was no latches or negligence

on his part to carry out the said work.

3. Anyhow, the petitioner was continuing with the work and

the part bill raised by the petitioner was being paid also. It is

further submitted that when the work was stopped due to heavy

rain, water logging and the pandemic covid-19, the third respondent

directed the petitioner to restart and complete the work by 31st

December, 2020, evident from Exhibit P5 letter dated 15.12.2020.

4. The case of the petitioner is that as per the agreement, it

is for the Water Authority to clear all obstacles along the alignment,

including the road cutting permits and consent from the owners of

the building abutting the alignment. It is also the case of the

petitioner that when requests were made in that regard, the

petitioner was directed to proceed leaving the area where the

obstructions are seen and therefore, according to the petitioner the

work was completed at the portions made available and handed

over to the petitioner. It is further submitted that the alignment

entered on a narrow road and the size of the pipe was to be

shortened due to site conditions and consequently, Exhibit P6 W.P.(C) No. 20387 & 20699 of 2022

request dated 20.12.2020 was forwarded to the office and the same

is lying unattended even now.

5. It is further submitted that obstructions were reported by

the petitioner as per Exhibit P7 dated 15.02.2021; but, no action

was taken by the authorities. While so, as per Exhibit P8

communication dated 09.08.2021 issued by the Executive Engineer,

Sewerage Division, Kerala Water Authority, respondent No. 4, time

for completing the work was extended till 30.09.2021. According to

the petitioner, even before the time extension, the petitioner re-

started the work at all possible places and completed the work

except 50 meters in the middle of the alignment.

6. It is also contended that local residents created

obstructions in the incomplete area and the affected parties started

filing complaints. Whatever that be, again Exhibit P9 letter dated

25.01.2022 was issued to the petitioner to re-start the work. But,

the contention of the petitioner is that the petitioner was not able to

commence the work as facilities were not provided by the Water

Authority.

7. According to the petitioner, it was at that point of time,

Exhibit P10 letter dated 11.03.2022 was issued by the third

respondent terminating the contract and thereafter, the third

respondent has taken necessary steps to invoke the bank

guarantee, evident from Exhibit P11 dated 13.04.2022. According W.P.(C) No. 20387 & 20699 of 2022

to the petitioner, the letter of termination and the letter for invoking

bank guarantee was responded to by the petitioner as per Exhibit

P12 letter dated 26.04.2022. However, there was no response or

consideration given to the petitioner by the Water Authority and

later, as per Exhibit P13 order dated 30.04.2022, the work was

terminated without taking into consideration the contentions

advanced by the petitioner, which disabled him from carrying out

the work in question.

8. Even though the petitioner has submitted Exhibit P14

representation dated 23.05.2022, the same was not considered by

the Managing Director of the Kerala Water Authority, respondent

No.2 is the contention. Anyhow, the work was re-tendered as per

Exhibit P15 notice dated 15.06.2022. These are the background

facts put forth by the petitioner in the aforesaid writ petition.

9. Insofar as W.P.(C) No. 20699 of 2022 is concerned, the

petitioner was awarded with the work 'Plan 30-2018-19-TSS-

Rehabilitation of Collection well and Pump House and Providing 3

nos. of sewage Pump Set at Arannoor Pump House. As per the

selection notice, agreement was executed and the site was handed

over to the petitioner and he started the work. Therein also, the

contentions raised in the other writ petition with respect to the

obstruction created by the local people, narrow width of the road

and other difficulties faced are raised. There were correspondences W.P.(C) No. 20387 & 20699 of 2022

by and between the parties. In fact, time for completing the work

was extended, as is evident from Exhibit P8 dated 25.01.2022.

Again, the petitioner was directed to complete the work in two

weeks from 31.01.2022. Anyhow, the contention advanced by the

petitioner is that in the meanwhile, the Superintending Engineer,

Kerala Water Authority, Public Health Circle, Thiruvananthapuram,

respondent No.3, without hearing the petitioner and without issuing

a notice, passed Exhibit P10 order dated 30.04.2022 terminating

the work.

10. Thereupon, the petitioner has submitted Exhibit P11

representation dated 23.05.2022. However, as per Exhibit P12

letter dated 26.05.2022, the third respondent has sought to invoke

the bank guarantee. The paramount contention advanced by the

petitioner is that the termination order, invocation of bank

guarantee and blacklisting are done without taking note of the

responsibilities and duties that are to be discharged by the Kerala

Water Authority and its officials.

11. It is contended that the grievances raised by the

petitioner at several stages of work are even now unattended. It is

further pointed out that a perusal of the files will reveal that there

was no response on the part of the respondents to the request

made by the petitioner for assistance and instruction at sight and

therefore, the impugned orders have been passed without taking W.P.(C) No. 20387 & 20699 of 2022

note of the ground realities. It is further submitted that even

though the petitioner has submitted a representation before the

Managing Director of the Kerala Water Authority, it also did not

yield any fruitful result and therefore, he seeks to quash the

coercive action initiated by the Kerala Water Authority.

12. The respondents have filed separate counter affidavits in

the writ petitions and have also produced documents to establish

that even though sufficient time and opportunities were provided to

the petitioner, he has not made any efforts to complete the work in

terms of the agreement executed and within the extended time

granted to the petitioner. It is also contended that as per the

Notice Inviting Tender, the selection notice and the agreement,

period of contract was for 8 months from the date of the selection

notice and any failure in adhering to the stipulations contained in

the tender documents would result in cancellation of the work and

the work would be arranged at the risk and cost of the petitioner.

13. It is further submitted that the respondents were aware

of the fact that the work requires challenging engineering skills and

that is the reason why the work was awarded to the contractor 38%

above the estimate rate. It is further pointed out that as per the

Notice Inviting Tender, the petitioner was well aware that the

buildings were situated close to the alignment and the work had to

be executed with formidable steel shoring.

W.P.(C) No. 20387 & 20699 of 2022

14. The sum and substance of the contention is that the

petitioner was aware of the site conditions and later the petitioner is

not at liberty to turn around and attack the respondents with

respect to the site conditions in order to carry out the work. It is

also stated that insofar as the work in W.P.(C) No. 20387 of 2022

is concerned, as per the agreement, it should have been completed

on or before 27.10.2019. However, taking into account the fact

that the contractors did not complete the work, time of completion

of the work has been extended upto 31.12.2020 and further upto

30.09.2021 at the request of the petitioner, vide orders of the

Executive Engineer.

15. It is further submitted that it was taking into

consideration the Covid-19 pandemic and unprecedented monsoon,

time was extended for almost two years; but, in spite of all the

efforts made by the Water Authority, the petitioner failed to

complete the work. It is further contended that thereafter on

10.02.2022, the petitioner was again instructed to commence the

work from 11.02.2022 to avoid legal action. However, there was no

positive response from the side of the petitioner, which persuaded

the Water Authority to take action to terminate the contract. It is

also submitted that in spite of termination of contract, the petitioner

did not respond; but, thereafter, on 26.04.2022, a communication

was sent making imputations against the conduct of the Water W.P.(C) No. 20387 & 20699 of 2022

Authority, which according to the respondents lack bona fides.

16. It is further submitted that sufficient opportunity was

provided to the petitioner before termination of the contract.

Insofar as the work in W.P.(C) No. 20699 of 2022 is concerned,

apart from common contentions, it is submitted that the said work

also had challenging engineering skills and it was taking into

account the said factor that the contractor was awarded 8.5%

above the estimate rate. Therein also, it is contended that the

petitioner had visited the site and was well aware of the site

conditions in order to supply the erection and commission of 45 KVA

for nearest power generator with suitable diesel engine for 20 HP

pump set.

17. It is also submitted that in spite of the fact that the work

should have to be completed on 21.05.2020 and time was extended

upto 31.12.2020, 07.05.2021, 08.12.2021 and further upto

21.01.2022 at the request of the petitioner, he did not complete the

work. Anyhow, again on 10.02.2022, the petitioner was instructed

to commence the work within a week to avoid the legal sanction.

But, there was no positive response from the part of the petitioner

and it was thereupon that show cause notice dated 30.04.2022 was

issued as to why further action shall not be taken against the

petitioner.

18. It is the further contention of the respondent that the W.P.(C) No. 20387 & 20699 of 2022

petitioner was hostile to all communications issued by the Kerala

Water Authority and even though Water Authority made its best

efforts, the petitioner was not co-operating to complete the work,

which constrained the Water Authority to terminate the work at the

risk and cost of the petitioner and blacklisting the petitioner.

19. I have heard the learned counsel for the petitioner Sri.

George Mathew, learned Standing Counsel for the Kerala Water

Authority Sri. Goergie Johny and the learned Government Pleader

Sri. Deepu Jyothish George, and perused the pleadings and material

on record.

20. Two questions emerge for consideration i.e., (i) whether

the termination of the contracts awarded to the petitioner is legally

correct or not; and (ii) whether the blacklisting was done without

notice to the petitioner. The award of the contract, execution of the

agreement, terms and conditions of the agreement, extension of

time granted for completion of the work etc. are all undisputed. It

is also clear from the Notice Inviting Tender produced as Exhibit

R2(a) in W.P.(C) No. 20387 of 2022 that every tenderer is

expected, before quoting his rate, to inspect the site of the

proposed work and also to inspect the quarries and satisfy himself

about the quality and availability of materials etc. It is also clear

from the Notice Inviting Tender that the Department does not

undertake to construct or make available any approach road or W.P.(C) No. 20387 & 20699 of 2022

other means of approach to the proposed work site and the

tenderer shall get acquainted with the available means of

approaches to the proposed site and quote for the various items;

and that the Department shall not be liable for any claim raised

later on the plea of the non availability or non access to the site.

21. It is also clear from the Notice Inviting Tender in both the

contracts that the contractor shall be liable for any loss caused to

the Government on account of the above work including any that

may arise due to non fulfillment of the contract. It is also clear that

the work shall be completed in all respects and also at the rate of

progress within the time limit and stipulations, failing which it is

stated that the contractor is liable to be fined in terms of the

stipulations contained in the special conditions. Various other

specifications are made in the Notices Inviting Tender, special

conditions and the agreement also so as to ensure that the work is

completed by the contractor in accordance with the terms and

conditions put forth by the Kerala Water Authority and accepted by

the petitioner.

22. It is also evident from the General Conditions issued by

the Kerala Water Authority in regard to the contracts awarded that

any dispute or difference that may arise between the Division Office

and the contractor on account of the contract shall at the instance

of either parties be referred to the Superintending Engineer, Kerala W.P.(C) No. 20387 & 20699 of 2022

Water Authority and whose decision given in writing shall be final,

conclusive and binding. It is an admitted fact that insofar the issue

in W.P.(C) No. 20387 of 2022 is concerned, the work had to be

completed even before the pandemic Covid-19 i.e, 27.10.2019,

which was being periodically extended and finally extended even in

the year 2022.

23. Insofar as the work in W.P.(C) No. 20387 of 2022 is

concerned, it was to be completed on 21.05.2020 i.e., almost two

months from the date of the lock-down restrictions imposed by the

Central and State Governments on account of pandemic Covid-19.

In spite of the lifting of the restrictions and providing sufficient time,

the petitioner could not complete the work. The contentions raised

by the petitioner with respect to the adverse situations at the sites

in question cannot be sustained at all, for the basic reason that the

petitioner was well aware of the site conditions and as per the

Notice Inviting Tender itself, it was made clear that the petitioner

had to visit the site and to be aware of the site conditions and the

Water Authority will not be responsible for any manner of complaint

in that regard.

24. This is a case where notices were issued to the

petitioner; however, in spite of the same, the petitioner has not

responded properly. This would be clear from the documents

produced by the petitioner itself. In fact, as per notice dated W.P.(C) No. 20387 & 20699 of 2022

25.01.2022 produced as Exhibit P9 in W.P.(C) No. 20387 of 2022,

the petitioner was directed to re-start and complete the work within

a month and it was warned that if he is not doing so, the authority

will be constrained to recommend to the Superintending Engineer,

P.H. Circle, Thiruvananthapuram to arrange the work at the risk and

cost of the petitioner. Thereafter, having not been responded to by

the petitioner, Exhibit P10 termination notice dated 11.03.2022 was

issued and thereafter Exhibit P11 communication dated 13.04.2022

was issued to the Bank to invoke the bank guarantee. It was in the

said constrained circumstances that the petitioner has submitted a

representation which was considered by the Superintending

Engineer in terms of the General Conditions of Contract and has

passed final order terminating the contract, as per clause 2116.2 of

Kerala Public Works Department Manual and consequently,

blacklisted the petitioner for a period of five years. Therefore, I do

not think, the petitioner has made out a case against the

cancellation of the contract and I am of the view that the allegations

raised by the petitioner against the respondents with respect to the

site conditions, non co-operation etc. cannot be sustained under

law, being against the terms and conditions of the contract. In my

considered view, the contentions advanced are against the basic

principles of law relating to contract, since the parties have agreed

to execute the contract on the specific terms and conditions of W.P.(C) No. 20387 & 20699 of 2022

contract including the ones contained in the Notice Inviting Tender

and general conditions of contract.

25. The second question to be considered is whether the

petitioner was given sufficient notice before blacklisting the

petitioner. As I have pointed out above, the Superintending

Engineer has relied upon clause 2116.2 of the Kerala Public Works

Department Manual. The contention advanced by the learned

counsel for the petitioner is that the provisions of the PWD Manual

would not apply to the Kerala Water Authority and therefore, the

blacklisting of the petitioner cannot be sustained under law.

26. It is an undisputed fact that as per clause 2116.2 of the

PWD Manual, the authority is vested with powers to terminate the

contract, if the contractor abandons the work after executing a

portion without genuine reasons and does not resume or complete it

even after specific direction from the Department; that the licence

of the contractor whose work has been terminated shall be

cancelled with immediate effect and shall be barred from quoting for

another work for a minimum period of five years; the contract

licence shall not be renewed in his name or different name of a

binamy; and that a company or person or firm once terminated

shall be disqualified from participating in any tender in his name or

by using a different name or binamy and there shall also be a fine

and forfeiture of deposits. It was accordingly relying upon the said W.P.(C) No. 20387 & 20699 of 2022

provision, the petitioner was heard and later blacklisted. Is it

correct, is the issue to be resolved.

27. The learned Standing counsel for the Kerala Water

Authority submitted that neither in the Notice Inviting Tender nor in

the agreement, the applicability of the PWD Manual is not referred

to; however, it is clear from Kerala Water Authority (Authentication

of Orders, Assurance of Property and Execution of Contracts)

Regulations, 1992, that PWD Code etc. would apply in the matter

of execution of contracts for works and purchase of materials,

stationery articles, furniture etc. Regulation 5(3) specifies that all

agreements shall be executed for and on behalf of the Authority and

the forms prescribed under the Stores Purchase Manual, the P.W.D

Code or the K.F.C, as the case may be, shall mutatis mutandis

apply to the execution of contracts under the Regulation.

28. Taking into consideration the authentication of the

contracts executed by and between the contractor and the Water

Authority under the Regulations, 1992, it can be clearly found that

blacklisting can be done by the Kerala Water Authority, relying upon

the above specified clause of PWD Manual in continuation of the

termination of contract. Then the sole question is whether the

petitioner was provided with an opportunity of hearing before the

blacklisting was done. It is an admitted fact that the petitioner had

filed a representation and the petitioner was heard by a competent W.P.(C) No. 20387 & 20699 of 2022

officer as required under law and upheld the action of the authority

after considering the issues raised by the petitioner.

29. The facts and circumstances discussed above would make

it clear that there was gross negligence and laches on the part of

the contractor in the matter of execution of the work inspite of the

extension of the time by the Water Authority on several occasions.

30. In the facts and circumstances, this Court needs to

consider only whether there is any arbitrariness or illegality or other

legal infirmities on the part of the Water Authority in the matter of

termination of contracts and blacklisting the petitioner.

31. In my considered opinion, sufficient opportunity was

provided to the petitioner before termination of the contract; but

the petitioner has not responded to the correspondences of the

Water Authority and it is quite clear and evident that the Kerala

Water Authority was constrained to terminate the contract due to

the negligence on the part of the petitioner. Once it is found that

the petitioner was negligent in executing the work in spite of the

extended time granted by the Water Authority, the authority

competent i.e., the Superintending Engineer, as per the General

Conditions of Contract, is entitled to blacklist the contractor. Clause

2116.2 of the PWD Manual makes it clear that once it is found that

the Contractor is responsible for not completing the work, then the

contractor shall be barred from quoting another work for a W.P.(C) No. 20387 & 20699 of 2022

minimum period of five years. Therefore, I do not think the

petitioner has made out any arbitrariness or illegality or any other

legal infirmities justifying interference of this Court under Article

226 of the Constitution of India.

Needless to say, the writ petitions fail and accordingly, they

are dismissed.

sd/- SHAJI P. CHALY, JUDGE.

Rv W.P.(C) No. 20387 & 20699 of 2022

APPENDIX OF WP(C) 20387/2022

PETITIONER'S EXHIBITS:

Exhibit P1 TRUE COPY OF SELECTION NOTICE NO.KWA/PHC/D4-

199(A-B)/2017 DATED 28.2.2019 BY 3RD RESPONDENT.

Exhibit P2 TRUE COPY OF REPRESENTATION DATED 10.10.2019 SUBMITTED BY PETITIONER TO 4TH RESPONDENT.

Exhibit P3 TRUE COPY OF LETTER DATED 04.02.2020 SUBMITTED BY PETITIONER TO 4TH RESPONDENT.

Exhibit P4 TRUE COPY OF LETTER DATED 21.05.2020 BY PETITIONER TO 5TH RESPONDENT.

Exhibit P5 TRUE COPY OF LETTER NO.KWA/PHC/D4-199(A&B)/2017 DATED 15.12.2020 ISSUED TO PETITIONER BY 3RD RESPONDENT.

Exhibit P6 TRUE COPY OF LETTER DATED 20.12.2020 SUBMITTED BY PETITIONER TO ASST. ENGINEER.

Exhibit P7 TRUE COPY OF LETTER DATED 15.02.2021 SENT BY PETITIONER TO 5TH RESPONDENT.

Exhibit P8 TRUE COPY OF LETTER NO.KWA/SSD/DB2/ JAGATHY/2019 DATED 09.08.2021 ISSUED BY 4TH RESPONDENT.

Exhibit P9 TRUE COPY OF LETTER NO.SMD/DB1/450/2019 DATED 25.01.2022 ISSUED BY 4TH RESPONDENT.

Exhibit P10 TRUE COPY OF TERMINATION NOTICE NO.KWA/PHC-

D4-199 (A&B)/2017/AMRUT DATED 11.03.2022 ISSUED BY 3RD RESPONDENT.

Exhibit P11 TRUE COPY OF LETTER NO.KWA/PHC/BG/JS/3532/2019 DATED 13.04.2022 ISSUED TO FINANCING INSTITUTION BY 3RD RESPONDENT.

Exhibit P12 TRUE COPY OF REPLY DATED 26.04.2022 SENT BY E-

MAIL BY PETITIONER TO 3RD RESPONDENT.

Exhibit P13 TRUE COPY OF ORDER NO.KLWA/PHC/-D4-199(A&B)/2017/ AMRUT DATED 30.04.2022 ISSUED BY 3RD RESPONDENT.

Exhibit P14 TRUE COPY OF REPRESENTATION DATED 23.05.2022 SUBMITTED BY PETITIONER TO 2ND RESPONDENT.

Exhibit P15 TRUE COPY OF RELEVANT PAGES OF NIT NO.28/2022-

23/KWA/SMD/TVM DATED 15.06.2022.

Exhibit P16 TRUE COPY OF LETTER DATED 03.04.2022 GIVEN BY A BUILDING OWNER ALONG THE ALIGNMENT TO 3RD RESPONDENT.

EXHIBIT P17 TRUE COPY OF LETTER NO.018/2022 DATED 13.07.2022 ISSUED BY MANAGER DHANALAKSHMI BANK LTD., KASARAGOD BRANCH TO 3RD RESPONDENT.

W.P.(C) No. 20387 & 20699 of 2022

RESPONDENT EXHIBITS Exhibit R2(A) TRUE COPY OF THE NOTICE INVITING TENDER OF WORKS AS PER NO. 17/2018-19/KWA/PHC/D4/TVM (RTI) DATED NIL.

Exhibit R2(B) TRUE COPY OF THE CONTRACT AGREEMENT ENTERED INTO ON 08/03/2019 BETWEEN THE PETITIONER AND THE 3RD RESPONDENT

True Copy

PS To Judge.

rv W.P.(C) No. 20387 & 20699 of 2022

APPENDIX OF WP(C) 20699/2022

PETITIONER'S EXHIBITS:

Exhibit P1 TRUE COPY OF SELECTION NOTICE NO.KWA/PHC/D4-

3080/ 2019 DTD. 22.11.2019 ISSUED BY 3RD RESPONDENT.

Exhibit P2 TRUE COPY OF LETTER NO.KWA/PHC/D4-3080/2019 DTD. 15.12.2020 ISSUED BY 3RD RESPONDENT TO PETITIONER.

Exhibit P3 TRUE COPY OF LETTER DTD. 28.12.2020 SUBMITTED BY PETITIONER TO 3RD RESPONDENT.

Exhibit P4 TRUE COPY OF LETTER DTD. 11.01.2021 SUBMITTED BY PETITIONER TO 5TH RESPONDENT.

Exhibit P5 TRUE COPY OF LETTER NO.KWA/PHC/D4-3080/2019 DTD. 18.07.2021 ISSUED BY 3RD RESPONDENT.

Exhibit P6 TRUE COPY OF LETTER DTD. 03.09. 2021 FROM PETITIONER TO 3RD RESPONDENT.

Exhibit P7 TRUE COPY OF LETTER DTD. 12.10.2021 FROM PETITIONER TO 3RD RESPONDENT.

Exhibit P8 TRUE COPY OF LETTER NO.SMD/DB1/2189/2019 DTD.

25.01.2022 ISSUED TO PETITIONER BY 4TH RESPONDENT.

Exhibit P9 TRUE COPY OF LETTER NO.KWA/SPS/ARANOOR/846/2019 DTD. 23.03.2022 ISSUED TO PETITIONER BY ASSISTANT ENGINEER. Exhibit P10 TRUE COPY OF ORDER NO.KWA/PHC/-D4-3080/2019 DTD. 30.04.2022 ISSUED BY 3RD RESPONDENT.

Exhibit P11 TRUE COPY OF REPRESENTATION DTD. 23.05.2022 SUBMITTED BY PETITIONER TO 2ND RESPONDENT.

Exhibit P12 TRUE COPY OF LETTER NO. KWA/PHC/ BG/JS/3532/ 2019(III) DTD. 26.05.2022 FROM 3RD RESPONDENT TO THE SOUTH INDIAN BANK LTD., CHERKALA BRANCH.

Exhibit P13 TRUE COPY OF THE LETTER NO. BR/0671/56/2022/23 DATED 15/07/2022 ISSUED BY THE MANAGER SOUTH INDIAN BANK, CHERKALA BRANCH TO THE PETITIONER Exhibit P14 TRUE COPY OF THE RELEVANT PAGES OF SCHEDULE APPENDED TO NIT AND AGREEMENT NO. 16/2019-

2020 DATED 12/12/2019 Exhibit P15 TRUE COPY OF THE RELEVANT PAGES OF SCHEDULE APPENDED TO NIT FOR CONTRACT O.

36/2022-23/KWA/SMD/TVM DATED NIL RESPONDENTS' EXHIBITS:

Exhibit R2(A) TRUE COPY OF THE NOTICE INVITING TENDER FOR W.P.(C) No. 20387 & 20699 of 2022

WORKS AS PER TENDER NO.14/2019-20/KWA/PHC/D4/TVM DATED NIL.

Exhibit R2(B) TRUE COPY OF THE AGREEMENT ENTERED INTO ON 12-12-2019 BETWEEN THE PETITIONER AND 3RD RESPONDENT.

True Copy

PS To Judge.

rv

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter