Citation : 2023 Latest Caselaw 1917 Ker
Judgement Date : 3 February, 2023
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MRS. JUSTICE M.R.ANITHA
FRIDAY, THE 3RD DAY OF FEBRUARY 2023 / 14TH MAGHA, 1944
RSA NO.1000 OF 2012
AGAINST THE JUDGMENT AS 136/2009 OF SUB COURT, PALA
OS 146/2007 OF MUNSIF COURT, KANJIRAPPALLY
APPELLANTS/APPELLANTS 1 TO 3/DEFENDANTS 1 TO 3:
1 STATE OF KERALA
REPRESENTED DISTRICT COLLECTOR, KOTTAYAM
2 TAHSILDAR
TALUK OFFICE, KANJIRAPPALLY
3 ASST.EXECUTIVE ENGINEER,
NATIONAL HIGHWAY 220, KANJIRAPPALLY
BY SHEEBA.G, GOVERNMENT PLEADER
RESPONDENTS/R1 & 4TH APPELLANT/PLAINTIFF & 4TH DEFENDANT:
1 TOMY DOMINIC,
S/O.DOMINIC, KARIKKATTUKUNNEL HOUSE, CHIRAKKADAVU
VILLAGE, VADAKKUMBHAGOM MURI, KANJIRAPPALLY.P.O
PIN 686 507.
2 UNION OF INDIA
REPRESENTED BY THE SECRETARY, MINISTRY OF
SHIPPING, ROAD TRANSPORT AND HIGHWAYS NEW DELHI
PIN 110014
BY ADVS.
SRI.T.KRISHNAN UNNI (SR.)for R1
MANU S., DSG OF INDIA for R2
SMT.MEENA.A for R1
THIS REGULAR SECOND APPEAL HAVING COME UP FOR
ADMISSION ON 20.01.2023, THE COURT ON 03.02.2023 DELIVERED
THE FOLLOWING:
C.M.Appl.No.878 of 2012
in R.S.A.No.1000 of 2012 2
and R.S.A.No.1000 of 2012
M.R.ANITHA, J
******************
C.M.Appl.No.878 of 2012 in R.S.A.No.1000 of 2012 and R.S.A.No.1000 of 2012
---------------------------------------------- Dated this the 3rd day of February, 2023
ORDER & JUDGMENT
C.M.Appl.No.878 of 2012 is filed by the appellant to
condone the delay of 411 days in filing R.S.A.No.1000 of 2012.
2. The Deputy Thahasildar, Taluk Office, Kanjirapilly filed
supporting affidavit contending that delay caused due to
administrative exigencies occurred in the office of the respondent
and there is no wilful laches in not filing the appeal in time.
Hence the petition.
3. First respondent/plaintiff filed counter affidavit
contenting that the reason stated for the delay is not sufficient to
condone the long delay. No cogent and acceptable explanations
have been offered.
4. Heard both sides.
C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
5. Suit has been filed originally for perpetual injunction
and amended subsequently seeking declaration of title and
possession after filing written statement by the
appellants/defendants. The dispute is with regard to item No.2
property having an extent of 20 sq.meters in which south
western concrete pillar of the four storied building in plaint
schedule property is situated. When there was attempt on the
part of the defendants/appellants to trespass into plaint schedule
property and demolish the portion of building, the suit was filed.
6. Appellants/defendants filed written statement
contending that plaintiff included puramboke land in the plaint
schedule property and denying the right and possession of
plaintiff and predecessor over plaint item No.2 property. PW1
examined and Exts.A1 to A15, Exts.C1 to C2(a) were also
marked from the side of plaintiff. There was no evidence from
the side of appellants/defendants. The learned Munsiff on
evaluating facts, circumstances and evidence, decreed the suit,
as prayed for. Against which A.S.No.136/2009 was filed by
appellants/defendants with an application under Section 5 of C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
Limitation Act to condone the delay of 266 days. By the
impugned judgment, the petition to condone the delay and
appeal stand dismissed. Aggrieved by the same, the above R.S.A
has been filed with the C.M.Application.
7. Hence the question for consideration is whether there
is 'sufficient cause' to condone the delay of 411 days in filing the
R.S.A.
8. In Esha Bhattacharjee v. Managing Committee of
Raghunathpur Nafar Academy : 2013 (4) KLT Suppl. 59
(SC) a two Judge Bench of the Apex Court discussed about the
approach to be adopted by courts while dealing with application
for condonation of delay under Section 5 of the Limitation Act,
1963. Paragraph No.13 of the said decision is relevant to be
quoted which reads thus:
"13. Recently in Maniben Devraj Shah v.
Municipal Corporation of Brihan Mumbai[19], the learned Judges referred to the pronouncement in Vedabai v. Shantaram Baburao Patil [20] wherein it has been opined that a distinction must be made between a case where the delay is inordinate and a case where the delay is of few days and whereas in C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
the former case the consideration of prejudice to the other side will be a relevant factor, in the latter case no such consideration arises. Thereafter, the two-Judge Bench ruled thus: -
"23. What needs to be emphasized is that even though a liberal and justice-oriented approach is required to be adopted in the exercise of power under Section 5 of the Limitation Act and other similar statutes, the courts can neither become oblivious of the fact that the successful litigant has acquired certain rights on the basis of the judgment under challenge and a lot of time is consumed at various stages of litigation apart from the cost.
24. What colour the expression "sufficient cause" would get in the factual matrix of a given case would largely depend on bona fide nature of the explanation. If the court finds that there has been no negligence on the part of the applicant and the cause shown for the delay does not lack bona fides, then it may condone the delay. If, on the other hand, the explanation given by the applicant is found to be concocted or he is thoroughly negligent in prosecuting his cause, then it would be a legitimate exercise of discretion not to condone the delay." Eventually, the Bench upon perusal of the application for condonation of delay C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
and the affidavit on record came to hold that certain necessary facts were conspicuously silent and, accordingly, reversed the decision of the High Court which had condoned the delay of more than seven years."
9. Hence the duty is upon the court in each case to
determine whether there is sufficient cause offered by the
parties. Whether there is negligence or inaction on the side of
the party approaching the court in taking timely action has to be
ascertained from the factors brought in by them as explanation.
There is also distinction between cases where delay is inordinate
and cases where delay is of few days and in the former case, the
consideration of prejudice to the other side is a relevant factor
and if the delay is of the few days, the question of prejudice is
not of much relevance.
10. In Basawaraj v. Special Land Acquisition Officer :
2013 (3) KLT Online 1108 (SC) the meaning of the word
'sufficient cause' under Section 5 of the Limitation Act, 1963 has
been dealt with in detail and paragraph No.9 of the said decision
is relevant in this context to be extracted which reads thus: C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
"Sufficient cause is the cause for which defendant could not be blamed for his absence. The meaning of the word "sufficient" is "adequate" or "enough", inasmuch as may be necessary to answer the purpose intended. Therefore, the word "sufficient" embraces no more than that which provides a platitude, which when the act done suffices to accomplish the purpose intended in the facts and circumstances existing in a case, duly examined from the view point of a reasonable standard of a cautious man. In this context, "sufficient cause" means that the party should not have acted in a negligent manner or there was a want of bona fide on its part in view of the facts and circumstances of a case or it cannot be alleged that the party has "not acted diligently" or "remained inactive". However, the facts and circumstances of each case must afford sufficient ground to enable the Court concerned to exercise discretion for the reason that whenever the Court exercises discretion, it has to be exercised judiciously. The applicant must satisfy the Court that he was prevented by any "sufficient cause"
from prosecuting his case, and unless a satisfactory explanation is furnished, the Court should not allow the application for condonation of delay. The court has to examine whether the C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
mistake is bona fide or was merely a device to cover an ulterior purpose. (See: Manindra Land and Manndra Lnd and Building Corporation Ltd. v. Bhootnath Banerjee & Ors., AIR 1964 SC 1336; Lala Matadn v. A. Narayanan, AIR 1970 SC 1953; Parimal v.Veena @ Bharti AIR 2011 SC 1150; and Maniben Devraj Shah v. Municipal Corporation of Brihan Mumbai AIR 2012 SC 1629.)
11. In University of Delhi v.
Union of India (UOI) and Ors. : MANU/SC/1761/2019 :
(2020) 13 SCC 745 while dealing with condonation of delay, it
has been held that a liberal approach is to be taken in the matter
of condonation of delay. That was a case in which respondent
No.13 was permitted by the Delhi Development Authority to
construct high rise multi-storied building in control zone of the
appellant. Permission was allowed for construction on plot. That
was leased out to Delhi Metro Rail Corporation by segregating
that plot. Appellant raised several contentions against the
construction and one of them was that construction was against
the master plan Delhi - 2021. Appellant challenged the action in
writ petition. Single Judge rejected the writ petition on the C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
ground of delay and laches. Later, executive council of the
appellant recommended to file intra court appeal. Therefore,
Letters Patent Appeal happens to be filed with delay of 916 days
with petition to condone the delay. Division bench rejected the
application for condoning the delay without considering the
merits of the matter against which appellant approaches the
Apex Court. While disposing the matter, the Apex Court held that
by and large a liberal approach is to be taken in the matter of
condonation of delay. Consideration for condonation of delay
would not depend on the status of the party, namely the
Government or the public bodies so as to apply a different
yardstick, but the ultimate consideration should be to render
even handed justice to parties. Even in such cases, condonation
of delay should not be automatic since the accrued right or the
adverse consequence to the opposite party is also to be kept in
perspective. So in that background, while considering
condonation of delay, routine explanation should not be enough.
But it should be in the nature of indicating sufficient cause to
justify the delay which will depend on the backdrop of each case C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
and will have to be weighed carefully by the courts based on the
fact situation. Merely because the appellant is a public body is
not a reasonable explanation for condonation of delay of 916
days and there should be reasonable explanations. When there is
such a long delay and there is no proper explanation, laches
would also come into play while noticing as to the manner in
which a party has proceeded before filing an appeal. The delay
offered in that case was two fold, i.e non availability of Vice
Chancellor due to retirement and subsequent appointment of new
Vice Chancellor, also that the matter was placed before the
executive council and a decision was taken to file the appeal and
the said process caused the delay. Evaluating the circumstances,
it was held that the decision of the Division Bench in dismissing
the LPA on the ground of delay of 916 days is justified and do not
call for interference.
12. In Poothadi Grama Panchayat v. S.C.Sukumaran :
2019 KHC 896 relied on by the counsel for respondents was a
writ appeal filed with 2106 days delay. Appellant is a Government
office and the reason offered for delay was missing of file and in C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
the said circumstances, it was held that the reason offered to
condone the delay was not sufficient.
13. State of Kerala v. N.U.Poulose (Died) and
Others : 2019 KHC 882 was a case in which arbitration appeal
was filed with a delay of 1127 days. The reason stated in the
delay condonation application is that the judgment of the court
below was pronounced on 16.08.2016 and the application for
obtaining certified copy of the judgment and decree was filed on
30.10.2018. Stamp paper was called for on 08.11.2018 and copy
of the judgment and decree was obtained on 12.11.2018. In the
said circumstances, it was held that there is absolutely no reason
why the appellants did not file any application for obtaining
certified copy of the judgment between 16.08.2016 and
30.10.2018. There is delay of more than two years and finding
that the delay is not properly explained, the petition was
dismissed and consequently appeal also rejected.
14. In the present case, the only reason stated by the
Deputy Tahsildar in the affidavit attached to the petition to
condone the delay of 411 days in filing the above R.S.A is C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
administrative exigencies in the office of the petitioners. It is
discernible from the affidavit that the judgment was pronounced
on 07.01.2011. But application for certified copy was filed on
31.05.2011. It is further alleged that certified copy of the
judgment was received on 04.08.2011. It was forwarded to the
office of the deponent on 10.08.2011 and it was sent to the office
of Advocate General on 21.10.2011 for examining the scope of
appeal. It is further alleged that then it is forwarded to the office
of Advocate General's office for preparing the appeal. That date
is not stated in the affidavit. The appeal has been filed only on
23.07.2012. So, there is no proper explanation for that delay
caused. In Esha Bhattacharjee the Apex Court had also guided
a principle that an application for condonation of delay should be
drafted with careful concern and not in a half hazard manner
harbouring the notion that the courts are required to condone
delay on the bedrock of the principle that adjudication of a lis on
merits is seminal to justice dispensation system. The fact that
the appellants are State and its officials is not a reason to apply a
different yardstick for condonation of delay. Apart from the C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
routine explanation of the administrative exigencies, no
reasonable cause is forthcoming for condoning the delay of more
than one year in filing the appeal in view of the settled principles
of law above discussed. Hence it cannot be found that the
petitioners/appellants offered sufficient cause for entertaining the
petition for condoning the long delay of 411 days in filing the
appeal.
15. It is true that the learned Government Pleader brought
to my attention Mandal Revenue Officer v. Goundla
Venkaiah and Another : 2010 KHC 4011. That was a case in
which it has been alleged that the predecessor of the
respondents illegally occupied 5 acres of land which is classified
in the revenue records Kharizkhata - Sarkari and in 1965 and
1986 notices were issued under section 7 of Andra Pradesh Land
Encroachment Act, 1905 but no order has been passed for
eviction. In 1990, Mandal Revenue Officer filed application before
the Special Tribunal constituted under the Land Grabbing Act for
recovery of possession of 5 acres and the respondents contended
that they acquired title by adverse possession and also that they C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
are landless poor entitled to assignment of land as per board's
standing orders. But the appellant initiated proceedings under
the Land Grabbing Act and the Special Tribunal allowed the
application and declared that the scheduled land is a Government
land and directed to handover possession to Government. The
appeal preferred by the respondents was dismissed by the
special court. The respondents took up the matter in writ petition
and a Division Bench of the High Court did not disturb the finding
of the Special Tribunal that the scheduled land is Government
land, but set aside the orders on the premise that respondents
have acquired title by adverse possession and they cannot be
evicted being treated as land grabbers. But the Apex court held
that dropping of proceeding under erstwhile Andhra Pradesh Land
Encroachment Act, 1905 did not lead to an inference that
respondents' possession was open and hostile against
Government. Payment of land revenue and making of application
to Government for assignment of schedule land or regularisation
of possession was negation of respondents' plea that they had
acquired title by adverse possession.
C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
16. It appears that the argument advanced quoting
Mandal Revenue Officer by the learned Government Pleader, is
something concerning the merits of the matter, since the court
below declared title of plaintiff over item No.2 property by
adverse possession.
17. The property alleged to be encroached in this case by
the 1st respondent is plaint item No.2 which is 20 square meters
only and the portion of the building. So, the decision cited above
cannot be squarely made applicable in this case.
18. It is further to be noted that the above R.S.A has been
directed against the judgment and decree in A.S.No.136 of 2009
on the file of Sub court Pala which in turn arise out of judgment
and decree in O.S.No.146/2007. The appeal has been dismissed
consequent to dismissal of I.A.No.2032 of 2009 which was filed
under section 5 of the Limitation Act, to condone the delay of 266
days in filing the appeal. As per the impugned order, the reason
stated for the delay is that there was no proper information
regarding the suit and delay in collection of official records and
no other reason is stated in the affidavit for the delay of 266 C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
days. The respondent/plaintiff, on the other hand, contended that
the original suit was contested one and the special officer was
also deputed for conducting the suit in the trial court. Finding
that the grounds stated are not available as per the records
produced by the appellants, it was held that there is no sufficient
ground to condone the delay and consequently, appeal was
dismissed following the principles in Pundlik J. Patil v.
Executive Engineer : 2009 1 KLT S.N 25 (C No. 26) SC. In
such circumstances, what is the scope of interference by this
Court while sitting in second appeal against the dismissal of the
appeal consequent to the dismissal of the petition to condone the
delay, is also relevant.
19. In K. Subbarayudu v. Special Deputy Collector
(Land Acquisition) : (2017) 12 SCC 840, a two Judge Bench
of the Apex Court had occasion to consider the scope of
interference when court concerned exercising its discretion either
condoning or declining to condone the delay and it has been held
that normally superior court will not interfere in exercise of such
discretion. It is also held that the true guide is whether the C.M.Appl.No.878 of 2012
and R.S.A.No.1000 of 2012
litigant has acted with due diligence. Here, first appellate court
while considering the petition to condone delay found that the
reason stated for condoning the delay is not seen available as per
records and hence petition to condone the delay has been
dismissed. Even after the dismissal of first appeal on the ground
of delay, the 2nd appeal has also been filed with delay of 411
days.
20. Absence of diligence and inaction are writ large on the
part of the petitioners. Mere fact that State and its officials are
the appellants by itself is not a reason to condone the delay. So,
I am of the considered view that petitioners/appellants failed to
offer sufficient reason to condone the delay.
In the result, petition to condone the delay and Regular
Second Appeal stand dismissed. In the facts and circumstances,
there is no order as to cost.
(sd/-) M.R.ANITHA, JUDGE
jsr/
True Copy
P.S to Judge
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!