Citation : 2023 Latest Caselaw 5286 Ker
Judgement Date : 24 April, 2023
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE A.MUHAMED MUSTAQUE
MONDAY, THE 24TH DAY OF APRIL 2023 / 4TH VAISAKHA, 1945
RSA NO. 468 OF 2004
AGAINST THE DECREE AND JUDGMENT DATED 20.12.1997 IN OS
554/1996 OF ADDITIONAL MUNSIFF COURT, IRINJALAKUDA
AS 71/1998 OF PRINCIPAL SUB COURT, IRINJALAKUDA
APPELLANTS/DEFENDANTS:
1 STATE OF KERALA
REPRESENTED BY THRISSUR DISTRICT COLLECTOR,
THRISSUR,, AYYANTHOLE.
2 EXECUTIVE ENGINEER IDAMALAYAR
IRRIGATION PROJECT DIVISION NO.1, CHALAKUDY.
3 EXECUTIVE ENGINEER MINOR IRRIGATION
DIVISION, THRISSUR.
4 ASST.EXECUTIVE ENGINEER MINOR
IRRIGATION, SUB DIVISION, CHALAKUDY.
5 EXECUTIVE ENGINEER ADDITIONAL
EXECUTIVE DIVISION, CHEMBUKKAVU, THRISSUR.
BY ADV SR.GOVT.PLEADER
SRI. ASHWIN SETHUMADHAVAN GP
RESPONDENTS:
1 INDIRA, MELUR VILLAGE DESOM, MUKUNDAPURAM TALUK.
2 DR.REMA, MELUR VILLAGE DESOM, MUKUNDAPURAM
TALUK.
3 CHINDA, MELUR VILLAGE DESOM, MUKUNDAPURAM TALUK.
4 SUDHA, MELUR VILLAGE DESOM, MUKUNDAPURAM TALUK.
RSA NO. 468 OF 2004
..2..
BY ADVS.
SRI.KAROL MATHEWS SEBASTIAN ALENCHERRY
SRI.V.V.SIDHARTHAN SR.
SRI.D.G.VIPIN
THIS REGULAR SECOND APPEAL HAVING COME UP FOR
ADMISSION ON 24.04.2023, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
RSA NO. 468 OF 2004
..3..
J U D G M E N T
Today this second appeal came up before this
Court for admission after more than 19 years of
filing this second appeal. The State is the
appellant. In a suit for mandatory injunction
and permanent injunction, a decree has been
granted in favour of the plaintiffs. There was a
temporary injunction as against the officials of
the State Government, pending suit. That appears
to have been violated and as a result, the trial
court imposed a penalty of Rs.50,000/- (rupees
Fifty Thousand only) to be recovered from the
State Government. The judgment of the trail
court has been confirmed by the Appellate Court.
2. The brief facts involved in this case
are as follows:
3. The plaintiffs are residing on the
eastern side of Chalakkudy river. Construction RSA NO. 468 OF 2004
..4..
of check dam was proposed by the Government and
contractor started the construction. On half
way, the construction appears to have been
stopped. As a result, through the eastern gap of
the check dam, water reached to the house of the
plaintiffs. The plaintiffs approached the
officials to immediately complete the
construction and prevent the flowing of water to
the plaintiffs' house. No response was received.
4. In a suit filed by the plaintiffs, an
application for interim injunction was filed and
injunction was granted. The commission report
filed in the matter fully supports the case of
the plaintiffs. The trial court granted the
decree for permanent injunction and mandatory
injunction to construct the check dam and
retention of the wall on the western side to
prevent further damages to the plaintiffs' house.
5. An interlocutory application was filed
by the plaintiffs to recover Rs.50,000/- being RSA NO. 468 OF 2004
..5..
the value of the loss suffered by them,
consequent upon the disobedience of the interim
order. The interim order, which was granted to
prevent causing any damage to the plaintiffs'
house. The court below, while disposing the
interlocutory application along with the final
judgment, granted a sum of Rs.50,000/- to be
recovered from the Government.
6. The learned Government Pleader submits
that there was absolutely no evidence to
calculate the loss suffered by the plaintiffs.
It is further submitted that by "Act of God"
water reached to the house of the plaintiffs and
the Government officials or contractor cannot be
blamed for that.
7. The courts below rendered the decree and
judgment on findings on facts. Neither any
question of law nor substantial question of law
does arise in this matter. Factual appreciation
of evidence including the commission report RSA NO. 468 OF 2004
..6..
cannot be reversed at this stage. It is to be
noted that the trial court, based on the
commission report, found that much damage has
been caused to the plaintiffs' house and the
Government officials or the contractor had
opportunity to prevent causing damage to the
plaintiffs' house by complying the interim order.
Rs.50,000/- has been imposed more as penalty for
non compliance of the order rather than
proceeding against the officials for violating
the interim order.
In such circumstances, I find no reason to
admit this case. The second appeal fails and
dismissed in limine.
Sd/-
A.MUHAMED MUSTAQUE JUDGE PR
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!