Citation : 2022 Latest Caselaw 3428 Ker
Judgement Date : 22 March, 2022
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE DEVAN RAMACHANDRAN
TUESDAY, THE 22ND DAY OF MARCH 2022 / 1ST CHAITHRA, 1944
WP(C) NO. 28120 OF 2021
PETITIONER:
NELLOLI KUNHALAN, AGED 69 YEARS
S/O. MOHAMMED, VELIMUKKU P. O.,
MONNIYUR, MALAPPURAM DISTRICT - 676 317.
BY ADVS.
K.K.SAIDALAVI
K.K.NASRUL HAQUE
RESPONDENTS:
1 STATE OF KERALA, REPRESENTED BY THE SECRETARY,
PUBLIC WORKS DEPARTMENT (ROADS), SECRETARIAT,
THIRUVANANTHAPURAM - 695 001.
2 UNION OF INDIA, REPRESENTED BY THE MINISTRY
OF ROAD TRANSPORT AND HIGHWAYS, TRANSPORT
BHAVAN -1, PARLIAMENT STREET, NEW DELHI - 110 001.
3 THE NATIONAL HIGHWAYS AUTHORITY OF INDIA
REPRESENTED BY ITS PROJECT DIRECTOR, PIU,
NATIONAL HIGHWAYS AUTHORITY OF INDIA, NO.8/1187,
ARUMUGHAM COLONY, CHANDRA NAGAR, PALAKKAD DISTRICT,
PIN - 678 007.
4 THE DEPUTY COLLECTOR & COMPETENT AUTHORITY
OFFICE OF THE DEPUTY COLLECTOR (LA), (NH - 66),
KOTTAKKAL, MALAPPURAM DISTRICT, PIN - 676 503.
5 THE ASSISTANT EXECUTIVE ENGINEER, PUBLIC WORKS
DEPARTMENT (NH), OFFICE OF THE EXECUTIVE ENGINEER,
PWD, CIVIL STATION, MALAPPURAM - 676505.
BY ADVS.
SRI.VISHNU PRADEEP
SRI.MATHEWS K.PHILIP S.C.
SMT. MABLE .C .KURIAN SR.G.P
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
22.03.2022, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WPC 28120/21
2
JUDGMENT
The petitioner alleges that when the Competent Authority
for Land Acquisition (CALA for short) appointed under the
provisions of the National Highways Act ('NH Act'), measured
his property situated in the land acquired for the purposes of
the National Highway Authority of India (NHAI), there has been
a shortfall of 359.99 square metres. He says that, he, therefore,
approached the said Authority for remeasuring the property, but
that instead of doing so, an Award has now been issued. He,
therefore, prays that the 5th respondent - Assistant Executive
Engineer be directed to remeasure the area of the building, so
that a Supplementary Award can be issued by the CALA with
respect to the same.
2. In response to the afore submissions made by
Sri.K.K.Saidalavi - learned counsel for the petitioner, Smt.Mable
C. Kurian - learned Senior Government Pleader, submitted that
since the petitioner admits that an Award has been issued, his
remedy would be to challenge the same - which, she asserts she WPC 28120/21
has specific instructions - he has already done, by preferring an
application under Section 3G(5), before the jurisdictional District
Collector, who is the Statutory Arbitrator. She argued that,
therefore, the petitioner must now move the Statutory Arbitrator
for any relief because going by the judgment of this Court in
Usman Arif v. The Project Director [2022(1) KLT 35], the CALA
has now become functus officio.
3. I must say that I find substantial force in the
submissions of the learned Senior Government Pleader because,
as rightly stated by her, on Ext.P1 Award being issued, the
CALA has been rendered functus officio, except for issuing a
Supplementary or Additional Award as is permitted under the
'NH Act'.
4. In the case at hand, the petitioner's claim is that
Ext.P1 Award is wrong, since it is based on an incorrect
calculation of the area of the building. Therefore, it is clear
that it is not a case where an Additional or Supplementary
Award can be issued by the CALA, but that the Award itself
will have to be challenged before the Statutory Arbitrator. WPC 28120/21
5. Since the learned Senior Government Pleader submits
that the petitioner has already challenged the Award before the
Arbitrator, I am certain that all his contentions must be
considered by the said Authority in terms of law.
6. Sri.Mathews K. Philip - learned Standing Counsel for
the NHAI, submitted that the building in question may not have
already been demolished, but prayed that if this Court is
inclined to direct the Statutory Arbitrator to hear the petitioner,
then his client may also be given an opportunity of being
heard.
In the afore circumstances, I order this Writ Petition to
the limited extent of leaving liberty to the petitioner to move
the jurisdictional Statutory Arbitrator in the pending 3G(5)
application and seek remeasurement of the building in question;
and if it is done within a period of one week from the date of
receipt of a copy of this judgment, the said Authority will
consider such application, after affording him as also the
concerned official of the NHAI, an opportunity of being heard
and issue appropriate orders thereon, either acceding to such WPC 28120/21
request or citing the reasons why it cannot be acceded to and
communicate it to the petitioner without any avoidable delay
thereafter.
Needless to say, if the petitioner approaches the District
Collector in terms of the afore directions, all action to demolish
the building - if it has not already been done - shall be
deferred until the resultant order as per the afore directions is
communicated to him.
Sd/-
RR DEVAN RAMACHANDRAN
JUDGE
WPC 28120/21
APPENDIX OF WP(C) 28120/2021
PETITIONER EXHIBITS
Exhibit P1 TRUE COPY OF THE PROCEEDINGS
NO.D.5307/2021/TGI/333 DATED 28.09.2021 SHOWING THE COMPENSATION DETAILS.
Exhibit P2 TRUE COPY OF THE COMPARATIVE STATEMENT OF THE AREA UNDER ACQUISITION ALONG WITH SITE PLAN PREPARED BY THE LICENSED ENGINEER.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!