Monday, 20, Apr, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

National Energy And Waste ... vs State Of Kerala
2022 Latest Caselaw 6750 Ker

Citation : 2022 Latest Caselaw 6750 Ker
Judgement Date : 14 June, 2022

Kerala High Court
National Energy And Waste ... vs State Of Kerala on 14 June, 2022
        IN THE HIGH COURT OF KERALA AT ERNAKULAM
                        PRESENT
          THE HONOURABLE MR.JUSTICE N.NAGARESH
TUESDAY, THE 14TH DAY OF JUNE 2022 / 24TH JYAISHTA, 1944
                 WP(C) NO. 4517 OF 2021
PETITIONER:

         NATIONAL ENERGY AND WASTE MANAGEMENT
         MULTIPURPOSE CO-OPERTATIVE SOCIETY (KERALA) LTD
         REGD.NO.4484
         (NEWSCO), DREAM LAND BUILDING, K.S.R.T.C. ROAD,
         CHALAKUDY P. O., THRISSUR DISTRICT,
         PIN - 680307., REPRESENTED BY CHAIRMAN,
         C.L.ANTO, IN PERSON.

         BY Party-In-Person


RESPONDENTS:

    1    STATE OF KERALA
         REPRESENTED BY ITS SECRETARY, DEPARTMENT OF
         LOCAL SELF GOVERNMENT, GOVERNMENT SECRETARIAT,
         THIRUVANANTHAPURAM - 695 001.

    2    EXECUTIVE DIRECTOR
         SUCHITWA MISSION, LOCAL SELF GOVERNMENT
         DEPARTMENT, ANDANKODE JUNCTION P. O.,
         THIRUVANANTHAPURAM - 695 014.

    3    DIRECTOR OF PANCHAYATHS
         VIKAS BHAVAN, THIRUVANANTHAPURAM - 695 014.

    4    SECRETARY
         CHEMBILOT GRAMA PANCHAYATH, P. O. MOVANCHERY,
         KANNOOR DISTRICT, PIN - 670613.

    5    VILLAGE EXTENSION OFFICER
         CHEMBILOD GRAMA PANCHAYATH, P. O. MOVANCHERY,
         KANNOOR DISTRICT, PIN - 670613.
 W.P.(C) No.4517/2021
                             :2:


    6      DIRECTOR VIGILANCE AND ANTICORRUPTION
           VANCHIYUR P. O.,
           THIRUVANANTHAPURAM - 695 004.

           BY ADVS.
           BRIJESH MOHAN
           R.RAJPRADEEP
           GOVERNMENT PLEADER SRI.APPU P S

     THIS WRIT PETITION (CIVIL) HAVING COME UP     FOR
ADMISSION ON 14.06.2022, THE COURT ON THE SAME     DAY
DELIVERED THE FOLLOWING:
 W.P.(C) No.4517/2021
                                       :3:




                           N. NAGARESH, J.

          `````````````````````````````````````````````````````````````
                       W.P.(C) No.4517 of 2021

          `````````````````````````````````````````````````````````````
                Dated this the 14th day of June, 2022

                            JUDGMENT

~~~~~~~~~

The National Energy and Waste Management

Multipurpose Co-operative Society (Kerala) Ltd. No.4484 is

the petitioner in the writ petition. The petitioner seeks the

following reliefs:

(i) Issue an appropriate writ of mandamus, order or direction to the respondents 4 and 5 t6o comply with provisions of Panchayat Raj Act, Rules and constitutional obligations, by kindly revoking Ext.P22, illegal letter or respondent No.4

(ii) Issue a writ of mandamus or any other appropriate writ, order or direction commanding respondents 1 and 2 to cancel all their illegal and arbitrary steps and to kindly cancel the two illegal and malafide lists portion of Ext.P24 (admitted by respondent No.2), aimed to marginalise the petitioner, in violation of Ext.P7, Ext.P8 direct6ions of this Hon'ble Court.

(iii) Issue such other writ, order or direction to respondents 4 and 5 commanding them to facilitate the petitioner to complete supplies, as per Ext.P13 contract, if needed, with higher volumes (1 W.P.(C) No.4517/2021

m3 plants) of plants as suggested to them during joint meeting, with additional payments, for higher volumes as mentioned in paragraph 46 of the writ petition.

(iv) Issue an appropriate writ of mandamus, order or direction to respondents 4 and 5 to stop harassing the petitioner society in arbitrary manner to weaken the petitioner society, by illegally holding the due payment etc., as part of larger conspiracy with respondents 1 and 2, by wilfully violating the provisions of Panchayat Raj Acts and Rules, constitutionally mandated duties etc.

(v) Issue an appropriate writ order or direction, directing respondents 4 and 5 to stop the constitutional violations and violations Panchayat Raj Act to pay the illegally retained money for Rs.13.65 lakhs, details as shown in paragraph 35, along with invoice Ext.P13a, which is kept pending, under oblique considerations, violating their mandated duties Schedule 3- Part B(8), Part C-XIX of Panchayat Raj Act.

(vi) Issue an appropriate writ order or direction directing respondents 4 and 5 to pay interest to the petitioner as per Ext.P13, damages, to the materials, moulds, etc. together as shown in paragraph 35 of the writ petition caused due to the illegal and arbitrary actions of respondent No.4.

(vii) Issue such other writ, order or direction to respondents 4 and 5 to pay compensation to the petitioner for the delay, loss of materials moulds etc. caused to the petitioner society due to the non- compliance of the provisions of Panchayat Raj Act, Store Purchase Manuel, etc. in a valid contract Ext.P13.

(viii) Issue such other writ, order or direction to respondents 1, 2, 4 and 5 from taking any arbitrary and vindictive decision against the petitioner and strictly adhere to Ext.P7, P8 directions of this Hon'ble Court and comply their mandated constitutional obligation towards the petitioner society.

W.P.(C) No.4517/2021

(ix) Issue such other writ, order or direction to respondent No.6 to conduct vigilance probe against respondents 1, 2, 4 and District coordinator of respondent No.2 to book the culprits as they acted contrary to the mandates of constitution, provisions of Panchayat Raj Act, in malice and arbitrary manner to cause wilful loss to the petitioner society aimed to cause illegal profit to private persons and for causing wastage of thousands of crores of rupees from the exchequers violating Exts.P7, P8 directions of this Hon'ble Court, Exts.P4, P5, P6, etc.

The petitioner is represented by its Chairman, party-in-

person.

2. The petitioner is a service provider in Waste

Management, approved by the Government of Kerala. The

Local Self Government Department of the Government of

Kerala issued Ext.P4 Government Order dated 23.05.2012

including more agencies in the panel of Service Providers, in

the field of Solid Waste Management. According to the

petitioner, the Local Self Government (LSG) Institutions, who

issue notice inviting tenders for Solid Waste Management

Services, are bound to follow the provisions contained in

Vigilance Manual, Store Purchase Manual and directions

issued by the Department for LSG.

W.P.(C) No.4517/2021

3. The 4th respondent, who is the Secretary to

Chembilode Grama Panchayat, published Ext.P10 notice

dated 15.02.2019, inviting tenders for supply 130 numbers of

0.5 m3 Biogas Plants. The petitioner submitted its tender

along with Ext.P11 covering letter dated 01.03.2019. In

Ext.P11, the petitioner suggested to the respondents that

scientific parameters require 1 m3 plants with water jackets

for smooth functioning of the units.

4. The Village Extension Officer of the Panchayat,

however, issued Ext.P12 Work Order to the petitioner

requiring to supply 210 units of biogas plants of 0.5 m 3. The

petitioner submitted agreement along with Ext.P13 letter

dated 07.03.2019, in which the petitioner informed the 4 th

respondent that 0.5 m3 inclusive of gas holder and digester

would be inadequate for processing 2.5 Kg. of waste. The

petitioner also submitted Ext.P13(a) invoice dated

25.03.2019. The petitioner states that due to the general

elections that intervened and the Kerala Floods 2019, the

supply could not be effected immediately. W.P.(C) No.4517/2021

5. The petitioner supplied 60 plants by 08.08.2019.

The 4th respondent did not pay the bill for supply nor the

additional charges required for installation, feed materials

and taxes, contends the petitioner. The petitioner therefore

submitted Ext.P15 representation to the Deputy Director of

Panchayats and requested to arrange payment in respect of

the effected supply so that balance quantities can be

supplied. The petitioner states that respondents 3 and 4 did

not take steps to make the payment and the petitioner was

forced to file W.P.(C) No.5224 of 2020 on 24.02.2020.

6. The petitioner states that in the said writ petition,

this Court directed as an interim measure to install five

biogas plants by paying ₹1,500/- per plant. The petitioner

installed five plants. The five beneficiaries gave Ext.P18

letters endorsing successful installation and satisfactory

working of the plants. The Secretary to the Panchayat,

however, issued Ext.P20 letter to the petitioner stating that

the installed plants are functioning only up to 15 minutes and

according to the Secretary's understanding, the plants W.P.(C) No.4517/2021

should function at least for 40 minutes.

7. The 4th respondent was deliberately making

objections to deny payment to the petitioner, contends the

petitioner. The petitioner sent Ext.P21 reply letter pointing out

that biogas plants of 0.5 m3 are unscientific as already made

clear by the petitioner and water jackets are to be installed

for optimum functioning of the supplied plants. The petitioner

requested the 4th respondent to effect payments against the

invoice submitted.

8. In the meanwhile, alleging that the petitioner has

supplied lesser number of plants than the 210 to be supplied

and the petitioner has installed only 8 biogas plants, that too

after the agreement period, the 4 th respondent issued

Ext.P22 letter dated 22.12.2020. In Ext P22, it was stated

that now there is no valid and subsisting contract with the

petitioner and that the petitioner is eligible only for the costs

of the supplied biogas plants for which the petitioner will have

to produce bill and receipt issued by the Panchayat. The

petitioner took up the matter with the 2 nd respondent- W.P.(C) No.4517/2021

Executive Director, Suchitwa Mission as per Ext.P24 letter

dated 25.04.2017. Respondents 2 to 4 have not taken any

steps to settle the amounts due to the petitioner, contended

the petitioner.

9. Respondents 4 and 5 resisted the writ petition,

filing a counter affidavit. Respondents 4 and 5 stated that

procurement of goods and services by Grama Panchayats is

to be based on the Procurement Manual of LSG Institutions

appended to Ext.P6 Government Order. LSG institutions

have to follow the Procurement Manual. In the tender

proceedings for procuring biogas plants, the petitioner

became the lowest tenderer, quoting ₹6,500 /- per unit. The

selected service provider has to follow the instructions and

guidelines issued by the Government from time to time in the

matter of supply, installation and maintenance of the biogas

plant.

10. Ext.P10 tender notice clearly indicated that the

unit cost of biogas plant is ₹10,500/- per unit. As it was a

limited tender among the accredited service providers, the W.P.(C) No.4517/2021

petitioner ought to have known the specification, condition of

installation and maintenance protocols as laid down by the

Government Orders. As per Ext.R4(a) Government Order,

the unit cost is including cost of materials, labour,

conveyance including installation at households/user

locations and commissioning facility. Cost is also inclusive of

taxes payable. All incidental expenditure including cow dung

and other expendable items required for completing the unit

has to be provided and it is inclusive in the unit cost. The

agency undertaking the supply is bound to train the

beneficiary in operation and capacity building of the unit. The

agency should also provide one year warranty from the date

of installation of the unit.

11. Respondents 4 and 5 stated that 0.5 m3 biogas

plants were ordered in view of the standard specifications

prescribed by the Suchitwa Mission which is a governmental

agency. The Panchayat cannot change the components of

an approved project. While the Panchayat earmarked

₹10,500/- per unit, the petitioner quoted ₹6,500/- per unit, W.P.(C) No.4517/2021

due to which the Panchayat increased the number of units

from 130 to 210. The petitioner submitted two sets of

preliminary agreements which clearly stated that a biogas

plant should be of size 0.05 m3 with water jacket. But, in the

final agreement submitted by the petitioner, the words "with

water jacket" were replaced by the words "devoid of water

jacket". The implementing officer could not recognise the

substitution of words. Merely because the 5 th respondent

could not detect the change, the petitioner cannot deviate

from the guidelines and government directions, contended

respondents 4 and 5.

12. The petitioner supplied only 60 units so far.

Ext.P13 agreement became null and void due to lapse of

time. The petitioner did not install even a single unit. As per

government directions, there cannot be separate installation

charges in the case of biogas plants. Some of the

beneficiaries installed the units themselves. The units were

not working and no training was provided by the petitioner.

The District Ooordinator of Suchitwa Mission found that the W.P.(C) No.4517/2021

petitioner had supplied biogas plants without water jacket

and that causes malfunctioning.

13. Pursuant to the interim orders of this Court in W.P.

(C) No.5224 of 2020, the petitioner installed five biogas

plants. Respondents 4 and 5 submitted that it is learnt that

biogas plants with 0.5 m3 capacity with water jacket are still

functioning satisfactorily in other places in the State. As the

petitioner failed to adhere to the conditions in the contract,

the Panchayat on 04.11.2020 decided to terminate the

contract and the Panchayat issued Ext.P22 termination letter

on 22.12.2020. The Panchayat was forced to terminate the

contract due to the inordinate delay in implementing the

project. The writ petition is therefore liable to be dismissed.

14. The 3rd respondent also resisted the writ petition

filing counter affidavit. The 3rd respondent stated that the

standard specifications are prescribed by Suchitwa Mission,

which is the governmental agency, in this matter. The

Panchayat cannot change the components of an approved

project on its own relying upon the words of a service W.P.(C) No.4517/2021

provider. While the Panchayat earmarked ₹10,500/- per unit,

the petitioner offered to supply at the rate of ₹6,500/- per

unit. In the preliminary agreement, water jacket was included

as an essential component. The service provider cannot

circumvent government orders by entering into any legal

agreement stating entirely new conditions, contrary to the

Government Orders.

15. I have heard the petitioner-party-in-person, the

learned Government Pleader representing respondents 1 to

3 and 6 and the counsel appearing for respondents 4 and 5.

16. The grievance of the petitioner relates to the

alleged violations of contractual terms, non-payment of bill

for the biogas plants supplied and inclusion of alleged

ineligible entities in Ext.P24 panel of service providers under

the Suchitwa Mission. The petitioner was found to be the

lowest tenderer in Ext.P10 tender proceedings of

Chembilode Grama Panchayat. Ext.P13 agreement was

signed by the petitioner for supply of 210 biogas plants.

Ext.P12 work order for supply of 210 biogas plants was W.P.(C) No.4517/2021

issued by the 5th respondent-Village Extension Officer.

17. The biogas plants were to be supplied in tranches

of 30 numbers. It is an admitted position that the petitioner

has supplied 60 biogas plants. There was admittedly delay

on the part of the petitioner in supply, which was attributable

to the intervening general elections and Kerala Floods. The

petitioner would allege that they have transported the

component parts of the remaining biogas plants to the work

site provided by the Grama Panchayat. The Panchayat

authorities, however, would dispute receipt of any such

component parts.

18. Admittedly, the 4th respondent has not settled the

Bill in respect of the first two tranches of supply (30+30) of

biogas plants made by the petitioner. The 4 th respondent

would state that the petitioner is not entitled to payment for

more than one reason. Firstly, the supply was not made

within the stipulated time. Secondly, the petitioner has not

installed the biogas plants in the houses of beneficiaries.

Thirdly, the petitioner has not supplied water jackets which W.P.(C) No.4517/2021

are to be part of the biogas plants. Fourthly, the petitioner

has not provided training classes for the beneficiaries as

agreed. And to top it all, the biogas plants supplied by the

petitioner are not functioning properly and even where the

petitioner has installed the plants pursuant to the interim

direction of this Court, there are complaints of

malfunctioning.

19. As regards the delay in supplying biogas plants,

as per the contractual terms, the supply ought to have been

made within 90 days of work order. Ext.P12 work order was

issued on 06.03.2019 and the said period came to an end on

05.06.2019. The petitioner effected the supply only in the

month of August, 2019. However, it is an admitted position

that there was intervening general elections during April-May,

2019 and consequential Code of Conduct. Thereafter, during

and after the supply of 60 biogas plants by the petitioner, the

Kerala Floods occurred. The counsel for the 4 th respondent,

during the hearing of the case, submitted that the contract

was extended till 06.06.2020. Therefore, it has to be held W.P.(C) No.4517/2021

that the petitioner has supplied 60 biogas plant units, within

the contractual period.

20. As regards the remaining quantities, the case of

the petitioner is that the petitioner has transported the

component materials to the work site in the Panchayat. The

4th respondent would contend that the Panchayat has not

received any component materials from the petitioner. There

is nothing on record to arrive at a finding in this regard.

21. The 4th respondent has taken a stand that the

petitioner was bound to provide water jackets along with the

biogas plants. However, Ext.P13 agreement would indicate

that the biogas plants to be supplied by the petitioner, are to

include Digester and Gas Holder but "devoid of water jacket".

When the agreement entered into by the Grama Panchayat

and the petitioner specifically excluded water jacket, the 4 th

respondent cannot be heard to contend that the petitioner

ought to have provided free of cost water jackets along with

biogas plants.

W.P.(C) No.4517/2021

22. The 4th respondent would contend that the

agreement excluding water jacket was signed due to a

mistake and the petitioner is bound by the guidelines and

instructions of the Government and therefore, the petitioner

is required to provide water jacket along with each biogas

plant. The 4th respondent did not bring to the notice of this

Court any guideline or government direction which prohibits

tendering of biogas plant without water jacket. At any rate,

after signing Ext.P13 agreement, the 4 th respondent cannot

take a contrary stand.

23. The 4th respondent would argue that the petitioner

ought to have installed biogas plants in the houses of

beneficiaries. The 4th respondent relied on Ext.R4(a) G.O. to

urge that the unit cost would include installation at

households. However, it has to be noted that Clause 6 of

Ext.P13 agreement with the petitioner provides that the

Grama Panchayat will provide proper address, telephone

numbers, etc. for effective supply of plants "in cases where

the installations are needed". Clause 11 mandates that if the W.P.(C) No.4517/2021

installations are not needed, the petitioner will conduct a

class to guide the beneficiaries regarding installation.

24. Exts.P13 letter dated 07.03.2019 issued by the

petitioner to the 4th respondent would show that the petitioner

had required the respondents to provide list of beneficiaries

along with telephone numbers. The 4 th respondent has no

case that such a list has been supplied to the petitioner. The

only conclusion possible therefore is that the Panchayat or

the beneficiaries did not require installation of biogas plants

by the petitioner.

25. Ext.P21 communication of the petitioner would

show that the petitioner was ready to take classes to the

beneficiaries. There is no document on the side of the 4 th

respondent which would indicate that the petitioner was

required to come and conduct classes for the beneficiaries

on any particular day or time or at any venue. In the

absence of supply of list of address and telephone number of

beneficiaries, the petitioner could not have itself arrange

classes. Therefore, the said defence of the 4 th respondent W.P.(C) No.4517/2021

cannot be accepted.

26. The 4th respondent will finally urge that the biogas

plants supplied by the petitioner are not functioning properly,

inasmuch as the functioning lasts for only about 15 minutes

and not 40 minutes, as expected. In this regard, it is

pertinent to note that from the initial stage, the petitioner has

been pointing out that the 0.5 m 3 biogas plants are not viable

and would not give optimum utility.

27. In Ext.P11 communication dated 01.03.2019 itself,

the petitioner pointed out that a minimum of 1 m 3 plant with

water jacket is needed for smooth functioning to manage a

minimum waste of 5 Kg. per day. The petitioner reiterated

this in Ext.P21 communication also. Furthermore, Ext.P28

minutes of the meeting of service providers convened in the

presence of Executive Director of Suchitwa Mission would

show that the service providers collectively informed the

Director that 0.5 m3 biogas plants are failure and the said

meeting decided to take steps to get permission to install

1 m3 biogas plants retaining subsidy. Therefore, it can only W.P.(C) No.4517/2021

be inferred that the reduced performance of 0.5 m 3 plants is

due to inherent lacuna of the project idea and cannot be

attributed to the quality of plants supplied by the petitioner.

28. Furthermore, it has to be noted that this Court in

W.P.(C) No.5224 of 2020 passed an interim order on

23.09.2020 directing the petitioner to install five units in

houses and directing the 4 th respondent to pay ₹1,500/- per

unit as installation charges. The petitioner installed the five

units. All the five beneficiaries have given letters as per

Ext.P18, certifying their satisfaction on the functioning of the

biogas plant units installed. This would also go to show that

the biogas plants supplied by the petitioner were flawless.

29. In the facts and circumstances of the case, the

petitioner is entitled to receive the cost of the biogas plants

supplied by the petitioner. As a matter of fact, the 4 th

respondent has admitted in Ext.P22 letter that the petitioner

is eligible for the cost of supplied biogas plants on the

petitioner producing the bill and receipt issued by the

Panchayat at the time of supply of plants. According to the W.P.(C) No.4517/2021

petitioner, they have already submitted the same to the

Panchayat. At any rate, the supply of 60 biogas plants and

installation of five gas plants as per interim orders of this

Court, are not in dispute.

30. As regards termination of the contract as per

Ext.P22 and entitlement of the petitioner to receive cost of

components of plants allegedly transported by the petitioner

to the work site, this Court is of the view that these issues

involve disputed questions of fact and cannot be decided in

these writ proceedings. The petitioner and the 4 th

respondent will be at liberty to pursue their respective claims

before the appropriate legal forum.

31. The petitioner has sought to quash a panel of

service providers selected by the respondents, which has

been appended to Ext.P24. There are no materials

whatsoever available to hold that any of the agencies

enlisted in the panel is ineligible to be empanelled. Such

entities are not parties to the writ petition either. The prayer

of the petitioner in this regard, is therefore liable to be W.P.(C) No.4517/2021

rejected.

In the result, the writ petition is partly allowed. The

4th respondent is directed to pay the cost of biogas plants

supplied by the petitioner and installation charges at the rate

of ₹1,500/- in respect of the plants installed by the petitioner

pursuant to the interim order dated 23.09.2020 of this Court

in W.P.(C) No.5224 of 2020, if those charges are not already

paid. Challenge against Ext.P24 is repelled. Other issues

are left open and the parties are at liberty to agitate those

issues before appropriate legal forum.

Sd/-

N. NAGARESH, JUDGE aks/13.06.2022 W.P.(C) No.4517/2021

APPENDIX OF WP(C) 4517/2021

PETITIONER'S EXHIBITS

EXHIBIT P1 TRUE COPY OF THE DOWN LOADED VERSION

SHOWING THE PITIFUL CONDITION OF THE WASTE MANAGEMENT IN THE STATE BEFORE 2011.

EXHIBIT P2             TRUE COPY OF THE FIRST FEW PAGES OF
                       THE DETAILED PROJECT REPORT OF THE
                       PETITIONER SUBMITTED TO THEN C. M. OF
                       KERALA     DATED    26.06.2011,    WITH
                       INSTRUCTIONS     TO     DISCUSS    WITH
                       PETITIONER TO SUBMIT REPORT TO THE
                       CABINET.
EXHIBIT P3             TRUE COPIES OF SOME RELEVANT PAGES
                       FROM A SCIENTIFIC BOOK DEALING WITH
                       THE BIOGAS PLANTS.
EXHIBIT P4             TRUE COPY OF RELEVANT PORTION OF THE

G.O.1418/12/LSGD DATED 23.05.2012.

EXHIBIT P5 TRUE COPIES OF SOME RELEVANT PORTIONS OF THE STORES PURCHASE MANUEL G. O.(P) NO.03/2013 SPD DATED 21.06.2013.

EXHIBIT P6 TRUE COPY OF RELEVANT PAGES OF G.O.NO.

(P) 259/2010/LSGD DATED 08.11.2010 ISSUED BY LSG DEPARTMENT.

EXHIBIT P7 TRUE COPY OF ONLY THE ORDER PORTION OF DIRECTION IN WPC 28921/12 DATED 14TH DEC. 2012.

EXHIBIT P8 TRUE COPY OF ORDER IN WPC 35261/19 DATED 19.12.19.

EXHIBIT P9 TRUE COPY OF THE G.O.NO.151/12/LSGD, DATED 13.01.12 FOR BIGGER PLANTS AND POWER PRODUCTION.

EXHIBIT P10 TRUE COPY OF THE TENDER NOTICE FOR SUPPLY OF BIOGAS PLANTS OF 0.5M 3 SIZE.

EXHIBIT P11 TRUE COPY OF COVERING LETTER IN E TENDER, QUOTE FOR SUPPLY OF PLANTS ETC. DATED 1ST MARCH, 2019.

 W.P.(C) No.4517/2021



EXHIBIT P12            TRUE COPY OF WORK ORDER BASED ON A
                       DECISION    OF    THE    COUNCIL    DATED

06.03.2019, FOR ONLY SUPPLY OF PLANTS. EXHIBIT P13 TRUE COPY OF THE FINAL AGREEMENT WITH THE RESPONDENTS 4 AND 5 DATED 07.03.19 FOR SUPPLY OF PLANTS, PAYMENT ETC.

EXHIBIT P13a TRUE COPY OF THE P. INVOICE 201/19 DATED 25.03.19 FOR RS. 13.65 LAKHS.

EXHIBIT P14 TRUE COPY OF ONE OF SUCH REPRESENTATIONS DATED 21.02.2020 SENT TO RESP.4 ETAL. DEMANDING OVER DUE PAYMENT.

EXHIBIT P15 TRUE COPY OF LETTER WRITTEN TO DEPUTY DIRECTOR, PANCHAYATH DATED 07.01.20 ABOUT THE NON PAYMENT, VIOLATION OF THE MANDATED DUTIES BY THE SECRETARY.

EXHIBIT P16            TRUE COPY OF THE LATEST BANK STATEMENT
                       FROM   HDFC    BANK   DTD.    26.02.2020,
                       SHOWING FINANCIAL CRUNCHES.
EXHIBIT P17            TRUE COPIES OF TWO OF THE NOTICES SENT
                       BY CATHOLIC SYRIAN BANK FOR THE
                       REDEMPTION OF GOLD HYPOTHECATED FOR
                       THE    SOCIETY,     WITH    BANK    DATED
                       27.01.2020.
EXHIBIT P18            TRUE COPY OF THE SATISFACTORY LETTER
                       FROM THE BENEFICIARIES STATING THE
                       PLANT ARE WORKING.
EXHIBIT P19            TRUE COPIES OF PHOTOGRAPHS TAKEN WITH
                       BENEFICIARIES    SHOWING    PLANTS    ARE
                       WORKING.
EXHIBIT P20            TRUE COPY OF THE LETTER SENT BY THE
                       SECRETARY   OF    CHEMBILOD    PANCHAYATH
                       DATED 19TH NOV. 2020, SHOWING PLANTS
                       ARE WORKING.
EXHIBIT P21            TRUE   COPY    OF    THE   REPLY    DATED

26.02.2020 EXPLAINING THAT PLANTS OF 0.5 M 3 CAN WORK ONLY 10-20 MINUTES AS PER SCIENCE.

EXHIBIT P22 TRUE COPY OF ARBITRARY AND ILLEGAL LETTER OF RESP. NO.4 DATED DEC. 2020 TERMINATING CONTRACT.

W.P.(C) No.4517/2021

EXHIBIT P23 TRUE COPY OF THE REPLY BY PETITIONER DATED 26TH DEC. POINTING MALA FIDE CONTEMPT OF COURT AND URGING TO REINSTATE CONTRACT ETC.

EXHIBIT P24 TRUE COPY OF LETTER DATED 25.03.2017 ALONG WITH TWO LISTS ADMITTEDLY ISSUED 18.08.2013 AND 05.10.2018, IN VIOLATION EXT. P-7, 8 DIRECTIONS OF HIGH COURT THAT TOO WITHOUT GIVING ANY ORDER TO THE PETITIONER.

EXHIBIT P25            TRUE COPY OF THE AUTHORIZATION OF THE
                       BOARD   OF    THE   PETITIONER    DATED
                       02.07.2019.
EXHIBIT P27            COPY OF RELEVANT PAGE NO.27 FROM
                       SCIENTIFIC PUBLISHED BY IRENA.
EXHIBIT P28            COPY OF COVERING LETTER DT 6.3.2015.
Exhibit P29            TRUE COPY OF THE FINAL NOTICE SENT
                       FROM CSB BANK, DTD. 4/5/2022 SHOWING

AUCTIONING THE GOLD PAWNED, FOR UNDER TAKING THE WORK ALLOTTED BY RESP.

NO.4, ON 18TH MAY, 2022 Exhibit P30 TRUE COPY OF THE LETTER DATED 30/5/2019 SHOWING THE DELAY DUE TO ELECTION IS EXPLAINED AND BILL WILL BE RAISED AS PER ACTUAL SUPPLIES THROUGH MATERIALS FOR ENTIRE 210 PLANTS WERE SUPPLIED ON 06/03/2019 BEFORE RAISING THE BILL DATED 25/3/2019 SHOWING AS SUPPLIES OF ENTIRE PLANTS EFFECTED (REF.EXT.P13A. FOR IM3 PLANTS AFTER DISCUSSIONS) Exhibit P31 TRUE COPY OF LETTER DATED 8/11/2019 GIVEN DIRECTLY TO RESP. NO.4 BY OUR DIRECTOR THOMAS PETITIONER SHOWING BILLS FOR TWO SUPPLIES OF 30 EACH ARE PENDING, FOR THE SUPPLIES MADE BY AUGUST, 2019 THOUGH THE RESP. NO.4 IS MANDATED BY THE AGREEMENT - CLAUSE 0.2 TO MAKE 80 % OF THE PAYMENT ON SUPPLY, BEFORE NEXT SUPPLY W.P.(C) No.4517/2021

Exhibit P32 TRUE COPY OF LETTER DATED 8/8/2019 SHOWING BALANCE 60 BURNERS AND VALVES ARE SENT (BALANCE OF BURNERS AND VALVES REMAINING AFTER THE SUPPLY AS PER EXT.P30 AND BILL EXT.P13 A Exhibit P33 CONSOLIDATED SINGLE BILL SENT THROUGH ON OF OUR DIRECTORS LATER AS PER REQUEST OF RESP. NO.4 FOR 60 PLANTS ALREADY SUPPLIED.

Exhibit P34 TRUE COPY OF BILL DATED 7/3/2019 FOR TWO PLANTS AS 0.5 MS PLANTS (THROUGH ONE PLANT IS OF 0.5 M3 AND ANOTHER IS OF 1M3 AS FIRST SAMPLES, AND TO BE PART OF SUPPLIES AS USUAL PRACTICE) Exhibit P35 TRUE COPY OF BILL DATED 20/3/2019 FOR TWO PLANTS AS ONE PLANT OF 0.5M3 AND ANOTHER PLANT OF 1M3 AS PER THE SUGGESTION OF RESP. NO.4 AND 5 AS MOST OF THE SUPPLIES WILL BE OF 1 M3.

Exhibit P36             LETTER   FROM   DISTRICT     COORDINATOR
                        SUCHITWA   MISSION    DATED    29/1/2020
                        REVEAL    THE     CONSPIRACY     AGAINST

PETITIONER AS HE WELL AWARE OF EXT.P28 OF 2015

RESPONDENT'S EXTS

R4(A) COPY OF GO DT 20.9.2012 R4(B) COPY OF PRELIMINARY AGREEMENTS DT 2.3.2019. R4(C) COPY OF LETTER DT 4.7.2019 BY 4TH RESPONDENT. R4(D) COPY OF LETTER DT 29.1.2020 BY DISTRICT COORDINATOR.

R4(E) COPY OF ORDER DT 23.9.2020 IN WPC.5224/2020. R4(F) COPY OF ORDER DT 28.10.2020 IN WPC.5224/2020

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter