M/S. Om Construction vs Engineer In Chief
2022 Latest Caselaw 6732 Ker

Citation : 2022 Latest Caselaw 6732 Ker
Judgement Date : 14 June, 2022

Kerala High Court
M/S. Om Construction vs Engineer In Chief on 14 June, 2022
             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                             PRESENT
             THE HONOURABLE MR. JUSTICE SATHISH NINAN
  TUESDAY, THE 14TH DAY OF JUNE 2022 / 24TH JYAISHTA, 1944
                        AR NO. 54 OF 2022
PETITIONER/S:

         M/S. OM CONSTRUCTION,SR NO 47/1, HOUSE NO.1240
         VIGHNAHAR PARK, SUNITA NAGAR, WADGAON SHERI
         PUNE - 411014 REPRESENTED BY ITS MANAGING PARTNER
         MR. SAMEER PRABHAKAR GAIKWAD.
         BY ADVS.
         MADHU RADHAKRISHNAN
         NELSON JOSEPH
         M.D.JOSEPH
         DEEPAK ASHOK KUMAR


RESPONDENT/S:

    1    ENGINEER IN CHIEF
         DIRECTORATE OF CONTRACT ADMINISTRATION AND
         MANAGEMENT MILITARY ENGINEER SERVICES
         ARMY HEAD QUARTERS, KASHMIR HOUSE, RAJAJI MARG
         NEW DELHI - 110011.
    2    CHIEF ENGINEER (NW) KOCHI
         MILITARY ENGINEER SERVICES, KATARIBAGH, NAVAL
         BASE (PO),KOCHI - 682004.
    3    GARRISON ENGINEER (FORT) KOCHI,MILITARY ENGINEER
         SERVICES, FORT KOCHI - 682001.
         BY ADV S.KRISHNA


     THIS ARBITRATION REQUEST HAVING COME UP FOR ADMISSION
ON 14.06.2022, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
                         Sathish Ninan, J.
                ==============================
               Arbitration Request No.54 of 2022
                  ==========================
             Dated this the 14th day of June, 2022

                                  JUDGMENT

The petitioner entered into a contract with the

respondents with regard to the work of "Repair for

replacement of Fresh Water Distribution Pipelines".

Exts A1 to A3 are the documents relating to the

contract. According to the petitioner, the work was

completed before the agreed date of completion and they

sought for issuance of completion certificate. However,

the respondents took the stand that the work as agreed

has not been completed and 20% of the work still

remains. There arose dispute between the parties. Though

the contract between the parties contains an arbitration

clause and though the petitioner sought for appointment

of an arbitrator in terms thereof, the respondent have

not co-operated. It is on the said contention that the

petitioner has approached this Court under Section 11 of

the Arbitration and Conciliation Act, 1996.

2. The respondents have filed a statement denying

the averments in the arbitration petition, on its

merits.

3. I have heard the learned counsel Sri.Madhu

Radhakrishnan on behalf of the petitioner and

Smt.S.Krishna, the learned Central Government Standing

Counsel.

4. That the contract in question contains an

arbitration clause, is admitted. There is dispute

between the parties regarding the stage of the work, as

to whether it is completed in terms of the contract or

not. It is a matter for consideration by the arbitrator.

The respondents have placed on record a panel of

arbitrators constituted by the Ministry of Defence. It

is submitted by the learned counsel for the respondents

that an arbitrator from the said panel could be

appointed. The learned counsel for the petitioner

submits that the nominees of the respondent may not be

appointed since the petitioner would have concerns over

a possible bias.

5. I deem it only appropriate that an independent

arbitrator be appointed to arbitrate into the dispute

between the parties.

6. In the light of the above, the Arbitration

Request is ordered as hereunder :-

(a) Rtd. Justice. Sunil Thomas,68/1288A,

St.Benedict's Extension Road, Kochi - 682018, is

provisionally nominated as the Sole Arbitrator to

adjudicate upon the disputes between the parties arising

out of Annexure A1 to A3.

(b) A copy of this order shall be communicated to

the learned Arbitrator by the Advocate of the applicant

within a period of one week from today. A copy of the

order shall also be forwarded to the learned Arbitrator

by the Registry in his address.

(c) The Arbitrator is requested to forward his

statement of disclosure under Section 11(8) r/w. Section

12(1) of the Act 3 of 2016. The disclosure statement

shall be placed before this Court for confirmation of

the appointment of the Arbitrator.

(d) The Arbitrator's fees shall be governed by the

Kerala High Court (Fee Payable to Arbitrators) Rules,

2017.

(e) The arbitration costs and fees shall be shared

equally.

(f) The interim order of stay granted by this Court

on 05.04.2022 will not be operative any further.

Sd/-

Sathish Ninan, Judge vdv APPENDIX OF AR 54/2022

PETITIONER ANNEXURES Annexure A1 TRUE COPY OF THE TENDER ACCEPTANCE LETTER DATED 25.06.2020 Annexure A2 TRUE COPY OF THE GENERAL CONDITIONS OF CONTRACTS FOR LUMPSUM CONTRACTS.

Annexure A3 TRUE COPY OF THE ERRATA TO THE GENERAL CONDITIONS OF CONTRACT IAFW-2249 Annexure A4 TRUE COPY OF THE LETTER DATED 22.09.2021 SUBMITTED BY THE PETITIONER BEFORE THE 3RD RESPONDENT.

Annexure A5 TRUE COPY OF THE LETTER DATED 23-9-2021 ISSUED BY THE 3RD RESPONDENT.

Annexure A6 TRUE COPY OF THE REPLY STATEMENT DATED 06.10.2021 ISSUED BY THE PETITIONER TO THE 3RD RESPONDENT.

Annexure A7 TRUE COPY OF THE ARBITRATION INVOKING LETTER DATED 12.10.2021 ISSUED BY THE PETITIONER. Annexure A8 TRUE COPY OF THE REPLY LETTER DATED 29.10.2021 ISSUED BY THE 3RD RESPONDENT. Annexure A9 TRUE COPY OF THE LETTER DATED 01.11.2021 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER Annexure R1(a) A true copy of the award of tender dated 25.06.2020 Annexure R1(b) A true copy of the work order dated 10.08.2020 Annexure R1(c) A true copy of the letter dated 18.02.2021 Annexure R1(d) A true copy of the notice dated 21.06.2020 Annexure R1(e) A true copy of the letter dated 09.08.2021 Annexure R1(f) A true copy of the letter dated 20.09.2021 Annexure R1(g) A true copy of the letter dated 01.11.2021 Annexure R1(h) A true copy of the letter dated 08.11.2021 Annexure R1(j) A true copy of the letter dated 18.10.2021 Annexure R1(k) A true copy of the communication dated 29.10.2021 Annexure R1(l) A true copy of the letter dated 02.11.2021 Annexure R1(m) A true copy of the letter dated 18.10.2021 Annexure R1(n) A true copy of the relevant extract of the General Conditions of Contract Annexure R1(o) A true copy of the panel of arbitrators

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IDRC

 
 
Latestlaws Newsletter