Citation : 2022 Latest Caselaw 719 Ker
Judgement Date : 17 January, 2022
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
MONDAY, THE 17TH DAY OF JANUARY 2022 / 27TH POUSHA, 1943
WP(C) NO. 21159 OF 2021
PETITIONER:
MUHAMMED NOUFAL C,
AGED 29 YEARS,
S/O ABOO, CHOLAMUGATH HOUSE,
VALAMKULAM P.O., PERINTHALMANNA,
MALAPPURAM DISTRICT-679 357.
BY ADV BIJU ABRAHAM
RESPONDENTS:
1 THE CHIEF MANAGER,
KERALA INSTITUTE OF LOCAL ADMINISTRATION,
PROJECT MANAGEMENT UNIT-KILA-KIIFB,
KLLA REGIONAL CENTRE, KUMARAPURAM P.O.,
THIRUVANANTHAPURAM DISTRICT-695 011.
2 EXECUTIVE ENGINEER,
OFFICE OF THE EXECUTIVE ENGINEER,
LSG DIVISION, PALAKKAD DISTRICT-678 721.
3 ASSISTANT ENGINEER,
MANNARKKAD MUNICIPALITY, MANNARKKAD-678 582.
4 ASSISTANT EXECUTIVE ENGINEER,
LSGD SUB DIVISION,
MANNARKKAD BLOCK PANCHAYATH,
MANNARKKAD-678 582.
R1 BY ADV SRI.V.A.MUHAMMED, SC, KILA
R3 BY ADV.SRI.P.R.VENKATESH, SC
SRI.APPU P.S., GOVERNMENT PLEADER
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
17.01.2022, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No.21159/2021
2
JUDGMENT
Dated this the 17th day of January, 2022
The petitioner, aggrieved by the improper and illegal
steps taken by the respondents in connection with the tender
for construction of School building in Mannarkkad, has filed
this writ petition seeking to direct the respondents to
refund/pay to the petitioner the deposit and expenses met by
him in connection with the agreement No.92/CL-
23/CMPMU/KILA-KIIFB/2020-21 dated 26.02.2021 with
interest to the petitioner, within a time limit fixed by this Court.
2. The petitioner states that he entered into an
agreement with the respondents for construction of the School
building of GUPS, Mannarkkad in Mannarkkad Municipality in
Palakkad District. The agreement was executed on WP(C).No.21159/2021
26.02.2021. As per the agreement, the work had to be
completed within six months from the date of handing over the
site to the petitioner. The petitioner submits that the work site
was not handed over to the petitioner. After about two months
of execution of the agreement, the petitioner sent a notice
dated 19.04.2021, requiring to handover the site. The request
was not positively responded to. The petitioner again
submitted another representation on 05.07.2021. The
representation dated 05.07.2021 also did not yield any result.
3. The petitioner submits that thereafter on
04.08.2021, the petitioner submitted Ext.P7 representation
requiring the respondents to relieve him from the contractual
liability and to repay the amount deposited by the petitioner in
connection with the contract. The respondents thereafter
issued a letter to the petitioner to carry out the work. The
learned counsel for the petitioner submits that after the period
of contract, the petitioner cannot be forced to complete the
work. The respondents did not handover the site to the WP(C).No.21159/2021
petitioner for completion of the work. In the circumstances, the
respondents are compellable to relieve the petitioner from the
contractual obligations and also to refund the amount
deposited by the petitioner.
4. The 1st respondent contested the writ petition filing a
Statement. The 1st respondent stated that he addressed the
Director of KILA on 28.10.2021 stating the lapses on the part
of the petitioner in carrying out the works he undertook. The
petitioner did not respond to the notice dated 08.09.2021 to
handover the work site. The petitioner failed to commence the
work which was undertaken by him. Therefore, the petitioner
is not entitled to any relief. The respondents further submitted
that the reliefs sought for by the petitioner are not liable to be
granted in exercise of the discretionary jurisdiction of this
Court under Article 226 of the Constitution of India. The
remedy available to the petitioner is to approach the Civil
Court.
WP(C).No.21159/2021
5. Heard the learned counsel for the petitioner and the
learned Standing Counsel representing the 1st respondent.
6. It is not disputed that the petitioner had entered into
an agreement with the 1st respondent on 26.02.2021. The
period allocated for completion of the work was six months
from the date of handing over of the site. It is further not
disputed that the work site was not handed over to the
petitioner within the period of six months.
7. The petitioner has submitted notices to the
respondents seeking handing over of the site in the month of
April and July, 2021. The site was not handed over.
Subsequently, after expiry of about six months, the petitioner
sent Ext.P7 representation requiring to relieve him from the
contractual liabilities. It is at this stage that the 1 st respondent
and its officers required the petitioner to resume the work.
This Court finds that the respondents handed over the work
site for carrying out the work, after the period stipulated for
completion of work under the contract. The respondents WP(C).No.21159/2021
cannot compel the petitioner to start and complete the work so
belatedly. The action of the respondents in requiring the
petitioner to start the work after about seven months of
execution of the agreement when the stipulated period for
completion of work is six months, is therefore unjustified.
Consequently, it is declared that the petitioner is entitled to get
relieved from the contractual obligations.
The writ petition is disposed of declaring that the
petitioner should be relieved from the contractual obligations in
respect of the work in question. The respondents are directed
to refund the amount deposited by the petitioner with the
respondents in connection with the agreement, within a period
of two months. The question of payment of interest and
compensation is left open.
Sd/-
N. NAGARESH JUDGE SR WP(C).No.21159/2021
APPENDIX OF WP(C) 21159/2021
PETITIONER'S EXHIBITS:
Exhibit P1 A TRUE COPY OF THE TENDER ACCEPTANCE
NOTICE DATED 20.02.2021 ISSUED BY THE
1ST RESPONDENT TO THE PETITIONER
Exhibit P2 A TRUE COPY OF THE FORMAT OF CONTRACT
AGREEMENT COMMUNICATED TO THE
PETITIONER BY THE 1ST RESPONDENT ALONG WITH A LETTER OF ACCEPTANCE NOTICE Exhibit P3 A TRUE COPY OF THE LETTER GIVEN BY THE PETITIONER TO THE 3RD RESPONDENT DATED 5.4.2021 Exhibit P4 A TRUE COPY OF THE COMMUNICATION DATED 19.4.2021 BY THE PETITIONER TO THE 1ST RESPONDENT Exhibit P5 A TRUE COPY OF THE LETTER DATED 5.7.2021 GIVEN BY THE PETITIONER TO THE 1ST RESPONDENT Exhibit P6 A TRUE COPY OF THE COMMUNICATION OF THE 1ST RESPONDENT DATED 22.7.2021 Exhibit P7 A TRUE COPY OF THE NOTICE SEND BY THE PETITIONER THROUGH HIS LAWYER DATED 4.8.2021 Exhibit P8 A TRUE COPY OF THE COMMUNICATION DATED 24.8.2021 OF THE 1ST RESPONDENT TO THE PETITIONER Exhibit P9 A TRUE COPY OF THE LETTER SEND BY THE PETITIONER THROUGH HIS LAWYER HATED 27.8.2021 TO THE RESPONDENTS Exhibit P10 A TRUE COPY OF THE NOTICE WITH APPENDIX ISSUED BY THE 3RD RESPONDENT TO THE PETITIONER DATED 13.9.2021
RESPONDENTS' EXHIBITS:
ANNEXURE 1 TRUE COPY OF THE LETTER No.CM/KILA-
KIIFB-PMU/CL-23/87/2020 DATED 28.10.2021 OF THE CHIEF MANAGER, KILA.
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!