Citation : 2021 Latest Caselaw 19761 Ker
Judgement Date : 23 September, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE P.V.KUNHIKRISHNAN
THURSDAY, THE 23RD DAY OF SEPTEMBER 2021 / 1ST ASWINA, 1943
WP(C) NO. 8496 OF 2021
PETITIONER/S:
M.C.BABY
AGED 58 YEARS
S/O.CHACKO, MATTATHIL HOUSE, MONAPPILLY,
PUTHENCRUZ P.O., ERNAKULAM-682308.
BY ADVS.
TESSY JOSE
SRI.ELDHO PAUL
RESPONDENT/S:
1 STATE OF KERALA
REPRESENTED BY PRINCIPAL SECRETARY, PUBLIC WORKS DEPARTMENT,
ROADS AND BRIDGES, SECRETARIAT, THIRUVANANTHAPURAM-695001.
2 THE SUPERINTENDING ENGINEER,
P.W.D., ROADS AND BRIDGES,
CENTRAL CIRCLE,
ALUVA-683101.
3 THE ASSISTANT ENGINEER,
PWD ROADS SECTION, MULLANTHURUTHY-682014.
4 THE ASSISTANT EXECUTIVE ENGINEER,
PWD ROADS, SUB DIVISION, THRIKKAKARA,
ERNAKULAM-682021.
5 THE EXECUTIVE ENGINEER,
PWD ROADS DIVISION, THRIKKAKARA P.O.,
ERNAKULAM-682021.
BY ADV GOVERNMENT PLEADER
SMT. DEEPA NARAYANAN, SR.GP
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 23.09.2021,
THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C) NO. 8496 OF 2021
2
P.V.KUNHIKRISHNAN, J.
===================
WP(C) No. 8496 OF 2021
===================
Dated this the 23rd day of September 2021
JUDGMENT
The above writ petition is filed with the following
prayers;
" i) Issue a writ of certiorari to quash Exts.P3 and P5 orders passed by the 2nd respondent.
ii. To grant such other relief as this Hon'ble Court may deem fit in the facts and circumstances of the case."
2. The main grievance of the petitioner is that, the
fine imposed in Exts. P3 and P5 orders for extension of
completion of the work is illegal, in the light of the remarks
by the respondents in Exts. P2 and P4 application.
3. The learned counsel for the petitioner submitted
that, an application for extension of time for the completion WP(C) NO. 8496 OF 2021
of work was submitted as evident by Ext.P2 on 09.01.2019.
The date of completion as per the agreement was on
09.01.2019 and the petitioner prayed for extension up to
30.05.2019. Column 7 of Ext.P2 is the reason mentioned for
not completing the work by the petitioner and the same is
extracted hereunder;
" Difficulty in executing the work due to heavy traffic road, shortage of Bitumen and delay in supply of shredded plastics work could not be completed."
4. Column No. 11 of Ext.P2 is the remarks of the
Departmental Officers which is extracted hereunder;
" Difficulty in executing the work due to heavy traffic road, shortage of Bitumen and delay in supply of shredded plastics work could not be completed."
5. In Ext.P2 the Assistant Engineer, Assistant
Executive Engineer and Executive Engineer signed. The
Assistant Executive Engineer clearly stated that, the reason
stated is genuine. It is true that, there is no remarks by the WP(C) NO. 8496 OF 2021
Assistant Engineer and Executive Engineer while putting their
signature. Thereafter Ext.P3 order is passed in which it is
stated that, the Executive Engineer has also recommended
that the time of completion may be extended up to
30.05.2019 with fine since the facts explained by the
contractor are not genuine.
6. Similarly Ext.P4 is the application submitted by the
petitioner for extension of time in another work. The date of
commencement of that work was on 10.12.2018. The date up
to which the extension was sought was 30.09.2019. Column
No. 7 of Ext.P4 is the reason for not completing the work
mentioned by the petitioner contractor which is extracted
hereunder;
" Due to heavy rain balance works like road marking, surface drain etc. were delayed which could be completed only after monsoon."
7. Column No. 11 of Ext.P4 is the remarks of the
departmental officers which is also extracted hereunder; WP(C) NO. 8496 OF 2021
" Due to heavy rain balance works like road marking, surface drain etc. were delayed which could be completed only after monsoon."
8. In Ext.P4 the Assistant Engineer, Assistant
Executive Engineer and Executive Engineer signed. It is true
that, the Assistant Executive Engineer stated that, the
extension can be given without fine. But, the Executive
Engineer stated that "recommended for extension up to
30.09.2019 with fine". Thereafter, Ext.P5 is the order passed
in Ext.P4, which says that, Executive Engineer has also
recommended that the time of completion may be extended
up to 30.09.2019 with fine since the facts explained by the
contractor are not genuine.
9. when the remarks made by the Departmental
Officers in column No. 11 in Exts.P2 and P4 are compared
with the reasoning in Exts. P3 and P5 orders, it is clear that,
there is contradiction. According to me, this is a matter to be
re considered by the authority concerned. I don't want to WP(C) NO. 8496 OF 2021
make any further opinion. In Exts.P2 and P4 application the
contractor specifically mentioned a reason which is endorsed
by the Departmental Officers in column No. 12 of Exts.P2 and
P4. Hence, in such situation, I think, it is injustice on the part
of the respondents to issued Exts.P3 and P5 orders imposing
fine. I think, the matter is to be reconsidered again.
Therefore this writ petition is allowed in the following
manner.
1. The fine imposed in Ext.P3 and P5 orders are set as
side.
2. The 2nd respondent is directed to reconsider the
matter, after giving an opportunity of hearing to the
petitioner.
3. The above exercise should be completed by the 2 nd
respondent as expeditiously as possible, at any rate, within WP(C) NO. 8496 OF 2021
one month from the date of receipt of a copy of this
judgment.
(Sd/-)
P.V.KUNHIKRISHNAN JUDGE LU WP(C) NO. 8496 OF 2021
APPENDIX OF WP(C) 8496/2021
PETITIONER EXHIBITS
EXHIBIT P1 TRUE COPY OF THE AGREEMENT NO.17/SECCA/2019-2020 DATED 31.05.2019 BETWEEN THE PETITIONER AND THE 2ND RESPONDENT.
EXHIBIT P2 TRUE COPY OF APPLICATION SUBMITTED BY THE PETITIONER TO THE 2ND RESPONDENT DATED 09.01.2019.
EXHIBIT P3 TRUE COPY OF THE ORDER NO.DEE-10593/2017 DATED 09.09.2020 ISSUED BY THE 2ND RESPONDENT.
EXHIBIT P4 TRUE COPY OF THE APPLICATION DATED 28.05.2019 SUBMITTED BY THE PETITIONER TO THE 2ND RESPONDENT.
EXHIBIT P5 TRUE COPY OF THE ORDER NO.DEE-10593/2017 DATED 16.09.2020 ISSUED BY THE 2ND RESPONDENT.
EXHIBIT P6 TRUE COPY OF THE COMMUNICATION DATED 04.10.2020 SENT BY THE PETITIONER TO THE 2ND RESPONDENT.
EXHIBIT P7 TRUE COPY OF THE ORDER NO.DEE-10593/2017 DATED 28.09.2020 ISSUED BY THE 2ND RESPONDENT.
RESPONDENTS EXHIBITS
ANNEXURE R2 (A) TRUE COPY OF THE PROCEEDINGS NO. DEE 10593/2017 DATED 09.09.2020 WP(C) NO. 8496 OF 2021
ANNEXURE R2 (B) TRUE COPY OF THE PROCEEDINGS NO. DEE 10593/2017 DATED 16.09.2020.
// True Copy // PA to Judge
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!