Citation : 2021 Latest Caselaw 19535 Ker
Judgement Date : 17 September, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR. JUSTICE DEVAN RAMACHANDRAN
FRIDAY, THE 17TH DAY OF SEPTEMBER 2021 / 26TH BHADRA, 1943
WP(C) NO. 29004 OF 2020
PETITIONER:
RDS PROJECT LIMITED,
REGISTERED OFFICE AT SHIHAB THANGAL ROAD,
PANAMPILLY NAGAR, KOCHI-682036,
REP. BY ITS VICE PRESIDENT (PROJECTS)
COL. M.R.RAVEENDRAN NAIR (RTD.)
BY ADVS.
K.T.THOMAS
SHRI.MATHEW B KURIAN
RESPONDENTS:
1 THE DISTRICT POLICE CHIEF
THIRUVANANTHAPURAM RURAL,
PMG JUNCTION, THIRUVANANTHAPURAM-8.
2 THE STATION HOUSE OFFICER,
MANGALAPURAM POLICE STATION,
POTHENCODE MURUKKUMPUZHA ROAD,
NH 66, MANGALAPURAM, KERALA-695501.
3 SRI.JAYAN,
CONVENOR, INTUC, 16 MILE,
THONNAKKAL P.O., THIRUVANANTHAPURAM-695584.
4 SRI.RAVINDRAN,
CONVENOR, CITU, 16 MILE, THONNAKKAL P.O.,
THIRUVANANTHAPURAM-695584.
5 THE CHAIRMAN,
KERALA HEADLOAD WORKERS WELFARE FUND BOARD,
SUB LABOUR OFFICE, BPS ROAD,
ATTINGAL, THIRUVANANTHAPURAM-85.
6 HLL INFRA TECH SERVICES LTD.,
HLL BHAVAN, GOLDEN JUBILEE BLOCK,
POOJAPPURA P.O.,
THIRUVANANTHAPURAM-695012,
REP. BY ITS AUTHORISED OFFICER.
BY ADVS.
GOVERNMENT PLEADER
SRI.SAMPATH V. TOMS-R3,4
SHRI.THOMAS ABRAHAM-R5
SRI.K.JAJU BABU (SR.)
SMT.M.U.VIJAYALAKSHMI
KUM.T.S.ATHIRA-R6
W.P(C)No.29004 of 2020
2
OTHER PRESENT:
Sri E C Bineesh, GP
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
17.09.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
W.P(C)No.29004 of 2020
3
JUDGMENT
Dated this the 17th day of September, 2021
The petitioner is stated to be a Company registered
under the provisions of the Companies Act, 1956 and they
say that they are in the midst of a construction and its allied
activities like electrification, installation of fire fighting
systems, plumbing, site leveling etc., as per Ext.P1 Letter of
Acceptance of the 6th respondent and the subsequent
agreement between the parties for such purpose.
2. The petitioner says that even though the members
of 3rd and 4th respondents - Unions are being engaged, as and
when it becomes necessary, for the purpose of loading and
unloading of the construction articles, they are now causing
continuous obstruction, claiming that the petitioner or the 6 th
respondent cannot do any such activity using mechanized
means. They assert that this demand of the Unions and their
members is untenable because most of the articles used for W.P(C)No.29004 of 2020
the construction and its allied activities are heavy and
delicate, which will require to be handled only through
machines and skilled workers. Petitioner contends that, in
spite of this, when the members of the respondents - Unions
continued with their obstructionist and violent actions, they
were forced to approach the 2nd respondent - Station House
Officer through Ext.P3 seeking protection. They allege that,
however, no action was taken by the said Authority, thus
constraining them to have approached this Court through
writ petition.
3. I have heard Sri.K.T.Thomas - learned counsel for
the petitioner; Sri.Sampath.V.Toms - learned counsel
appearing for respondent Nos.3 and 4; Sri.Thomas
Abraham - learned Standing Counsel appearing for
respondent No.5; Smt.Athira.T.S - learned counsel appearing
for respondent No.6 and Sri.E.C.Bineesh - learned
Government Pleader appearing for respondent Nos.1 and 2.
4. Sri.Sampath.V.Toms, the learned counsel for
respondents 3 and 4, argued that continued prosecution of W.P(C)No.29004 of 2020
this writ petition by the petitioner is an abuse of process,
because, pending this lis, a settlement had been entered into
by them, as also the 6th respondent, with his clients, leading
to Ext.R4(r), where under, various items of work to be
handled by his clients were enumerated and fixed. He
submitted that, therefore, as of now, there can be no
controversy and that petitioner cannot seek any further
orders from this Court.
5. Sri.Thomas Abraham; learned Standing Counsel
for respondent No.5, Board, confirmed that the area in
question is covered by a Scheme under the Kerala Head
Load Workers Act, 1978 and submitted that, therefore, only
the members of respondents 3 and 4 Unions can be
permitted to undertake loading and unloading activities. He
added that, in fact, petitioner is engaging them even now,
but that the controversy appears to be that they are using
mechanized means for loading and unloading certain
consignments and articles.
6. The learned Government Pleader, Sri.E.C.Bineesh, W.P(C)No.29004 of 2020
submitted that, in obedience to the interim order of this
Court dated 22/12/2020, Police is keeping a vigil in the area
in question and that members of respondents 3 and 4 have
not been allowed to take law into their own hands or to
commit any action, which will have the effect of breach of
law and order. He submitted that Police will continue to
keep such a vigil and to ensure that there is no breach of
peace in the area in future.
7. When I evaluate the afore submissions, it is
rendered indubitable that the real controversy between the
petitioner on one hand and the members of respondents 3
and 4 Unions or the other, is with respect to the loading and
unloading of certain large and delicate consignments and
articles. While the petitioner asserts that these
consignments and articles can only be handled through
mechanized means; the members of respondents 3 and 4
Unions assert otherwise and say that they are capable of
handling it and that petitioner is obliged to allow them to do
so, on account of Ext.R4(r) Settlement. W.P(C)No.29004 of 2020
8. When I evaluate the rival submissions, it is
apodictic, it having been settled through a series of
judgments, that head load workers can only insist on work
which is within their competence and which can be handled
through human effort. In fact, the definition of the word
'head load worker' is so in the Head Load Workers Act itself.
Therefore, when consignments, incapable of being handled
manually or which are delicate, are to be loaded or unloaded
in the premises of the construction, I cannot find any reason
for the members of respondents 3 and 4 to cause any
obstruction. If they have a case that a particular
consignment or article can be handled by their members and
that petitioner is using mechanised methods only to deny
them legitimate employment, their remedy is to approach the
Competent Authority under Section 21 of the Kerala Head
Load Workers Act, but cannot take law into their own hands
or cause obstruction.
That said, I notice that it is virtually conceded that
the construction activities in the premises are now going on W.P(C)No.29004 of 2020
smoothly on account of the interim order of this Court and
that the only surviving apprehension for the respondents
Unions against it being continued is that, in the event they
want to raise a dispute with respect to a particular
consignment or article in future, they will be incapacitated
from doing so.
In the afore circumstances, I allow this writ
petition, confirming the interim order of this Court dated
22/12/2020; thus directing the 2nd respondent to ensure that
respondents 3 and 4 or their men are not allowed to take
law into their own hands in any event, and that law and
order is constantly maintained in the area without any
breach.
Needless to say, if 3rd and 4th respondents or their
men have any cause with respect to a particular consignment
or article, which the petitioner or the 6 th respondent
attempts to load or unload using mechanized means; or if
they are aggrieved with respect to the incorporation of
Exhibit R4(r), they will be at liberty to invoke their remedies W.P(C)No.29004 of 2020
under Section 21 of the Kerala Head Load Workers Act, and
my observations in this judgment will not fetter or trammel
them in any manner whatsoever.
To reiterate, the sum total of my observations
above is that, even if a dispute is to be raised by respondents
3 and 4 and their men with respect to any component of the
work; or as regards Exhibit R4(r), they shall not be allowed
to indulge in violence or to commit any acts contrary to law
and that they will have to invoke their legal remedies as per
the statutory scheme.
Sd/-
DEVAN RAMACHANDRAN JUDGE
NR/17/09/2021 W.P(C)No.29004 of 2020
APPENDIX PETITIONER'S EXHIBITS EXHIBIT P1 TRUE COPY OF LETTER OF ACCEPTANCE DATED 21.9.2020 ISSUED BY 6TH RESPONDENT.
EXHIBIT P2 TRUE COPY OF COMPLAINT DATED 27.11.2020 SUBMITTED BY PETITIONER.
EXHIBIT P3 TRUE COPY OF COMPLAINT DATED 12.12.2020 SUBMITTED BY PETITIONER.
RESPONDENTS' EXHIBITS Exhibit R4(A) TRUE COPY OF THE WORK ORDER DTD. 21.11.2020. Exhibit R4(B) TRUE COPY OF THE WORK ORDER DTD. 23.12.2020. Exhibit R4(C) TRUE COPY OF THE WORK ORDER DTD. 31.12.2020. Exhibit R4(D) TRUE COPY OF THE WORK ORDER DTD. 01.01.2021 Exhibit R4(E) TRUE COPY OF THE WORK ORDER DTD. 3.01.2021. Exhibit R4(F) TRUE COPY OF THE WORK ORDER DTD. 15.01.2021. Exhibit R4(G) TRUE COPY OF THE WORK ORDER DTD. 17.01.2021. Exhibit R4(H) TRUE COPY OF THE WORK ORDER DTD. 25.01.2021. Exhibit R4(I) TRUE COPY OF THE WORK ORDER DTD. 31.01.2021. Exhibit R4(J) TRUE COPY OF THE WORK ORDER DTD. 03.02.2021. Exhibit R4(K) TRUE COPY OF THE WORK ORDER DTD.09.02.2021 Exhibit R4(I) TRUE COPY OF THE WORK ORDER DTD. 12.02.2021 Exhibit R4(M) TRUE COPY OF THE WORK ORDER DTD. 21.12.2021. Exhibit R4(N) TRUE COPY OF THE WORK ORDER DTD. 22.02.2021. Exhibit R4(O) TRUE COPY OF THE MINUTES OF THE MEETING CONVENED AT THE OFFICE OF THE 5TH RESPONDENT DTD 24.12.2020.
Exhibit R4(P) TRUE COPY OF THE LETTER SENT BY THE SUPERINTENDENT KERALA STATE HEAD LOAD WORKERS WELFARE BOARD, ATTINGAL, OFFICE TO THE CHAIRMAN, KERALA HEADLOAD, WORKERS WELFARE BOARD 01.01.2021
Exhibit R4(Q) TRUE COPY OF THE MINUTES OF THE MEETING HELD AT THE DISTRICT LABOUR OFFICE.23.01.2021 Exhibit R4 (R) TRUE COPY OF THE COMMUNICATION ISSUED BY THE PETITIONER TO THE RESPONDENTS 3 AND 4, SHOWING THE REVISED LABOUR UNION RATES FOR UNLOADING WORK
// TRUE COPY// PA TO JUDGE
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!