Citation : 2021 Latest Caselaw 21257 Ker
Judgement Date : 29 October, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE S.V.BHATTI
&
THE HONOURABLE MR.JUSTICE BASANT BALAJI
FRIDAY, THE 29TH DAY OF OCTOBER 2021/7TH KARTHIKA, 1943
WRIT APPEAL NO.764 OF 2017
(AGAINST THE JUDGMENT DATED 6.2.2017 IN W.P.(C)No.13614/2016
OF HIGH COURT OF KERALA, ERNAKULAM)
APPELLANT:
SAJAN VARGHESE, MANAGING DIRECTOR,
MANGALAM PUBLICATION (INDIA) PRIVATE LTD.,
S.H.MOUNT P.O., KOTTAYAM, PIN-686 006.
BY ADVS.
SRI.A.A.ZIYAD RAHMAN
SRI.JOSEPH KURIAN VALLAMATTAM
SRI.LAL K.JOSEPH
SRI.V.S.SHIRAZ BAVA
SRI.M.B.SOORI
SRI.M.SASIDHARAN
RESPONDENTS:
1 THE ASSISTANT EXECUTIVE ENGINEER,
ELECTRICAL SUB DIVISION, KOTTAYAM CENTRAL,
KERALA STATE ELECTRICITY BOARD LIMITED-695 601
2 THE STATE ELECTRICITY OMBUDSMAN,
CHARANGATTU BHAVAN NO.34/895,
MAMANGALAM-ANJUMANA ROAD, EDAPPALLY, KOCHI-682 024.
3 THE CONSUMER GRIEVANCE REDRESSAL FORUM (SOUTH),
KERALA STATE ELECTRICTY BOARD LIMITED,
SOUTHERN REGION, VYDHYUDHI BHAVANAM, KOTTARAKKARA,
PIN-691 506, REPRESENTED BY ITS CHAIRMAN
BY ADVS.
SRI.RAJU JOSEPH (SR.)
SRI.N.SASIDHARAN UNNITHAN
SRI.GEORGEKUTTY MATHEW, SC, KSEB
THIS WRIT APPEAL HAVING COME UP FOR ADMISSION ON
29.10.2021, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
W. A. No.764 of 2017
2
JUDGMENT
Basant Balaji, J
This intra court appeal is filed challenging the
judgment dated 16.02.2017 in W.P.(C)No.13614 of 2016 by
the 3rd respondent. The 1st respondent herein approached
this court by filing the above mentioned writ petition
challenging Ext.P8 order of the 2 nd respondent herein,
whereby the Ombudsmen has quashed the penal bill for
Rs.33,11,236/- issued to the appellant herein. The
appeal petition before the 2 nd respondent was filed by
the appellant herein challenging the order of the 3 rd
respondent/Consumer Grievance Redressal Forum; which
confirmed that the delay occurred to install the (CT/PT)
Unit and the 'POD Meter' is not due to the fault of the
1st respondent herein and it was the responsibility of
the appellant herein to provide metering equipments in
the premises. Hence the 1 st respondent was given liberty
to invoke penal charges according to the gazette W. A. No.764 of 2017
notification dated 27.9.2014, issued by the Kerala State
Electricity Regulatory Commission.
2. The short question to be considered in this
appeal is, whether there is any scope for interfering
with the judgment of the learned single judge? Whereby
the learned single has found that the delay in
installing the (CT/PT) Unit in the premises of the
appellant was due to the latches of both the appellant
as well as the Officials of the Board. The learned
single judge interfered with the order of the Ombudsman
and the penalty of 50% imposed on the appellant was
reduced to 25%.
3. Heard learned counsel for the appellant, Sri
Lal K.Joseph and learned Senior counsel Sri.Raju Joseph
for the 1st respondent.
4. It is an undisputed fact that the appellant's
un-authorised use of electricity was detected by the
inspection of 'Anti Power Theft Squad' (APTS) on
12.11.2012. On the basis of inspection, the appellant W. A. No.764 of 2017
was required to enhance additional contract demand, for
which he applied in December 2013. The contention of the
appellant is that, before 18.04.2014, the time permitted
by the Deputy Chief Engineer, the appellant had produced
the test report of the (CT/PT) Unit from the
transformers with a covering letter on 20.03.2014
itself. The counsel for the appellant argued that, the
Board Officials failed to install the (CT/PT) Unit, and
it is because of the said delay on the part of the
Officials in the Board that he had to pay the penal
charges.
5. The learned single judge came to the specific
conclusion that it is an admitted position that the
appellant did not produce (CT/PT) Meter, which was
calibrated and tested before the Assistant Engineer,
eventhough test reports were produced before him. The
learned single judge also found that on receipt of
Ext.R3(c), the first respondent has not sought for the
(CT/PT) Meter from the appellant herein and so the meter W. A. No.764 of 2017
was not affixed to the connection of the appellant and
he alleged that the electricity energy was used by the
appellant without any meter. The Electricity Board
eventhough had power to disconnect the connection, for
reasons unknown chose not to do so. Thus the learned
single judge came to the conclusion that both the
appellant as well as the Board Officials are at fault
for the delay in installing the (CT/PT) Unit in the
premises of the appellant.
6. Another contention raised before the learned
single judge was that, on the basis of Clause(4) of
Part-B of the Tariff Order, there could be no penal
charges levied, if there was no defect in the meter. It
was found that, the levy can be made even in case of
replacement where the consumer trying to purchase and
supply the meter. The time required for purchase and
supply of the meter as per Clause(4) of the Tariff Order
of High Tension and Extra High Tension is two months and
if the consumer does not replace the same within two W. A. No.764 of 2017
months, the consumer will be charged 50% extra rates,
applicable to him both demand and energy from the date
of expiry of two months fixed for purchase and supply of
the meter, till the date on which the meter is purchased
and supplied by the consumer to the licence. Adverting
to this, the learned single judge found that, levy of
penal charges would be permissible in the present case,
where the 3rd respondent had failed to supply the (CT/PT)
Meter in time. The learned single judge having found
that the delay occurred in replacement of the (CT/PT)
Meter was on the appellant as well as the Board
Officials reduce the penalty to 25% extra over the
prevailing rates.
We have anxiously considered the submissions made
by the counsel on both sides and perused the judgment of
the learned single judge as well as the documents
produced by both sides, and on going through the same,
we are of the opinion that, the learned single judge was
right in entering into a finding that the delay occurred W. A. No.764 of 2017
is due to the latches on the part of the appellant as
well as the lethargy on the part of the Board Officials.
Hence we are of the opinion that, no interference is
warranted on the judgment of the learned single judge
and therefore the Writ Appeal is dismissed.
Sd/-
S.V.BHATTI, JUDGE
Sd/-
BASANT BALAJI, JUDGE ss
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!