Sunday, 03, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Shyam S.Menon vs Aravindakumar
2021 Latest Caselaw 21061 Ker

Citation : 2021 Latest Caselaw 21061 Ker
Judgement Date : 20 October, 2021

Kerala High Court
Shyam S.Menon vs Aravindakumar on 20 October, 2021
  OP(C).1951/2020                 1

            IN THE HIGH COURT OF KERALA AT ERNAKULAM
                             PRESENT
                THE HONOURABLE MR.JUSTICE V.G.ARUN
 WEDNESDAY, THE 20TH DAY OF OCTOBER 2021 / 28TH ASWINA, 1943
                      OP(C) NO. 1951 OF 2020
    AGAINST THE ORDER/JUDGMENT IN E.P.NO.191 OF 2015 IN OS
         567/2007 OF II ADDITIONAL SUB COURT,ERNAKULAM
PETITIONER/S:

    1      SHYAM S.MENON,
           AGED 54 YEARS
           S/O.LATE KRISHNA MENON, DARPAN, R.MADHAVAN NAIR
           ROAD, PALLIMUKKU, ERNAKULAM- 682 016 REPRESENTED
           THROUGH THE POWER OF ATTORNEY HOLDER, MRS.SUBHA
           GOKUL MENIN, AGED 52 YEARS, D/O.LATE KRISHNA MENON,
           DARPAN, R.MADHAVAN NAIR ROAD, PALLIMUKKU, ERNAKULAM
           -682 016.

    2      SUBHA GOKUL MENON
           AGED 52 YEARS
           D/O.LATE KRISHNA MENON, DARPAN, R.MADHAVAN NAIR
           ROAD, PALLIMUKKU, ERNAKULAM - 682016.

    3      SIVA GOPALAKRISHNAN
           AGED 49 YEARS
           S/O.LATE KRISHNA MENON, DARPAN, R.MADHAVAN NAIR
           ROAD, PALLIMUKKU, ERNAKULAM - 682 016 REPRESENTED
           THROUGH THE POWER OF ATTORNEY HOLDER, MRS.SUBHA
           GOKUL MENON, AGED 52 YEARS, D/O.LATE KRISHNA MENON,
           DARPAN, R.MADHAVAN NAIR ROAD, PALLIMUKKU, ERNAKULAM
           - 682016.

           BY ADVS.
           P.G.SURESH
           SMT.ASWATHY KRISHNAN



RESPONDENT/S:

    1      ARAVINDAKUMAR
           AGED 70 YEARS
           S/O.GOVINDALU, RESIDING AT DOOR NO.39/4844,
   OP(C).1951/2020                      2

            M.G.ROAD, RAVIPURAM, KOCHI - 682 016.

    2       P.B.GOPALAKRISHNAN
            AGED 62 YEARS
            S/O.RAGHAVAN PILLAI, PUKALAKATTU ETTUKETTIL HOUSE,
            P.O.PALAROVATTOM, ERNAKULAM, PIN - 682 025.

    3       BHIMA JEWELS
            JOSE JUNCTION, M.G.ROAD, ERNAKULAM REPRESENTED
            THROUGH ITS MANAGING DIRECTOR, PIN - 682 011.

            BY ADVS.
            V.N.HARIDAS
            SIBY.P.JOSE
            SAIFUDEEN T.S
            K.T.BOSCO
            SMITHA GOPINATH
            P.B.KRISHNAN




     THIS    OP     (CIVIL)   HAVING   COME   UP   FOR   ADMISSION   ON
16.9.2021, THE COURT ON 20.10.2021 DELIVERED THE FOLLOWING:
   OP(C).1951/2020                        3




                              V.G.ARUN, J.
               -----------------------------------------------
                      O.P(C).No.1951 of 2020
               -----------------------------------------------
             Dated this the 20th day of October, 2021

                               JUDGMENT

The petitioners are judgment debtors 2 and 3 in E.P.No.191 of

2015 on the files of the Subordinate Judge's Court-II, Ernakulam. The

1st respondent has filed the petition seeking to execute Exhibit P1

award of the Lok Adalat. Exhibit P1 award was passed on the basis

of a compromise petition filed by the petitioners and the

respondents, settling all disputes with respect to the construction of

a building complex. Clause 2 of the compromise petition stipulates

that the respondents are entitled for 68% equal share in the super

built up area in the basement and ground floor of the building and

58% equal share in the super built up area in the third and fourth

floors, along with proportionate area of land. The 1 st respondent is

claiming allotment of his share in terms of the compromise and the

award.

2. The petitioners resisted the execution petition, contending

that as per the terms of the compromise the respondents were

bound to complete the construction of the building before 19.9.2009

or at least within the grace period of six months. Having failed to do

so, the 1st respondent is not entitled to get the decree executed.

The execution court repelled the objection by Exhibit P8 order and

held the execution petition to be maintainable. Finding that the

petitioner had rented out the third floor of the building to the 3 rd

respondent from 2016 onwards, the execution court passed Exhibit

P9 order directing the petitioners to deposit 58% of the rent

received from the 3rd respondent, from the date of filing of the

petition, within one month. The prayer in this original petition is to

set aside Exhibits P8 and P9 orders.

3. Sri.P.G.Suresh, learned counsel for the petitioners assailed

the impugned orders by contending that, having failed to complete

the construction in terms of the compromise, the decree holder is

not entitled to seek execution of the award. In support of the

contention regarding non-compliance, learned counsel referred to

Clauses 6, 7, 9, 10, 12 and 16 of the joint statement of compromise

extracted hereunder;

"6. The plaintiff and 4th defendant shall construct the third and fourth floor of the said multistoried building, at their cost, expense and responsibility, in accordance with the approved building permit bearing MOP.1/294/01, obtained by the defendants 1 to 3. The plaintiff and 4 th defendant shall complete the said construction within a period of Twelve (12) months from today.

7. The plaintiff and 4th defendant shall construct, setup and provide all common facilities and other mandatory requirements in the said multistoried building in accordance with the approved building permit and plan, within the aforesaid period, at their cost. The common facilities shall include Staircase cabin, covering up the terrace and leak proofing terrace, installing two lifts, indoor transformers and generator, complying with all necessary statutory and fire requirements, completely leak proofing the basement floor and making it usable, putting up water tanks as per the statutory requirements and everything necessary to be complied with under Kerala Building Rules, and other provisions of Law.

xx xx xx

9. If the plaintiff and 4 th defendant fails to complete the construction of 3rd and 4th floor within the time as aforesaid, except due to vis majeure/acts of God, the time fixed for completion of the construction may be extended for a further period of Six (6) months, and, in that event, the plaintiff and 4th defendant shall pay a sum of Rs.50,000/- per month to the defendants 1 to 3 during the aforesaid grace period towards mutually agreed compensation. If the plaintiff and 4th defendant fails to complete the construction even within the grace period of above said six months, their right to construction as per this compromise shall automatically stand terminated, and plaintiff and 4th defendant shall not have any manner of right to construct the 3 rd and 4th floor or to proceed with the construction already started and the plaintiff and 4th defendant will not have any right in respect of the 3rd and 4th floors and in such an event, defendants 1 to 34 shall have right and liberty to proceed with the construction

of the 3rd and 4th floor and defewndants 1 to 3 alone will have the right to alienate, encumber or appropriate the same and defendants 1 to 3 alone shall have the absolute right to the considerations arising from the above, and plaintiff and 4 th defendant shall not cause any manner of hindrance or obstruction for the same.

10. Construction of the building as aforesaid shall be at the responsibility of the plaintiff and 4th respondent. The plaintiff and 4th defendant shall construct the 3rd and 4th floors of the building by using good quality of materials and quality of the construction shall be the sole responsibility of the plaintiff and 4th defendant. The plaintiff and 4th defendant alone will be liable for any flaws or shortfalls in the construction or quality of construction without making the defendants 1 to 3 in any way liable for the same, and in such an event plaintiff and 4th defendant shall indemnify the defendants 1 to 3 from all such liabilities.

xx xx xx

12. The plaintiff and 4th defendant shall be responsible to comply with all necessary statutory requirements and they shall be responsible to obtain the completion certificate, occupation certificate and get the building assessed and numbered from the local authority within the stipulated period as aforesaid or at any rate within the grace period as aforesaid and the time in the essence of the terms agreed to herein.

xx xx xx

16. Subject to clause 6 & 9 above, on completion of the construction and performing the obligations as aforesaid, the defendants 1 to 3 shall be entitled to 42% share and plaintiff and 4th defendant together shall be entitled to 58% share in

the super built up area in the 3rd and 4th floors along with proportionate area in land."

4. It is contended that Exhibits P3 to P5 are sufficient proof of

the fact that the elevators were not installed even in the year 2015.

Relying on Exhibit P6 interim order in W.P(C).No.11522 of 2015, it is

submitted that the petitioners had to complete the construction and

approach this Court for getting the building provisionally numbered.

Exhibit P7 Commission report and photographs are pressed into

service to contend that some of the works are yet to be completed.

The gist of the argument is that, allotment of shares being subject

to the condition of the respondents completing the construction

within one year of the compromise petition dated 19.9.2008 or at

least within a further period of six months and the respondents

having failed to complete the construction within the said period,

the court below committed an illegality in passing Exhibit P8 order.

The challenge against Exhibit P9 is on the premise that the 3 rd

respondent is not a party to the compromise and the direction to

deposit proportionate share of the rent collected from the 3 rd

respondent is beyond the scope of the decree and the remedy of

the 1st respondent is to file a separate suit. In support of this

contention, reliance is placed on the decision of the Honourable

Supreme Court in Deepa Bhargava and Another v. Mahesh

Bhargava and Others [(2009) 2 SCC 294].

5. Sri.P.B.Krishnan, learned counsel for the 1 st respondent drew

attention to Exhibits A1 to A27 documents submitted before the

execution court by the 1st respondent to contend that the 1st

respondent had undertaken and completed the construction in

terms of the compromise. The petitioners, on the other hand, failed

to produce any document in support of othe contention that they

had completed the construction. Reference is made to the

averments in W.P(c().No.11522 of 2015, where the specific case is

that construction of the building was completed by the petitioners

during September, 2009. Learned counsel contended that the

petitioners having admitted that the construction was completed

within time and the 1st respondent having succeeded in convincing

the execution court that the construction was carried out by him,

no interference is warranted in exercise of the supervisory power

under Article 227 of the Constitution of India.

6. It is not in dispute that as per Clause 6 of the compromise,

respondents 1 and 2 were bound to complete the construction

within a period of 12 months from 19.9.2008. As per clause 7, they

were also bound to set up and provide common facilities including

two elevators within the said period. Clause 9 provides for extension

of the time limit by a further period of six months, subject to the

respondents paying a sum of Rs.50,000/- per month to the

petitioners during the aforesaid grace period. The Clause further

stipulates that if respondents 1 and 2 fail to complete the

construction even within the grace period of six months, their right

to construction as per the compromise will stand automatically

terminated. As rightly found by the execution court, the petitioners

have no case that on failure of respondents 1 and 2 to complete the

construction within one year, the petitioners had raised any demand

for the amount of Rs.50,000/-per month, as stipulated in Clause 9.

Moreover, other than contending that they had completed the

construction, absolutely no evidence in that regard is produced by

the petitioners before the execution court or even before this Court.

On the other hand, the 1st respondent produced Exhibits A1 to A27

documents in support of his contention that the construction was

carried out and completed by him within the 12 month period.

Exhibits P3 to P5, on which much reliance is placed by the

petitioners indicates that the elevators were fixed earlier, but were

not functional for reason of certain missing parts. Apart from all

these, the specific averment of the petitioners in W.P(C).No.11522

of 2015 is that the construction of the building, in conformity with

the building plan and permit issued by the 2nd respondent, was

completed during September, 2009. It is also averred that due to

some internal disputes, the petitioners could not submit completion

certificate for issuance of occupancy certificates and allotment of

building number and that, after resolving the disputes, the

petitioners had submitted the completion certificate on 19.1.2015.

The above being the evidence on record, the execution court was

fully justified in coming to the conclusion that the construction was

completed before September, 2009, i.e., within the stipulated

period. Even if it is taken that some minor works remained

incomplete, that is no reason to hold the execution petition to be

not maintainable and to deny the legitimate share due to the 1st

respondent.

7. The petitioners are not disputing the fact that they have

inducted the 3rd respondent as a tenant in the third floor of the

building. As such, 1st respondent is also entitled for a share in the

rent received from the 3rd respondent. The hyper technical

argument that the direction in Exhibit P9 is beyond the scope of the

execution petition and the 1st respondent ought to file a separate

suit for recovery of the rent arrears cannot be countenanced. It

needs no reiteration that the Rules of procedure are intended to be

a handmaid to the administration of justice and they must,

therefore, be construed liberally and in such a manner as to render

the enforcement of the substantive right, effective.

For the aforementioned reasons, the challenge against Exhibits

P8 and P9 orders fail. Consequently, the original petition is

dismissed.

Sd/-

V.G.ARUN, JUDGE

vgs

APPENDIX OF OP(C) 1951/2020 PETITIONER EXHIBITS

EXHIBIT P1 THE TRUE COPY OF THE AWARD PASSED BY THE LOK ADALATH DATED 19/09/2008.

EXHIBIT P2 THE TRUE COPY OF THE EXECUTION PETITION FILED BY THE 1ST RESPONDENT/DECREE HOLDER BEFORE THE HONOURABLE SUB COURT AT ERNAKULAM AS E.P.NO.191/2015 DATED 10/09/2015.

EXHIBIT P3 THE TRUE COPY OF THE LICENSE FOR THE INSTALLATION OF THE LIFTS ISSUED BY THE DEPUTY CHIEF ELECTRICAL INSPECTOR, ERNAKULAM DATED 21/10/2015.

EXHIBIT P4 THE TRUE COPY OF THE APPROVAL FOR THE INSTALLATION OF 2 LIFTS ISSUED BY THE DEPUTY CHIEF ELECTRICAL INSPECTOR DATED 05/06/2010.

EXHIBIT P5 THE TRUE COPY OF THE ESTIMATE FOR THE INSTALLATION OF THE LIFT IN THE PLAINT SCHEDULE BUILDING ISSUED BY THE OMEGA ELEVATORS DATED 06/11/2015.

EXHIBIT P6 THE TRUE COPY OF THE INTERIM ORDER PASSED BY THE HONOURABLE HIGH COURT IN THE WRIT PETITION NO.11522/2015 DATED 08/04/2015.

EXHIBIT P7 THE TRUE COPY OF THE COMMISSION REPORT FILED BY THE ADVOCATE COMMISSIONER AND THE EXPERT ENGINEER DATED 12/06/2019.

EXHIBIT P8          THE TRUE COPY OF THE ORDER DATED
                    29/09/2020 PASSED BY THE HONOURABLE SUB
                    COURT, ERNAKULAM IN E.P.NO.191/2015 IN
                    O.S.NO.567/2007.

EXHIBIT P9          THE TRUE COPY OF THE ORDER PASSED BY THE
                    HONOURABLE SUB COURT ERNAKULAM IN
                    E.A.NO.337/2018 IN E.P.NO.191/2015 IN
                    O.S.NO.567/2007 DATED 04/11/2020.
 

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter