Citation : 2021 Latest Caselaw 20821 Ker
Judgement Date : 6 October, 2021
IN THE HIGH COURT OF KERALA AT ERNAKULAM
PRESENT
THE HONOURABLE MR.JUSTICE N.NAGARESH
WEDNESDAY, THE 6TH DAY OF OCTOBER 2021 / 14TH ASWINA, 1943
WP(C) NO. 7489 OF 2019
PETITIONER:
BRINDA SURESH,
AGED 58 YEARS,
W/O.LATE SURESH K.BABU, T.C.4/1248,
THAYIL MANA, KBR-10, KOWDIAR P.O.,
THIRUVANANTHAPURAM - 695 003,
REPRESENTED BY POWER OF ATTORNEY HOLDER
R.JOTHIRAJ, AGED 40 YEARS,
COMPANY EXECUTIVE,
S/O.A.RAMARAJAN, RESIDING AT T.C.39/1313,
CHALAI, CHALAI P.O., THIRUVANANTHAPURAM - 695 036.
BY ADVS.
SRI.R.S.KALKURA
SRI.M.S.KALESH
SRI.HARISH GOPINATH
SMT.R.BINDU
SMT.P.ANJANA
SRI.JOHNSON JOSE PANJIKKARAN
SRI.P.I.NAJUMAL HUSSAIN
SMT.NEENU PAVITHRAN
SRI.R.HARIKRISHNAN (KAMBISSERIL)
SRI.NIKHEL K GOPINATH
RESPONDENTS:
1 THE THIRUVANANTHAPURAM CORPORATION,
REPRESENTED BY ITS SECRETARY,
CORPORATION BUILDING,
THIRUVANANTHAPURAM - 695 033.
2 THE SECRETARY,
THIRUVANANTHAPURAM CORPORATION,
CORPORATION BUILDING,
THIRUVANANTHAPURAM - 695 033.
BY ADVS.
SRI.N.NANDAKUMAR MENON (SR.)
SRI.P.K.MANOJKUMAR, SC, TVPM CORPORATION
THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
06.10.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
WP(C).No.7489/2019
2
JUDGMENT
Dated this the 6th day of October, 2021
The petitioner along with her late husband
possessed 44.160 Cents of land in Kowdiar Village within the
territorial limits of Thiruvananthapuram Corporation. The
petitioner has approached this Court seeking to quash Exts.P7
and P9 and to direct the 1st respondent-Thiruvananthapuram
Corporation to collect such amount from the petitioner as was
applicable as per Rules in respect of the omitted FAR at the
rate prescribed at the time for submission of plan for approval.
2. The petitioner propose to construct an Apartment
Complex having 20 floors plus 2 basement floors. Ext.P1
Building Permit was issued to the petitioner in the year 2007. WP(C).No.7489/2019
The petitioner wanted to revise the Building Plan and an
application was submitted on 05.11.2012 for revising the
building plan. By the proposed revision the petitioner wanted
to reduce the number of floors from 20 to 14. The petitioner
completed the construction and submitted a completion plan
on 10.06.2013.
3. The respondents refused to issue Occupancy
Certificate. Thereupon the petitioner approach the Tribunal for
Local Self Government Institutions filing Appeal No.414 of
2014. The Tribunal dismissed the appeal and directed the
petitioner to file an application for regularisation of the alleged
unauthorised construction. Aggrieved by Ext.P4 appeal, the
petitioner filed W.P.(C) No.31811 of 2015. This Court in Ext.P5
judgment found that there is no reason to think that the
petitioner has not acquired any deemed permit as claimed by
the petitioner and that there is no requirement of an application
for regularisation as directed by the Tribunal, in view of the
proviso to Rule 16 of the Rules. Accordingly, Ext.P4 order of WP(C).No.7489/2019
the Tribunal was quashed.
4. This Court taking into consideration the factual
circumstances of the case directed the 2 nd respondent to issue
a notice of demand if at all any fee is due with respect to any
additional area on the basis of the revised FAR calculation,
within 15 days from the date of receipt of a copy of a
judgment, failing which it was directed that if the petitioner is
not liable to pay any amount, the petitioner shall be issued
Occupancy Certificate and the Building shall be numbered in
accordance with law.
5. Pursuant to Ext.P5 judgment, the 1 st respondent
issued Ext.P6 demand to the petitioner requiring to pay an
amount of Rs.10,62,480/-. Ext.P6 was issued on 16.08.2017.
On 23.11.2018, the Secretary again issued Ext.P7 notice
wherein the amount claimed was reduced to Rs.9,38,259/-.
The petitioner is aggrieved by this demand.
6. The petitioner submits that the demand has been
made taking into consideration the revised FAR rates. WP(C).No.7489/2019
According to the petitioner, in the year 2007, when the Building
Permit was originally issued, the rate was only Rs.1000/- per
Square metre. In 2013, the rate was enhanced to Rs.3000/-
and again in the year 2017 it was enhanced to Rs.5000/- per
Square metre. The learned counsel for the petitioner
submitted that the petitioner is liable to pay fees only at the
rates as was available in the year 2007.
7. It was stated that this Court in Ext.P5 judgment has
held that there is no requirement of any regularisation of the
construction as this Court found that the petitioner had
acquired deemed licence for the construction. The petitioner
further urged that till date, apart from the above demand, the
petitioner has not been served with any notice of any illegal
construction whatsoever. In the circumstances, the
respondents are liable to recompute the amount due from the
petitioner and pass fresh orders. Furthermore, since there is
no violation of Building Plan or Permit conditions, the petitioner
is entitled to get Occupancy Certificate and also to get the WP(C).No.7489/2019
Building numbered by the respondents.
8. The 1st respondent entered appearance and
contested the writ petition. The 1 st respondent stated that the
petitioner has constructed a Multi Storied Building and the
petitioner has deposited an amount of Rs.9,38,259/- on
26.04.2019 during the pendency of this writ petition. The
petitioner has not produced the Final Fire NOC and NOC of
the Airport Authority. The petitioner was required to produce
those documents which have not been produced so far. When
petitioner has failed to produce Final Fire NOC and NOC of
the Airport Authority, the respondents are justified in not
issuing Occupancy Certificate.
9. The 1st respondent further submitted that a local
inspection was conducted by the Officers of the Engineering
Department on the basis of the plan submitted by the
petitioner and it was found that the construction of the building
has been made by petitioner in violation of the Kerala
Municipality Building Rules, 1999. The Engineering WP(C).No.7489/2019
Department noted 10 defects as stated in paragraph 9 of the
statement. The first respondent however submitted that once
the defects are cured by the petitioner, his application for
Occupancy Certificate and numbering the building can be
considered.
10. I have heard the learned counsel for the petitioner
and the learned Senior Counsel assisted by the Standing
Counsel for the 1st respondent.
11. From the pleadings and arguments, it is evident that
the petitioner had obtained a Building Permit for construction
of an Apartment Complex having 20 floors and 2 basement
floors in the year 2007. The petitioner submitted a revised
Building Plan in the year 2012 reducing the number of over
ground floors to 14. The building construction was completed
on 10.06.2013. When the respondents desisted from issuing
Occupancy Certificate, the petitioner approached the Tribunal
for Local Self Government Institutions. The Tribunal dismissed
the Appeal filed by the petitioner. When the petitioner WP(C).No.7489/2019
approached this Court challenging the order of the Tribunal,
this Court as per Ext.P5 judgment found that the petitioner
holds deemed licence for construction of the Building as per
the revised plan. This Court categorically found that in such
circumstances the question of regularisation of the
construction does not arise. The said judgment has not been
challenged and it has become final. Therefore, the
respondents cannot take any stand contrary to the findings of
this Court in Ext.P5 judgment.
12. While the facts being so, the only issue remaining is
on the rates applicable for levying FAR fee from the petitioner.
According to the petitioner, the rate of FAR applicable was
Rs.1000/- per Square meter which was subsequently
enhanced to Rs.3000/- in the year 2013 and to Rs.5000/- in
2017. According to the learned counsel for the petitioner, the
rates have to be taken as they existed as on the date of
submission of the application. From Exts.P6 and P7 it is not
discernible whether the Secretary has considered the legality WP(C).No.7489/2019
of levying a compounding fee from the petitioner as per the
revised rates. This is because as already held in Ext.P5
judgment that there is no question of regularisation of the
Building in so far as the construction made by the petitioner is
concerned. In such circumstances, this Court is of the
considered opinion that the Secretary to the 1 st respondent-
Corporation has to reconsider Ext.P6 communication.
13. It has to be kept in mind that this is a Building, the
construction of which was started in 2007 and it is an
Apartment Complex having residential Units. Therefore, this
Court is of the opinion that in view of Ext.P5 judgment the
respondents are to be directed to issue Occupancy Certificate
without further delay to the petitioner and also grant numbers
to the apartment units.
In such circumstances, the writ petition is disposed
of directing the 2nd respondent to compute the amount to be
levied from the petitioner toward FAR fee after giving an
opportunity of hearing to the petitioner. The 2 nd respondent WP(C).No.7489/2019
shall issue Occupancy Certificate to the petitioner within a
period of one month and number the Buildings also. However,
it is made clear that if there are any variations from the revised
Building Plan, the respondents will be at liberty to proceed
against the petitioner and take such action as is permissible
under law. To enable the 2 nd respondent to recompute the
amount due from the petitioner, Exts.P6 and P7
communications are set aside.
Sd/-
N. NAGARESH JUDGE SR WP(C).No.7489/2019
APPENDIX OF WP(C) 7489/2019
PETITIONER'S EXHIBITS:
EXHIBIT P1 TRUE COPY OF THE BUILDING PERMIT DATED
30/5/2007 ISSUED BY THE FIRST
RESPONDENT IN FAVOUR OF THE PETITIONER AND HER HUSBAND.
EXHIBIT P2 TRUE COPY OF THE COMPLETION CERTIFICATE DATED 08/06/2013.
EXHIBIT P3 TRUE COPY OF THE APPLICATION FOR ASSESSMENT OF BUILDING TAX SUBMITTED BY THE PETITIONER BEFORE THE FIRST RESPONDENT.
EXHIBIT P4 TRUE COPY OF THE ORDER IN APPEAL NO.414 OF 2014 DATED 5/2/2015 ON THE FILE OF THE TRIBUNAL FOR LOCAL SELF GOVERNMENT INSTITUTIONS, THIRUVANANTHAPURAM.
EXHIBIT P5 TRUE COPY OF THE JUDGMENT DATED 9/11/2018 IN W.P.(C) NO.31811/2015 ON THE FILE OF THE HON'BLE HIGH COURT OF KERALA.
EXHIBIT P6 TRUE COPY OF THE LETTER DATED 16/8/2017
ISSUED BY THE 1ST RESPONDENT TO THE
PRINCIPAL SECRETARY GOVERNMENT OF
KERALA.
EXHIBIT P7 TRUE COPY OF THE LETTER DATED
23/11/2018 ISSUED BY THE RESPONDENT TO THE PETITIONER.
EXHIBIT P8 TRUE COPY OF THE STATEMENT FILED BY THE 1ST RESPONDENT IN COC NO.44/2019.
EXHIBIT P9 TRUE COPY OF THE ADDITIONAL STATEMENT FILED BY THE 1ST RESPONDENT IN COC NO.44/2019.
EXHIBIT P10 TRUE COPY OF THE GOVERNMENT ORDER NO.167/2014/LSGD DATED 27/09/2014.
EXHIBIT P11 THE RELEVANT PORTIONS OF THE KERALA MUNICIPALITY BUILDING RULES, 1999 AS IT STOOD BEFORE 21/6/2010 IN RESPECT OF THE TABLE PERTAINING TO COVERAGE AND FLOOR AREA.
WP(C).No.7489/2019
EXHIBIT P12 THE RELEVANT PORTIONS OF THE KERALA MUNICIPALITY BUILDING RULES, 1999 AS IT STOOD AS ON 21/06/2010 IN RESPECT OF THE TABLE PERTAINING TO COVERAGE AND FLOOR AREA.
EXHIBIT P13 THE RELEVANT PORTIONS OF THE KERALA MUNICIPALITY BUILDING RULES, 1999 AS IT STOOD AS ON 31/10/2017 IN RESPECT OF THE TABLE PERTAINING TO COVERAGE AND FLOOR AREA.
EXHIBIT P14 TRUE COPY OF THE FILE NOTINGS MAINTAINED IN THE FILE OF THE FIRST RESPONDENT PERTAINING TO THE BUILDING OF THE PETITIONER OBTAINED UNDER THE RIGHT TO INFORMATION ACT.
Exhibit P15 TRUE COPY OF THE RECEIPT BEARING NO.
0293049 DATED 26/04/2019 ISSUED BY THE RESPONDENT TO THE PETITIONER INDICATING DEPOSIT OF AN AMOUNT OF RS.938259/-
COVERED BY EXHIBIT-P7
Publish Your Article
Campus Ambassador
Media Partner
Campus Buzz
LatestLaws.com presents: Lexidem Offline Internship Program, 2026
LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!