Thursday, 07, May, 2026
 
 
 
Expand O P Jindal Global University
 
  
  
 
 
 

Raji Mathew vs State Of Kerala
2021 Latest Caselaw 22523 Ker

Citation : 2021 Latest Caselaw 22523 Ker
Judgement Date : 11 November, 2021

Kerala High Court
Raji Mathew vs State Of Kerala on 11 November, 2021
                 IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                 PRESENT
                   THE HONOURABLE MR.JUSTICE N.NAGARESH
    THURSDAY, THE 11TH DAY OF NOVEMBER 2021 / 20TH KARTHIKA, 1943
                         WP(C) NO. 23576 OF 2021
PETITIONER:

              RAJI MATHEW
              AGED 56 YEARS
              S/O. MATHEW, PAMPLANIYIL HOUSE, BHARANANGANAM P.O,
              MEENACHIL TALUK, KOTTAYAM DISTRICT-686 578.
              BY ADVS.
              GEORGE MATHEW
              M.D.SASIKUMARAN
              SUNIL KUMAR A.G
              GEORGE K.V.
              PRAVEEN S.
              DIPU JAMES
              STEPHY K REGI
              MATHEW K.T.


RESPONDENTS:

    1         STATE OF KERALA
              REPRESENTED BY CHIEF SECRETARY, GOVERNMENT SECRETARIAT,
              THIRUVANANTHAPURAM-695 001.
    2         THE PUBLIC WORKS DEPARTMENT
              REPRESENTED BY ITS SECRETARY, GOVERNMENT SECRETARIAT,
              THIRUVANANTHAPURAM-695 001.
    3         THE FINANCE DEPARTMENT (INDUSTRIES & PUBLIC WORKS-B)
              REPRESENTED BY ITS SECRETARY, GOVERNMENT SECRETARIAT,
              THIRUVANANTHAPURAM-695 001.
    4         THE CHIEF ENGINEER
              OFFICE OF THE CHIEF ENGINEER, PUBLIC WORKS DEPARTMENT
              (ROADS & BRIDGES), THYCADU, THIRUVANANTHAPURAM-695 014.
    5         THE SUPERINTENDING ENGINEER
              PUBLIC WORKS DEPARTMENT, ROADS CENTRAL CIRCLE,
              ALUVA-683 101.
    6         THE EXECUTIVE ENGINEER
              OFFICE OF THE EXECUTIVE ENGINEER,
              PUBLIC WORKS DEPARTMENT, ROADS DIVISION, PAINAVU P.O.,
              IDUKKI DISTRICT-685 603.
 WP(C) NO. 22964 OF 2021 & con.cases      2


     7       THE SENIOR FINANCE OFFICER
             OFFICE OF THE CHIEF ENGINEER,
             PUBLIC WORKS DEPARTMENT P.W.D (ROADS & BRIEGES),
             THYCADU, THIRUVANANTHAPURAM-695 014.

             BY ADV GOVERNMENT PLEADER
             SRI.K.V.MANOJKUMAR SR.G.P


      THIS     WRIT     PETITION      (CIVIL)    HAVING   COME   UP   FOR
ADMISSION      ON     11.11.2021,     ALONG     WITH   WP(C).21906/2021,
21944/2021 AND CONNECTED CASES, THE COURT ON THE SAME DAY
DELIVERED THE FOLLOWING:
 WP(C) NO. 22964 OF 2021 & con.cases        3




             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                      PRESENT
               THE HONOURABLE MR.JUSTICE N.NAGARESH
  THURSDAY, THE 11TH DAY OF NOVEMBER 2021 / 20TH KARTHIKA,
                                       1943
                        WP(C) NO. 21906 OF 2021
PETITIONER:
          VARGHESE SCARIA
          AGED 30 YEARS
          S/O. T.C.SCARIA, RESIDING AT PAZHUKKANIYIL HOUSE,
          PUTHUPARIYARAM P.O., THODUPUZHA, IDUKKI DISTRICT,
          PIN-685608.
          BY ADVS.
          ABDUL RAOOF PALLIPATH
          K.R.AVINASH
          E.MUHAMMED SHAFI
          C.H.ABDUL RASAC
RESPONDENTS:
    1     STATE OF KERALA
          REPRESENTED BY THE SECRETARY,
          PUBLIC WORKS DEPARTMENT,
          THIRUVANANTHAPURAM-695001.
    2     THE CHIEF ENGINEER,
          PUBLIC WORKS DEPARTMENT, 3RD FLOOR,
          REVENUE COMPLEX, PUBLIC OFFICE BUILDING,
          THIRUVANANTHAPURAM-695001.
    3     THE SUPERINTENDING ENGINEER,
          PWD ROADS & BRIDGES, CENTRAL CIRCLE, ALUVA,
          ERNAKULAM-683101.
    4     THE EXECUTIVE ENGINEER,
          PWD ROADS DIVISION, PAINAVU, IDUKKI-685603.
          BY ADV GOVERNMENT PLEADER
      THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON
11.11.2021, ALONG WITH WP(C).23576/2021 AND CONNECTED CASES, THE
COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C) NO. 22964 OF 2021 & con.cases        4




             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                      PRESENT
               THE HONOURABLE MR.JUSTICE N.NAGARESH
  THURSDAY, THE 11TH DAY OF NOVEMBER 2021 / 20TH KARTHIKA,
                                       1943
                        WP(C) NO. 21944 OF 2021
PETITIONER:

             MADATHIL ENTERPRICES,
             MADATHIL HOUSE, MANNAKKAT P.O, THODUPUZHA,
             IDUKKI DISTRICT 685 608
             REPRESENTED BY ITS MANAGING PARTNER, JILIMON JOHN
             BY ADVS.
             ABDUL RAOOF PALLIPATH
             K.R.AVINASH (KUNNATH)
             C.H.ABDUL RASAC
RESPONDENTS:

     1       THE STATE OF KERALA
             REPRESENTED BY THE SECRETARY, PUBLIC WORKS
             DEPARTMENT, THIRUVANANTHAPURAM 695 001
     2       THE CHIEF ENGINEER
             PUBLIC WORKS DEPARTMENT, 3RD FLOOR,
             REVENUE COMPLEX, PUBLIC OFFICE BUILDING,
             THIRUVANANTHAPURAM.
     3       THE SUPERINTENDING ENGINEER,
             PWD ROADS AND BRIDGES, CENTRAL CIRCLE, ALUVA,
             PIN 683101
     4       THE EXECUTIVE ENGINEER
             PWD ROADS DIVISION, PAINAVU, IDUKKI DISTRICT.
             BY ADV GOVERNMENT PLEADER
      THIS     WRIT    PETITION        (CIVIL)   HAVING   COME   UP   FOR
ADMISSION ON 11.11.2021, ALONG WITH WP(C).23576/2021 AND
CONNECTED CASES, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
 WP(C) NO. 22964 OF 2021 & con.cases        5




             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                      PRESENT
               THE HONOURABLE MR.JUSTICE N.NAGARESH
  THURSDAY, THE 11TH DAY OF NOVEMBER 2021 / 20TH KARTHIKA,
                                       1943
                        WP(C) NO. 22964 OF 2021
PETITIONER:

            M/S.MALABAR TECH
            REP BY ITS MANAGING PARTNER, N.ABDUL RAFEQUE,
            S/O. ABDUL RAHIMAN HAJI, AGED 49 YEARS, HI TOWER,
            IGBT BYE-PASS, MANJERI,
            MALAPPURAM DSITRICT-676 121
            BY ADVS.
            GEORGE MATHEW
            M.D.SASIKUMARAN
            SUNIL KUMAR A.G
            DIPU JAMES
            MATHEW K.T.
            GEORGE K.V.
            STEPHY K REGI


RESPONDENTS:

     1      STATE OF KERALA
            REPRESENTED BY CHIEF SECRETARY, GOVERNMENT
            SECRETARIAT, THIRUVANANTHAPURAM-695 001
     2      THE PUBLIC WORKS DEPARTMENT,
            REP BY ITS SECRETARY, GOVERNMENT SECRETARIAT,
            THIRUVANANTHAPURAM-695 001
     3      THE FINANCE DEPARTMENT (INDUSTRIES & PUBLIC WORKS
            -B)
            REP BY ITS SECRETARY, GOVERNMENT SECRETARIAT,
            THIRUVANANTHAPURAM-695 001
 WP(C) NO. 22964 OF 2021 & con.cases      6



     4       THE CHIEF ENGINEER,
             OFFICE OF THE CHIEF ENGINEER,
             PUBLIC WORKS DEPARTMENT (ROADS & BRIDGES)
             THYCAUD, THIRUVANANTHAPURAM-695 014

     5       THE SUPERINTENDING ENGINEER,
             PUBLIC WORKS DEPARTMENT, ROADS CENTRAL CIRCLE,
             ALUVA-683 101
     6       THE EXECUTIVE ENGINEER,
             OFFICE OF THE EXECUTIVE ENGINEER,PUBLIC WORKS
             DEPARTMENT, ROADS DIVISION, AYYANTHOLE,
             THRISSUR DISTRICT-680 002
     7       THE SENIOR FINANCE OFFICER,
             OFFICE OF THE CHIEF ENGINEER,
             PUBLIC WORKS DEPARTMENT, P.W.D (ROADS & BRIDGES)
             THYCAUD, THIRUVANANTHAPURAM-695 014

             SRI.K.V.MANOJKUMAR SR.GOVERNMENT PLEADER


      THIS     WRIT    PETITION       (CIVIL)   HAVING   COME   UP   FOR
ADMISSION ON 11.11.2021, ALONG WITH WP(C).23576/2021 AND
CONNECTED CASES, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
 WP(C) NO. 22964 OF 2021 & con.cases        7




             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                      PRESENT
               THE HONOURABLE MR.JUSTICE N.NAGARESH
  THURSDAY, THE 11TH DAY OF NOVEMBER 2021 / 20TH KARTHIKA,
                                       1943
                        WP(C) NO. 22950 OF 2021
PETITIONER:

            M/S MALABAR TECH
            REP BY ITS MANAGING PARTNER, N.ABDUL RAFEQUE, S/O
            ABDUL RAHIMAN HAJI, AGED 49 YEARS, HI TOWER, IGBT
            BYE-PASS, MANJERI, MALAPPURAM DISTRICT-676 121.
            BY ADVS.
            GEORGE MATHEW
            M.D.SASIKUMARAN
            MATHEW K.T.
            SUNIL KUMAR A.G
            GEORGE K.V.
            PRAVEEN S.
            DIPU JAMES
            STEPHY K REGI


RESPONDENTS:

     1      STATE OF KERALA
            REPRESENTED BY CHIEF SECRETARY,
            GOVERNMENT SECRETARIAT,
            THIRUVANANTHAPURAM-695 001.
     2      THE PUBLIC WORKS DEPARTMENT,
            REP BY ITS SECRETARY, GOVERNMENT SECRETARIAT,
            THIRUVANANTHAPURAM-695 001.
     3      THE FINANCE DEPARTMENT
            (INDUSTRIES & PUBLIC WORKS-B),
            REP BY ITS SECRETARY, GOVERNMENT SECRETARIAT,
            THIRUVAANANTHAPURAM-695 001.
 WP(C) NO. 22964 OF 2021 & con.cases      8



     4       THE CHIEF ENGINEER,
             OFFICE OF THE CHIEF ENGINEER,
             PUBLIC WORKS DEPARTMENT (ROADS & BRIDGES)
             THYCADU, THIRUVANANTHAPURAM-695M014.


     5       THE SUPERINTENDING ENGINEER,
             PUBLIC WORKS DEPARTMENT, ROADS CENTRAL CIRCLE,
             ALUVA-683 101.
     6       THE EXECUTIVE ENGINEER
             OFFICE OF THE EXECUTIVE ENGINEER, PUBLIC WORKS
             DEPARTMENT, ROADS, DIVISION, AYYANTHOLE,
             THRISSUR DISTRICT-680 002.
     7       THE SENIOR FINANCE OFFICER,
             OFFICE OF THE CHIEF ENGINEER, PUBLIC WORKS
             DEPARTMENT P.W.D (ROADS & BRIDGES) THYCADU,
             THIRUVANANTHAPURAM-695 014.

             SRI. K.V.MANOJKUMAR SR. GOVERNMENT PLEADER


      THIS     WRIT    PETITION       (CIVIL)   HAVING   COME   UP   FOR
ADMISSION ON 11.11.2021, ALONG WITH WP(C).23576/2021 AND
CONNECTED CASES, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
 WP(C) NO. 22964 OF 2021 & con.cases        9




             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                      PRESENT
               THE HONOURABLE MR.JUSTICE N.NAGARESH
  THURSDAY, THE 11TH DAY OF NOVEMBER 2021 / 20TH KARTHIKA,
                                       1943
                        WP(C) NO. 23085 OF 2021
PETITIONER:

            MALABAR TECH,
            REPRESENTED BY ITS MANAGING PARTNER,
            N.ABDUL RQFEQUE, S/O.ABDUL RAHIMAN HAJI, AGED 49
            YEARS, HI TOWER, NEAR POOKOTTUR JUNCTION,
            IGBT BYE-PASS, MANJERI,
            MALAPPURAM DISTRICT-676 121.
            BY ADVS.
            GEORGE MATHEW
            M.D.SASIKUMARAN
            S.PRAVEEN
            SUNIL KUMAR A.G
            DIPU JAMES
            MATHEW K.T.
            GEORGE.K.V
            STEPHY K REGI


RESPONDENTS:

     1      STATE OF KERALA,
            REPRESENTED BY ITS CHIEF SECRETARY,
            GOVERNMENT SECRETARIAT,
            THIRUVANANTHAPURAM-695 001.
     2      THE PUBLIC WORKS DEPARTMENT,
            REPRESENTED BY ITS SECRETARY, GOVERNMENT
            SECRETARIAT, THIRUVANANTHAPURAM-695 001.
     3      THE FINANCE DEPARTMENT (INDUSTRIES & PUBLIC WORKS
            -B),
            REPRESENTED BY ITS SECRETARY, GOVERNMENT
            SECRETARIAT, THIRUVANANTHAPURAM-695 001.
 WP(C) NO. 22964 OF 2021 & con.cases      10



     4       THE CHIEF ENGINEER,
             OFFICE OF THE CHIEF ENGINEER, PUBLIC WORKS
             DEPARTMENT (ROADS & BRIDGES), THYCADU,
             THIRUVANANTHAPURAM-695 014.
     5       THE SUPERINTENDING ENGINEER,
             PUBLIC WORKS DEPARTMENT, ROADS NORTH CIRCLE,
             PWD COMPLEX, MANANCHIRA,
             KOZHIKODE DISTRICT-673 001.
     6       THE EXECUTIVE ENGINEER,
             OFFICE OF THE EXECUTIVE ENGINEER,
             PUBLIC WORKS DEPARTMENT, ROADS DIVISION, MANJERI,
             MALAPPURAM DISTRICT-676 121.
     7       THE SENIOR FINANCE OFFICER,
             OFFICE OF THE CHIEF ENGINEER, PUBLIC WORKS
             DEPARTMENT, P.W.D., (ROADS & BRIDGES), THYCADU,
             THIRUVANANTHAPURAM-695 014.
              SRI. K.V.MANOJKUMAR SR. GOVERNMENT PLEADER


      THIS     WRIT    PETITION       (CIVIL)   HAVING   COME   UP   FOR
ADMISSION ON 11.11.2021, ALONG WITH WP(C).23576/2021 AND
CONNECTED CASES, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
 WP(C) NO. 22964 OF 2021 & con.cases        11




             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                      PRESENT
               THE HONOURABLE MR.JUSTICE N.NAGARESH
  THURSDAY, THE 11TH DAY OF NOVEMBER 2021 / 20TH KARTHIKA,
                                       1943
                        WP(C) NO. 23608 OF 2021
PETITIONER

            RAJI MATHEW
            AGED 56 YEARS
            S/O. MATHEW, PAMPLANIYIL HOUSE,
            BHARANANGANAM P.O., MEENACHIL TALUK, KOTTAYAM
            DISTRICT-686 578.
            BY ADVS.
            GEORGE MATHEW
            M.D.SASIKUMARAN
            PRAVEEN S.
            SUNIL KUMAR A.G
            DIPU JAMES
            MATHEW K.T.
            GEORGE K.V.
            STEPHY K REGI


RESPONDENTS:

     1      STATE OF KERALA
            REPRESENTED BY CHIEF SECRETARY,
            GOVERNMENT SECRETARIAT,
            THIRUVANANTHAPURAM-695 001.
     2      THE PUBLIC WORKS DEPARTMENT
            REPRESENTED BY ITS SECRETARY, GOVERNMENT
            SECRETARIAT, THIRUVANANTHAPURAM-695 001.
     3      THE FINANCE DEPARTMENT (INDUSTRIES & PUBLIC
            WORKS-B)
            REPRESENTED BY ITS SECRETARY, GOVERNMENT
            SECRETARIAT, THIRUVANANTHAPURAM-695 001.
 WP(C) NO. 22964 OF 2021 & con.cases      12




     4       THE CHIEF ENGINEER
             OFFICE OF THE CHIEF ENGINEER, PUBLIC WORKS
             DEPARTMENT (ROADS & BRIDGES), THYCADU,
             THIRUVANANTHAPURAM-695 014.


     5       THE SUPERINTENDING ENGINEER
             PUBLIC WORKS DEPARTMENT, ROADS CENTRAL CIRCLE,
             ALUVA-683 101.
     6       THE EXECUTIVE ENGINEER
             OFFICE OF THE EXECUTIVE ENGINEER, PUBLIC WORKS
             DEPARTMENT, ROADS DIVISION, PAINAVU P.O.,
             IDUKKI DISTRICT-685 603
     7       THE SENIOR FINANCE OFFICER
             OFFICE OF THE CHIEF ENGINEER,
             PUBLIC WORKS DEPARTMENT P.W.D. (ROADS & BRIDGES)
             THYCADU, THIRUVANANTHAPURAM-695 014.

             SRI. K.V.MANOJKUMAR SR. GOVERNMENT PLEADER


      THIS     WRIT    PETITION       (CIVIL)   HAVING   COME   UP   FOR
ADMISSION ON 11.11.2021, ALONG WITH WP(C).23576/2021 AND
CONNECTED CASES, THE COURT ON THE SAME DAY DELIVERED THE
FOLLOWING:
 WP(C) NO. 22964 OF 2021 & con.cases        13




             IN THE HIGH COURT OF KERALA AT ERNAKULAM
                                      PRESENT
               THE HONOURABLE MR.JUSTICE N.NAGARESH
  THURSDAY, THE 11TH DAY OF NOVEMBER 2021 / 20TH KARTHIKA,
                                       1943
                        WP(C) NO. 24694 OF 2021
PETITIONERS:
    1     ELDHO JOSE K,AGED 46 YEARS
          S/O. K.P.JOSE, KOTTISERIKKUDI HOUSE,
          NEDUNGAPARA P.O., PERUMBAVOOR, ERNAKULAM,
          PIN-683 545.
    2     SAJEEV P.A.
          AGED 66 YEARS
          S/O. AYYAPPANKUTTY, PARAMBIL HOUSE, ALLAPRA P.O.,
          PERUMBAVOOR, ERNAKULAM DISTRICT, PIN-683 556.
          BY ADVS., ABDUL RAOOF PALLIPATH
                   K.R.AVINASH (KUNNATH)
                  C.H.ABDUL RASAC
RESPONDENTS:
    1     STATE OF KERALA
          REPRESENTED BY THE SECRETARY, PUBLIC WORKS
          DEPARTMENT, THIRUVANANTHAPURAM-695 001.
    2     THE CHIEF ENGINEER
          PUBLIC WORKS DEPARTMENT, 3RD FLOOR, REVENUE
          COMPLEX, PUBLIC OFFICE BUILDING,
          THIRUVANANTHAPURAM-695 001.
    3     THE SUPERINTENDING ENGINEER
          PWD ROADS AND BRIDGES, CENTRAL CIRCLE, ALUVA,
          PIN-683 101.
    4     THE EXECUTIVE ENGINEER
          PWD ROADS DIVISION, ERNAKULAM,
          ERNAKULAM DISTRICT-682 016.
          SRI. K.V.MANOJKUMAR SR. GOVERNMENT PLEADER
      THIS   WRIT   PETITION   (CIVIL)    HAVING   COME   UP   FOR   ADMISSION   ON

11.11.2021, ALONG WITH WP(C).23576/2021 AND CONNECTED CASES, THE COURT

ON THE SAME DAY DELIVERED THE FOLLOWING:
 WP(C) NO. 22964 OF 2021 & con.cases   14


                               JUDGMENT

Dated this the 11th day of November, 2021

[WP(C) Nos.23576/2021, 21906/2021, 21944/2021, 22964/2021, 22950/2021, 23085/2021, 23608/2021, 24694/2021]

Petitioners in all these writ petitions are A class contractors

under the Public Works Department. They are before this Court

aggrieved by a Government Order dated 30.04.2021. As the

facts involved in all these writ petitions are same, W.P.(c)

No.22964 of 2021 is taken as the main case and the parties and

documents are referred to in this judgment as they are

arrayed/exhibited in W.P.(c) No.22964 of 2021.

2. The All Kerala Government Contractors Association

submitted Ext.R2(a) representation dated 18.10.2018 to the

Principal Secretary to the Finance Department of the Kerala

Government pointing out the sky rocketed prices of bitumen and

requesting that the escalated price of bitumen may be paid to

the contractors. Another Labour Contract Co-operative Society WP(C) NO. 22964 OF 2021 & con.cases 15

also submitted Ext. R2(c) representation to the Government,

with similar prayers.

3. Taking into consideration the fact that the unless

some adjustments are made, the contractors are bound to suffer

huge losses, the Finance (Industries & Public Works-B)

Department issued Ext.P8 order dated 13.11.2018 stating that

since the price of bitumen as on April, 2018 had increased by

33%, for the ongoing works with effect from 01.11.2018, the

price difference of bitumen as on the date of closing tender and

the date of invoice (invoice date on or after 01.11.2018) will be

paid to the contractors on the production of original invoice for

the actual quantity consumed for the work within original term of

completion. It was also ordered in Ext.P8 that price difference

will also be allowed to all works with extended Term of

Completion (without fine extension).

4. A Labour Contract Co-operative Society made a

representation to the Government requesting to modify the WP(C) NO. 22964 OF 2021 & con.cases 16

Ext.P8 Government Order by allowing the difference between

the estimate rate and market rate of bitumen. The Government

examined the matter and was pleased to modify Clause 1 of the

Ext.P8 Government Order to the extent that the price difference

of bitumen as on the date of agreement between the

contractor/accredited agency and the implementing officer and

the date of invoice (invoice date on or after 01.11.2018) may be

paid to or recovered from the contractor/accredited agency. This

modification was done as per Ext.P9 G.O. (Rt) dated

17.04.2020.

5. The Chairman, Builders Association of India

submitted yet another representation before the Hon'ble Minister

(Finance) requesting to modify Ext.P9 Government Order stating

that the date of closing of tender should be the basis for

calculation of the price difference of bitumen as the date of

agreement may be delayed for numerous reasons. Having

examined the matter, the Government, as per Ext.P10 G.O.(Rt) WP(C) NO. 22964 OF 2021 & con.cases 17

dated 25.09.2020, found that there is merit in the demand made

by the Chairman, Builders Association of India and accordingly

modified paragraph 3 of Ext.P9 Government Order and stated

that for open tenders, the price difference of bitumen as on date

of closing of tenders and the date of invoice ( after 01.11.2018)

will be payable. For works on nomination, the price difference of

bitumen as on date of agreement and date of invoice (after

01.11.2018) will be payable.

6. While the contractors were being extended with the

benefits of Exts.P8 to P10, the All Kerala Government

Contractors Association and the Chairman, Builders Association

of India, requested to issue clarification on the rate of bitumen to

be considered while calculating the allowable price difference of

bitumen and on whether Ext.P8 Government Order is applicable

for agreements executed after 01.11.2018. The Government

thereupon modified paragraph 3 of Ext.P8 order as follows:-

"3. Government have examined the matter in detail and are pleased to modify paragraph 3 of Government Order read as WP(C) NO. 22964 OF 2021 & con.cases 18

3rd paper above as follows:

For works based on open tenders the price of difference of bitumen payable/recoverable shall be reckoned, as the difference of invoice value and the market rate of bitumen, as on the last date of submission of tender.

For works on nomination, the price difference of bitumen payable/recoverable shall be reckoned as the difference of invoice value and the market rate of bitumen, as on the date of agreement, as the case may be."

4. This Government Order is applicable for all ongoing works and works for which agreements are executed after 01.11.2018.

In the said Ext.P7 G.O.(Rt) dated 30.04.2021, the Government

made it clear that the said order is applicable for all ongoing

works and works for which agreements are executed after

01.11.2018. It is aggrieved by the said Ext.P7 order dated

30.04.2021, the petitioners have filed these writ petitions.

7. The learned counsel representing the petitioners

contended that the Government Orders at Exts.P7 to P10 would

apply only to ongoing tenders as on 01.11.2018. The orders

were issued by the Government taking into consideration the

unprecedented escalation of price in bitumen and in order to

save the contractors from incurring huge losses. The intention of WP(C) NO. 22964 OF 2021 & con.cases 19

the Government was not to recover any amount out of the profit

legitimately being earned by the contractors.

8. The respondents are not justified in ordering recovery

of the price difference of bitumen from the amounts payable to

the petitioners based on Ext.P7. If at all there is any marginal

decrease in the price of bitumen between the date of agreement

and the date of invoice, that should be treated as legitimate

profit gained by the petitioners. The respondents have no right to

claim that such differential amount should be paid to the

Government. It was further contended by the petitioners that, if

such type of recovery is permitted from the bills payable to the

petitioners, tomorrow a day may come wherever the cost is

decreased in respect of any materials used by the contractors,

the Government can demand refund, following the same criteria.

9. The learned counsel for the petitioners argued that if

Ext.P7 is implemented as such, it will result in exerting undue

influence according to the whims and fancies of the WP(C) NO. 22964 OF 2021 & con.cases 20

respondents. Such action would be against principles of

fairness. In fact Ext.P7 Government Order would amount to

unconscionable bargain leaving the petitioners having no choice

or meaningful choice to resist the same. The impugned order

goes against the legitimate expectation of petitioners that they

would be able to undertake works for respondents and get cost

of work realised without unwarranted deduction.

10. The respondents resisted the writ petition. The

learned Senior Government Pleader pointed out that the attempt

of the petitioners is to take advantage of the Government Orders

and make profit, at the same time escaping from refunding

undue benefits emanating from the decrease of price of bitumen.

The learned Senior Government Pleader pointed out that Ext.P7

Government Order was issued at the request of the Contractors

Association and Labour Welfare Societies as is evident from

Exts.R2(b) and R2(c). The petitioners are bound by the

Government Orders, which were issued in the larger interest of WP(C) NO. 22964 OF 2021 & con.cases 21

all contractors.

11. The learned Senior Government Pleader relied on

Clause 5.2 of the Standard Bidding Documents (Ext.R2 (a)) to

contend that the contractors are bound to follow relevant Kerala

State Government Orders, Circulars, Kerala PWD Manual etc.

prevailing at the time of the contract eventhough specific

reference to these are not provided elsewhere in the contract

conditions. As the petitioners are bound by Clause 5.2 of the

Standard Bidding Document, they cannot be heard to contend

that Exts.P7 to P10 orders will not apply to them. The learned

Government Pleader urged that what is executed by the

petitioners is rate contract and but for Exts.P7 to P10, on no

account the petitioners are entitled to increase of rates once

fixed. The learned Senior Government Pleader relying on Ext.P2

pointed out that the defect liability period of the work should also

be taken as part of the contract and the term ongoing works will

include the work to be undertaken during the defect liability WP(C) NO. 22964 OF 2021 & con.cases 22

period also.

12. Relying on the judgment of the Hon'ble Apex Court in

State of U.P and Others v. Bride and Roof Company (India)

Ltd. [AIR 1996 SCC 3515], the learned Senior Government

Pleader urged that the writ petition filed by the petitioners shall

not be entertained. In respect of contractual matters when

deductions are legitimately made by the Governmental

authorities, such action cannot be challenged by filing a writ

petition. Any dispute relating to interpretation of the terms and

conditions of a contract cannot be agitated in a writ petition.

Those are matters either for arbitration as provided by the

contract or for civil court, as the case may be. Whether any

amount is due from the government under the contract and if so

how much and the further question whether retention or refusal

to pay any amount by the Government is justified or not, are all

matters which cannot be agitated or adjudicated upon in a writ

petition.

WP(C) NO. 22964 OF 2021 & con.cases 23

13. The learned Senior Government Pleader specifically

drew attention of this Court to paragraph 18 of the judgment in

State of U.P (supra) wherein the Hon'ble Apex Court held that

the writ petition filed by the respondent for the issuance of a writ

of mandamus restraining the Government from deducting or

withholding a particular sum, which according to the respondent

is payable to it under the contract, was wholly misconceived and

was not maintainable in law. The Hon'ble Apex Court held that

such writ petition ought to have been dismissed on that ground

alone.

14. Relying on the judgment in R.C.Tobacco (P) Ltd.

And another vs. Union of India and another [2005 7 SCC

725], the learned Senior Government Pleader contended that a

law cannot be held to be unreasonable merely because it

operates retrospectively. Even judicial decisions are in a sense

retrospective. There cannot be a legal proposition that no

Government Orders shall apply retrospectively. At the same WP(C) NO. 22964 OF 2021 & con.cases 24

time, the learned Government Pleader pointed out that when the

defect liability period is also treated as a part of the contractual

work, then the Government Orders issued even during the

defect liability period should be applicable to the contractors, in

view of Clause 5.2 of the Standard Bidding Documents.

15. The attempt of the petitioners is to take advantage of

the orders issued by the respondents pursuant to the collective

demand made by the contractors through their association and

at the same time to get unduly enriched by not adjusting the

amounts earned due to gross fall of price in the bitumen. Such

demands will be against public interest and would adversely

effect the public exchequer. The writ petitions are therefore

liable to be dismissed, contended the learned Senior

Government Pleader.

16. I have heard the learned counsel for the petitioners

and the learned Senior Government Pleader representing the

respondents.

WP(C) NO. 22964 OF 2021 & con.cases 25

17. The issues arising for consideration in these writ

petitions are whether Ext.P7 G.O. dated 30.04.2021 issued by

the respondents can be applied to the petitioners for effecting

recovery from the amounts payable to them and also whether

Ext.P7 can be operated retrospectively to all agreements

executed by the petitioners irrespective of whether those works

were ongoing as on 01.11.2018 or not. The Learned Senior

Government Pleader is right in contending that the petitioners

are bound to follow relevant Kerala State Government Orders,

Circulars, Kerala PWD Manual etc. prevailing at the time of the

contract eventhough specific reference to these are not provided

elsewhere in the contract condition. But the issue here is

whether Exts.P7 to P10 orders would apply to the petitioners at

all.

18. Ext.P8 is the first Government Order, by which certain

benefits were extended to the PWD contractors in the matter of

price difference in bitumen. The relevant portion of Ext.P8 G.O WP(C) NO. 22964 OF 2021 & con.cases 26

reads as follows:-

"1. Since the price of Bitumen as on April 2018 had increased by 33%, for the ongoing works with effect from 01.11.2018, the price difference of Bitumen as on the date of closing tender and the date of invoice (invoice date on or after 01.11.2018) will be paid to the contractor on the production of original invoice for the actual quantity consumed for the work within original term of completion."

The afore provision would show that it is intended to apply only

for the ongoing works with effect from 01.11.2018. Therefore if

the works under the agreements entered into by the petitioners

were not ongoing works, as on 01.11.2018, Ext.P8 Government

Order cannot be made applicable to the petitioners.

19. Ext.P8 Government Order was modified as per

Ext.P9. Paragraph 3 of Ext.P9 Government Order reads as

follows:-

3) Government have examined the matter in detail and are pleased to modify Clause 1 of the Government Order read above to the extend that the price difference of bitumen as on the date of agreement between the contractor/accredited agency and the Implementing Officer and the date of invoice (Invoice date on or after 01.11.2018) may be paid to or recovered from the contractor/accredited agency.

WP(C) NO. 22964 OF 2021 & con.cases 27

The said paragraph is very clear that by Ext.P9, the Ext.P8

Government Order has been modified only to the extent that the

price difference of bitumen is to be decided as on the date of

agreement between the Contractor/accredited agency and the

implementing officer and the date of invoice (invoice date on or

after 01.11.2018). The said price difference is to be paid to or

recovered from the contractor/ accredited agency. In other

words, all other terms and conditions in Ext.P8 Government

Order would remain the same. As Ext.P8 Government Order

was intended to apply only to those ongoing projects an on

01.11.2018, Ext.P9 also would apply only to those ongoing

projects.

20. By Ext.P10 Government Order dated 25.09.2020, the

Government has effected some more modifications. Paragraph

3 of Ext.P10 G.O, reads as follows:-

3. Government have examined the matter in detail and are pleased to modify para 3 of Government Order read as 2nd paper above as follows:

WP(C) NO. 22964 OF 2021 & con.cases 28

-For open tenders, the price difference of bitumen as on date of closing of tenders and the date of invoice (after 01.11.2018) will be payable.

-For works on nomination, the price difference of bitumen as on date of agreement and date of invoice (after 01.11.201) will be payable

The afore provisions would also show that the modification

effected by Ext.P10 is only to paragraph 3 of Ext.P9

Government Order. Therefore, other terms and conditions as

existed in Exts.P8 and P9 orders will continue to apply and

hence those orders will apply only to ongoing works as on

01.11.2018.

21. The petitioners are aggrieved by the subsequently

issued Ext.P7 Government Order dated 30.04.2021. After

examining the request made by the Contractor's Association, the

respondents as per Ext.P7 Government Order decided that for

works based on open tenders the price difference of bitumen

payable/ recoverable shall be reckoned, as the difference of

invoice value and the market rate of bitumen, as on the last date

of submission of tender. For works on nomination, the price WP(C) NO. 22964 OF 2021 & con.cases 29

difference of bitumen payable/recoverable shall be reckoned as

the difference of invoice value and the market rate of bitumen as

on the date of agreement, as the case may be. The material

portion of Ext.P7 reads as follows:-

"3. Government have examined the matter in detail and are pleased to modify paragraph 3 of Government Order read as 3rd paper above as follows:

For works based on open tenders the price of difference of bitumen payable/recoverable shall be reckoned, as the difference of invoice value and the market rate of bitumen, as on the last date of submission of tender.

For works on nomination, the price difference of bitumen payable/recoverable shall be reckoned as the difference of invoice value and the market rate of bitumen, as on the date of agreement, as the case may be."

Again, Ext.P7 would also show that the modification effected by

Ext.P7 is only to paragraph 3 of Ext.P10 Government Order.

22. The benefit or advantage conferred under Ext.P8

Government Order is intended only for those projects of the

contractors which were ongoing projects as on 01.11.2018. The

modifications effected by Exts.P8, P9 and P10 orders would

obviously apply only to those ongoing contract works as on WP(C) NO. 22964 OF 2021 & con.cases 30

01.11.2018, as contemplated by Ext.P8 Government Order. As

Exts.P8 to P10 Government Orders are intended to apply only to

ongoing contract works as on 01.11.2018, those orders cannot

be made applicable to the works undertaken by the petitioners,

subsequently, which were not ongoing works as on 01.11.2018.

23. Ext.P7 order has been issued based on a request made by

the All Kerala Government Contractors Association and the

Builders Association of India, to clarify the earlier orders on the

price of bitumen. As per paragraph 3 of Ext.P7, the Government

has modified paragraph 3 of the Ext.P10 order. The Ext.P7

however states that the said order is applicable for all ongoing

works and works for which agreements are executed after

01.11.2018. Thus, when Exts.P8 to P10 were applicable only to

ongoing works as on 01.11.2018, Ext.P7 made the modification

applicable to all ongoing works and works for which agreements

are executed.

WP(C) NO. 22964 OF 2021 & con.cases 31

24. The Ext.P7 thus imposes a new condition in all the

ongoing works as on 30.04.2021. Further, the said new

condition is made applicable to all works for which agreements

are executed after 01.11.2018. Ext.P7 is legally infirm for two

reasons. Firstly, by Ext.P7, a new onerous condition is imposed

on all ongoing works unilaterally, which is impermissible in law. It

is true that as per Clause 5.2 of the Standard Bidding Document,

a contractor is bound by all Government Orders prevailing. But

the said Clause cannot take in Government Orders which were

not prevailing at the time of the execution of agreement.

25. Secondly, there may be contracts executed after

01.11.2018 and works completed before issuance of Ext.P7 on

30.04.2021. Subsequently issued Government Orders cannot

alter the rights and liabilities of concluded commercial contracts.

For both the afore reasons, Ext.P7 order cannot be made

applicable to all agreements executed after 01.11.2018 and

before 30.04.2021.

WP(C) NO. 22964 OF 2021 & con.cases 32

In the circumstances, it is declared that Ext. P7

Government Order dated 30.04.2021 will not apply to such

contract works undertaken by the petitioners prior to 30.04.2021

which were not ongoing contract works as on 01.11.2018. All

consequence of such declaration will follow. The writ petitions

are disposed of as above. However, it is made clear that Ext. P7

Government Order will apply to all contract works including if

any undertaken by the petitioners, the work of which were

ongoing as on 01.11.2018.

Sd/-

N.NAGARESH JUDGE hmh WP(C) NO. 22964 OF 2021 & con.cases 33

APPENDIX OF WP(C) 21906/2021

PETITIONER EXHIBITS

Exhibit P1 TRUE COPY OF FORMAT OF NOTICE INVITING TENDER.

Exhibit P2 TRUE COPY OF THE CONTRACT AGREEMENT NO.74/SECCA/2019-2020 DATED 18.9.2019. Exhibit P3 TRUE COPY OF THE COMPLETION CERTIFICATE FOR THE CONTRACT AGREEMENT NO.74/SECCA/2019-2020 DATED 15.9.21. Exhibit P4 TRUE COPY OF CONTRACT AGREEMENT NO.93/SECCA/18-19 DATED 1.1.2019.

Exhibit P5 TRUE COPY OF THE COMPLETION CERTIFICATE FOR THE CONTRACT AGREEMENT NO.93/SECCA/18-19.

Exhibit P6 TRUE COPY OF THE G.O.(RT) NO.9386/2018/FIN DATED 13.11.2018 ISSUED BY THE GOVERNMENT.

Exhibit P7 TRUE COPY OF THE CIRCULAR NO.753/2012/CE/LSGD DATED 15.2.2020 ISSUED BY THE 2ND RESPONDENT.

Exhibit P8                  TRUE COPY OF THE G.O.(RT)
                            NO.3815/2021/FIN DATED 30.4.2021
                            ISSUED BY THE GOVERNMENT.
Exhibit P9                  TRUE COPY OF THE INTERIM ORDER PASSED
                            IN WP(C) NO.19228/2021 DATED
                            30.9.2021.
RESPONDENT EXHIBITS          NIL
 WP(C) NO. 22964 OF 2021 & con.cases   34


                     APPENDIX OF WP(C) 21944/2021


PETITIONER EXHIBITS

Exhibit P1                TRUE COPY OF FORMAT OF NOTICE INVITING
                          TENDER.
Exhibit P2                TRUE COPY OF THE CONTRACT AGREEMENT NO.

86/SECCA/2019-20 DATED 25-10-2019. Exhibit P3 TRUE COPY OF THE COMPLETION CERTIFICATE FOR THE CONTRACT AGREEMENT NO.

86/SECCA/2019-20 Exhibit P4 TRUE COPY OF WORK ORDER DATED 09-10-

2019 ISSUED BY THE 3RD RESPONDENT Exhibit P5 TRUE COPY OF THE RELEVANT PAGE OF PWD MANUAL Exhibit P6 TRUE COPY OF THE G.O(RT) NO 9386/2018/FIN DATED 13-11-2018 Exhibit P7 TRUE COPY OF THE CIRCULAR DATED 15-02-

2020 ISSUED BY THE 3RD RESPONDENT Exhibit P8 TRUE COPY OF THE G.O(RT) NO. 3815/FIN DATED 30-04-2021 Exhibit P9 TRUE COPY OF THE INTERIM ORDER PASSED IN W.P.C NO. 19228/2021 DATED 30-09-

RESPONDENT EXHIBITS         NIL
 WP(C) NO. 22964 OF 2021 & con.cases   35


                     APPENDIX OF WP(C) 22964/2021


PETITIONER EXHIBITS
Exhibit P1          TRUE COPY OF NIT NO.RDDNTSR/RD/2019/3397

DTD 30.11.2019 ISSUED BY 5TH RESPONDENT Exhibit P2 TRUE COPY OF LETTER NO.DTT-3397/2019 DTD 27.01.2020 ISSUED BY 5TH RESPONDENT Exhibit P3 TRUE COPY OF TREASURY SAVINGS BANK TERM DEPOSIT CERTIFICATE NO.JK O.315566 DTD 06.02.2020 ISSUED FROM SUB TREASURY , MANJERI Exhibit P4 TRUE COPY OF IBG NO.105013 DTD 07.02.2020 OF FEDERAL BANK, MALAPPURAM Exhibit P5 TRUE COPY OF COMPLETION CERTIFICATE DTD 02.07.2021 ISSUED BY 5TH RESPONDENT TO PETITIONER Exhibit P6 TRUE COPY OF CC 1ST AND FINAL BILL DTD NIL IN RESPECT OF EXT P1 WORK ISSUED BY 6TH RESPONDENT Exhibit P7 TRUE COPY OF G.O(RT) NO.3815/2021/FIN DTD 30.40.2021 ISSUED BY 3RD RESPONDENT Exhibit P8 TRUE COPY OF G.O(RT) NO.9386/2018/FIN DTD 13/11/2018 ISSUED BY 3RD RESPONDENT Exhibit P9 TRUE COPY OF G.O(RT) NO.2816/2020/FIN DTD 17.04.2020 ISSUED BY 3RD RESPONDENT Exhibit P10 TRUE COPY OF G.O(RT) NO.5502/2020/FIN DTD 2``5.09.2020 ISSUED BY 3RD RESPONDENT Exhibit P11 TRUE COPY OF ORDER DTD 30.09.2021 IN WPC NO.15722 OF 2021 RESPONDENT EXHIBITS

Exhibit R2(a) TRUE COPY OF THE RELEVANT PAGE OF THE CONTRACT.

Exhibit R2(b) TRUE COPY OF THE REPRESENTATION SUBMITTED BY CONTRACTORS ASSOCIATION BASED ON WHICH EXHIBIT P8 WAS ISSUED.

Exhibit R2(b) TRUE COPY OF THE REPRESENTATION SUBMITTED BY CONTRACTORS ASSOCIATION BASED ON WHICH EXHIBIT P9 WAS ISSUED.

WP(C) NO. 22964 OF 2021 & con.cases 36

APPENDIX OF WP(C) 22950/2021

PETITIONER EXHIBITS Exhibit P1 TRUE COPY OF NIT NO TSR/2018/10801 DATED 28.9.2019 ISSUED BY 5TH RESPONDENT Exhibit P2 TRUE COPY OF LETTER NO DTT-10810/2018 DATED 19.11.2019 ISSUED BY 5TH RESPONDENT Exhibit P3 TRUE COPY OF IBG NO 103080 DATED 27.11.2019 OF FEDERAL BANK LTD MALAPPURAM Exhibit P4 TRUE COPY OF TREASURY SAVINGS BANK TERM DEPOSIT CERTIFICATE NI JK NO 352846 DATED 30.11.2019 ISSUED FROM SUB TREASURY, MANJERI Exhibit P5 TRUE COPY OF COMPLETION CERTIFICATE DATED 7.7.2021 ISSUED BY 5TH RESPONDENT TO THE PETITIONER Exhibit P6 TRUE COPY OF CC 1ST AND FINAL BILL DATED NIL IN RESPECT OF EXT P1 WORK ISSUED BY 6TH RESPONDENT Exhibit P7 TRUE COPY OF NIT NO RDDN TSR/RD/2020/835 DATED 4.9.2020 ISSUED BY 5TH RESPONDENT Exhibit P8 TRUE COPY OF LETTER NO D3-2020/855 DATED 4.11.2020 ISSUED BY 5TH RESPONDENT Exhibit P9 TRUE COPY OF IBG NO 111048 DATED 6.11.2020 OF FEDERAL BANK LTD MALAPPURAM Exhibit P9(A) TRUE COPY OF IBG NO 111050 DATED 6.11.2020 OF FEDERAL BANK LTD, MALAPPURAM Exhibit P10 TRUE COPY OF TREASURY SAVING BANK TERM DEPOSIT CERTIFICATE NI JL0193396 DATED 6.11.2020 ISSUED FROM SUB TREASURY, MANJERI Exhibit P10(A) TRUE COPY OF TREASURY SAVING BANK TERM DEPOSIT CERTIFICATE NO JLO193397 DATED 6.11.2020 ISSUED FROM SUB TREASURY, MANJERI Exhibit P11 TRUE COPY OF COMPLETION CERTIFICATE DATED 6.5.2021 ISSUED 5TH RESPONDENT TO WP(C) NO. 22964 OF 2021 & con.cases 37

THE PETITIONER Exhibit P12 TRUE COPY OF CC 1ST AND FINAL BILL DATED IN RESPECT OF EXT P7 WORK Exhibit P13 TRUE COPY OF GO(RT) NO 3815/2021/FIN DATED 30.4.2021 ISSUED BY 3RD RESPONDENT WITH TYPED COPY Exhibit P14 TRUE COPY OF GO(RT0 NO 9386/2018/FIN DATED 13.11.2018 ISSUED BY 3RD RESPONDENT WITH TYPED COPY Exhibit P15 TRUE COPY OF GO(RT) NO 2816/2020/FIN DATED 17.4.2020 ISSUED BY 3RD RESPONDENT WITH TYPED COPY Exhibit P16 TRUE COPY OF GO(RT0 NO 5502/2020/FIN DATED 25.9.2020 OF 3RD RESPONDENT WITH TYPED COPY Exhibit P17 TRUE COPY OF ORDER DATED 30.9.2021 IN WPC NO 15722 OF 2021 WP(C) NO. 22964 OF 2021 & con.cases 38

APPENDIX OF WP(C) 23085/2021

PETITIONER EXHIBITS Exhibit P1 TRUE COPY OF LETTER NO.DCO7/RD/2020/2960 DATED 28.01.2021 ISSUED BY 5TH RESPONDENT.

Exhibit P2 TRUE COPY OF PROFORMA ALONG WITH RELEVANT PAGES OF AGREEMENT DATED 28.01.2021 ENTERED INTO BETWEEN PETITIONER AND 5TH RESPONDENT.

Exhibit P3 TRUE COPY OF COMPLETION CERTIFICATE DATED 01.07.2021 ISSUED BY 5TH RESPONDENT TO PETITIONER.

Exhibit P4 TRUE COPY OF RELEVANT PAGES OF CC 1ST AND FINAL BILL DATED 26.07.2021.

Exhibit P5 TRUE COPY OF LETTER NO.A1-2683/2021 DATED 20.10.2021 ISSUED BY 6TH RESPONDENT.

Exhibit P6 TRUE COPY OF GO(RT) NO.3815/2021/FIN DATED 30.04.2021 ISSUED BY3RD RESPONDENT.

Exhibit P7 TRUE COPY OF GO(RT) NO.9386/20189/FIN DATED 13.11.2018 ISSUED BY 3RD RESPONDENT.

Exhibit P8 TRUE COPY OF GO9RT0 NO.2816/2020/FIN DATED 17.04.2020 ISSUED BY 3RD RESPONDENT.

Exhibit P9 TRUE COPY OF GO(RT) NO.5502/2020/FIN DATED 25.09.2020 OF 3RD RESPONDENT.

Exhibit P10 TRUE COPY OF ORDER DATED 30.09.2021 IN WPC NO.15722 OF 2021.

WP(C) NO. 22964 OF 2021 & con.cases 39

APPENDIX OF WP(C) 23608/2021

PETITIONER EXHIBITS Exhibit P1 TRUE COPY OF WORK ORDER NO.DIT-1269/2019 DATED 2.8.2019 ISSUED BY 5TH RESPONDENT. Exhibit P2 TRUE COPY OF COMPLETION CERTIFICATE DATED 30.4.2021 ISSUED BY 5TH RESPONDENT.

Exhibit P3 TRUE COPY OF THE STATEMENT DATED NIL WITH REGARD TO DIFFERENCE IN COST OF BITUMEN OF EXT.P1 WORK.

Exhibit P4 TRUE COPY OF REQUEST DATED 26.8.2021 SUBMITTED BY PETITIONER TO 6TH RESPONDENT.

Exhibit P5 TRUE COPY OF LETTER NO.D2-1269/2019 DATED 1.9.2021 ISSUED BY 6TH RESPONDENT. Exhibit P6 TRUE COPY OF G.O.(RT) NO.3815/2021/FIN.

DATED 30.4.2021 ISSUED BY 3RD RESPONDENT.

Exhibit P7 TRUE COPY OF G.O.(RT) NO.9386/2018/FIN.

DATED 13.11.2018 ISSUED BY 3RD RESPONDENT.

Exhibit P8 TRUE COPY OF G.O.(RT) NO.2816/2020/FIN.

DATED 17.4.2020 ISSUED BY 3RD RESPONDENT.

Exhibit P9 TRUE COPY OF G.O.(RT) NO.5502/2020/FIN DATED 25.9.2020 OF 3RD RESPONDENT.

Exhibit P10 TRUE COPY OF ORDER DATED 30.9.2021 IN WPC NO.15722 OF 2021.

WP(C) NO. 22964 OF 2021 & con.cases 40

APPENDIX OF WP(C) 24694/2021

PETITIONER EXHIBITS

Exhibit P1 TRUE COPY OF FORMAT OF NOTICE INVITING TENDER.

Exhibit P2 TRUE COPY OF THE CONTRACT AGREEMENT NO.102/SECCA/2019-20 DATED 18.11.2019 EXECUTED BETWEEN THE IST PETITIONER AND 3RD RESPONDENT.

Exhibit P3 TRUE COPY OF THE COMPLETION CERTIFICATE FOR THE CONTRACT AGREEMENT NO.102/SECCA/2019-20 DATED 18.11.2019. Exhibit P4 TRUE COPY OF CONTRACT AGREEMENT 05/SECCA/2019-2020 DATED 27.05.2019 EXECUTED BETWEEN THE 2ND PETITIONER AND 3RD RESPONDENT.

Exhibit P5 TRUE COPY OF THE COMPLETION CERTIFICATE FOR THE CONTRACT AGREEMENT NO.05/SECCA/2019-2020 DATED 27.05.2019 Exhibit P6 TRUE COPY OF THE G.O.(RT)NO.9386/2018/FIN DATED 13.11.2018.

Exhibit P7 TRUE COPY OF THE CIRCULAR DATED 15.2.2020 ISSUED BY THE 3RD RESPONDENT.

Exhibit P8 TRUE COPY OF THE G.O.(RT) NO.3815/2021/FIN DATED 30.4.2021.

Exhibit P9 TRUE COPY OF THE INTERIM ORDER PASSED IN WPC NO.15722/2021 DATED 30.9.2021.

WP(C) NO. 22964 OF 2021 & con.cases 41

APPENDIX OF WP(C) 23576/2021

PETITIONER EXHIBITS

Exhibit P1 TRUE COPY OF WORK ORDER NO.DII-

10222/2019 DATED 26.7.2019 ISSUED BY 5TH RESPONDENT.

Exhibit P2 TRUE COPY OF COMPLETION CERTIFICATE DATED 3.5.2021 ISSUED BY 5TH RESPONDENT. Exhibit P3 TRUE COPY OF THE STATEMENT DATED NIL WITH REGARD TO DIFFERENCE IN COST OF BITUMEN OF EXT.P1 WORK.

Exhibit P4 TRUE COPY OF REQUEST DATED 26.8.2021 SUBMITTED BY PETITIONER TO 6TH RESPONDENT.

Exhibit P5 TRUE COPY OF LETTER NO.D1-10222/2019 DATED 1.9.2021 ISSUED BY 6TH RESPONDENT. Exhibit P6 TRUE COPY OF WORK ORDER NO.DIT-1269/2019 DATED 2.8.2019 ISSUED BY 5TH RESPONDENT. Exhibit P7 TRUE COPY OF COMPLETION CERTIFICATE DATED 12.2.2021 ISSUED BY 5TH RESPONDENT.

Exhibit P8 TRUE COPY OF THE STATEMENT DATED NIL WITH REGARD TO DIFFERENCE IN COST OF BITUMEN OF EXT.P6 WORK.

Exhibit P9 TRUE COPY OF REQUEST DATED 26.8.2021 SUBMITTED BY PETITIONER TO 6TH RESPONDENT.

Exhibit P10 TRUE COPY OF G.O.(RT) NO3815/2021/FIN.

DATED 30.4.2021 ISSUED BY 3RD RESPONDENT.

Exhibit P11 TRUE COPY OF G.O.(RT) NO.9386/2018/FIN.

DATED 13.11.2018 ISSUED BY 3RD RESPONDENT ALONG WITH TYPED COPY.

Exhibit P12 TRUE COPY OF G.O.(RT) NO.2816/2020/FIN.

DATED 17.4.2020 ISSUED BY 3RD RESPONDENT ALONG WITH TYPED COPY.

WP(C) NO. 22964 OF 2021 & con.cases 42

Exhibit P13 TRUE COPY OF G.O.(RT) NO.5502/2020/FIN.

DATED 25.9.2020 OF 3RD RESPONDENT ALONG WITH TYPED COPY.

Exhibit P14 TRUE COPY OF ORDER DATED 30.9.2021 IN WPC NO.15722 OF 2021.

 
Download the LatestLaws.com Mobile App
 
 
Latestlaws Newsletter
 

Publish Your Article

 

Campus Ambassador

 

Media Partner

 

Campus Buzz

 

LatestLaws Guest Court Correspondent

LatestLaws Guest Court Correspondent Apply Now!
 

LatestLaws.com presents: Lexidem Offline Internship Program, 2026

 

LatestLaws.com presents 'Lexidem Online Internship, 2026', Apply Now!

 
 

LatestLaws Partner Event : IJJ

 

LatestLaws Partner Event : Smt. Nirmala Devi Bam Memorial International Moot Court Competition

 
 
Latestlaws Newsletter